  1. Slide 1: Minas-Rio International Media Visit 2015

    IRON ORE BRAZIL MINAS-RIO INTERNATIONAL MEDIA VISIT - 2015 May, 2015

  2. Slide 2: Anglo American: The Diversified Miner

    ANGLO AMERICAN: THE DIVERSIFIED MINER Diversified across 10 product groups that span the development cycle Founded in 150,000 employees 1917 and contractors Key Headquarters Corporate & representative offices Iron Ore and Manganese Met and Thermal Coal Copper Nickel Niobium and Phosphates Operating

  3. Slide 3: Anglo American in Brazil

    ANGLO AMERICAN IN BRAZIL A long and successful partnership Nickel Exploration Office Nickel Niobium Iron Ore (Minas-Rio) More than Phosphates Iron ore export 40 years in terminal Brazil Brazilian corporate office Phosphates 3

  4. Slide 4: Brazil: Economic and Political Scenario

    BRAZIL: ECONOMIC AND POLITICAL SCENARIO A challenging set-up in spite of favourable conditions Selected indicators1 – % Brazil OECD Brazilian environment Modest growth due to tighter monetary and fiscal policies, weak external demand, low levels of investment and infrastructure bottlenecks; GDP Grow

  5. Slide 5: Minas-Rio: Safety as a Cornerstone of Performance

    MINAS-RIO: SAFETY AS A CORNERSTONE OF PERFORMANCE Benchmark Safety Performance = Leadership, Ownership and Accountability Man-Hours Total Recordable Cases High Potential Incidents Risk Change Management Worked = 170m (TRCFR) HPI = 127 RCM = 96% (million) 40 35 0.38 0.38 41 96% 26 28 0.31 0.23 85% 31

  6. Slide 6: Minas-Rio: Large Reserve & Resource Base

    MINAS-RIO: LARGE RESERVE & RESOURCE BASE Long-term value from a Tier 1 deposit with a fully integrated logistics • 2.8 Bt of Total Ore Reserves in addition to 2.6 Bt of Total Mineral Resources* • Easy to mine material due to geological formation • Low strip ratio over LOM ~0.4:1 and easily liberates

  7. Slide 7: Minas-Rio Overview

    MINAS-RIO OVERVIEW A fully integrated operational infrastructure – from mine to port BENEFICIATION PLANT MINE IRON ORE TERMINAL FILTRATION PLANT PIPELINE 7

  8. Slide 8: Minas-Rio Process

    MINAS-RIO PROCESS A fully integrated operational infrastructure – from mine to ship MINE PLANT PIPELINE FILTRATION IRON ORE TERMINAL • Life of mine is • One 230kV • The longest slurry • Filtration plant located • Dedicated iron ore estimated at 45 years transmission line pipeline in the world the Po

  9. Slide 9: Shipped First Ore on October 2014

    SHIPPED FIRST ORE ON 25 OCTOBER 2014 FOOS delivered safely and responsibly within revised plan and budget • First Ore on Ship two months ahead of schedule • Capital saving 0.4 billion - $8.4 billion • Ramp-up: 18 - 20 months post First Ore on Ship • 13 shipments to customers in China, India, Middle

  10. Slide 10: A Major Achievement

    A MAJOR ACHIEVEMENT Engineering complexity in an evolving environment 33 MUNICIPALITIES 170,000,000 man hours worked 35,600,000 m3 of earthworks ≈ ≈ 7 Burj Khalifa (Dubai) 2m PEOPLE - Tallest building in the world. 4,100 light vehicles + mobile equipments 4,000,000 km/month 32 FULLY FILLED WEMBLEYS

  11. Slide 11: Minas-Rio Video

    MINAS-RIO VIDEO First Ore on Ship delivered in line with revised plan Minas-Rio 11

  12. Slide 12: Competitive Operating Cost Position

    COMPETITIVE OPERATING COST POSITION Lower Half of the Cost Curve FOB Cash Cost (post ramp up) Global Iron Ore Cost Curve - 2016 ($/dmt, FOB) 1st 18 yrs. Avg. (Real 2014 Terms wmt) • Minas-Rio in the 2nd quartile of the cash cost curve Mine $10/t - $11/t 200 Beneficiation $9/t 150 Pipeline $2/t 100 F

  13. Slide 13: High Quality Pellet Feed Products

    HIGH QUALITY PELLET FEED PRODUCTS With the perfect fit for the evolving iron ore consumer market 0% 2% Minas-Rio • Increased market demand for high quality ore = Minas-Rio • Minas-Rio High quality pellet feed products Alumina + silica content 4% Brazil • Direct Reduction – ~68% Fe North America Othe

  14. Slide 14: The Focus Is Now on Safe Ramp-Up

    THE FOCUS IS NOW ON SAFE RAMP-UP World-class performance and strong risk management Delivered project at $8.4 billion capex Product Ramp-up (Mtpa - wet basis) & FOB Cash Cost 8.4 0.4 8.8 0.9 7.5 Product (mt) 26.5 24-26 FOB ($/ wmt) LTD 2015 / Total project Saving Previous ~$60/t Feb15 2016 estimate

  15. Slide 15: Stakeholder Support: Earning Our Social Licence

    STAKEHOLDER SUPPORT: EARNING OUR SOCIAL LICENCE Projects and initiatives focusing on the short, medium and long term requirements Education, Culture and Tourism Infrastructure and Access Health  Local labour programme  Professional Training  Senai  Pavement works  Historical building renovation

  16. Slide 16: Working Together

    WORKING TOGETHER There are no limits to what can be achieved if we truly work together OUR VALUES TOGETHER WITH THE COMMUNITY CREATING THE RIGHT ENVIRONMENT % of Total Workforce 100 19 81 • 474 students graduated to date 69 • All of them from local communities 31 • 347 (73%) hired by Anglo American

  17. Slide 17: Minas-Rio International Media Visit

    IRON ORE BRAZIL MINAS-RIO INTERNATIONAL MEDIA VISIT

  18. Slide 18: Appendix – Social Licence to Operate

    IRON ORE BRAZIL MINAS-RIO INTERNATIONAL MEDIA VISIT APPENDIX – Social Licence to Operate

  19. Slide 19: Community Development Programs

    COMMUNITY DEVELOPMENT PROGRAMS Local Supplier Development Program Local Labour Development Program - MOVER Building Blocks  Business development, financial support and  Prepare the local population for entry into the professional qualification since 2012; labour market;  516 local suppliers suppo

  20. Slide 20: Investment in Education

    INVESTMENT IN EDUCATION  30 information technology centres in Conceição do Mato Information Dentro, Alvorada de Minas, Dom Joaquin and Serro; Technology  More than 1600 people have benefited; Program  Partners: Milplan, CMDNet, Enesa, ARG.  9100 pupils and 910 teachers in 49 schools across 5 mun

  21. Slide 21: Investment in Culture and Infrastructure

    INVESTMENT IN CULTURE AND INFRASTRUCTURE Cultural tradition and Restorations Health Care  Support cultural tradition and preservation in Conceição do Mato Dentro and Serro;  Health care infrastructure in 3 municipalities:  Heritage education; • Contracting of health care professionals;  Qualific

  22. Slide 22: Investment in the Environment

    INVESTMENT IN THE ENVIRONMENT Fauna Monitoring and Flora Rescue Fire awareness and prevention  More than 950 fauna species were monitored;  Partnership with the State Forest Institute (IEF) aiming to reduce fire incidents in the Espinhaço region;  Production of more than 350,000 native seedlings

  23. Slide 23: Anglo American Brazil - Partner in the Future

    ANGLO AMERICAN BRAZIL - PARTNER IN THE FUTURE Four main initiatives with the objective of shared benefits IFC Best Practice Sharing ARPA For Life  Participation to IFC's Sustainability Exchange Forum  Investment of US$5 million - disbursement from December 2014  Unbundle social investments from o