KGL Resources Limited · ASX:KGL

KGL Resources — Kentor Gold — Investor Presentation (May 2011)

31 slides from KGL Resources's investor presentation, May 2011

  1. Slide 1: Kentor Gold Investor Presentation

    Slide 1: Kentor Gold Investor Presentation

    Kentor Gold May 2011 Investor Presentation

  2. Slide 2: Andash Project

    Slide 2: Andash Project

    ANDASH PROJECT Andash Project  1.6mtpa to 3.2mtpa throughput  Simple and conventional open pit and flotation plant  3 stage crush, grind, float process  Average annual production: – 70,000 oz Au and 7,400t Cu – High grade concentrate 24.5% Cu and 72 g/t Au  No deleterious elements  Initial min

  3. Slide 3: Project Economics (KGL 80%)

    Slide 3: Project Economics (KGL 80%)

    ANDASH PROJECT Project Economics (KGL 80%)  Cash cost US$29/oz Au Cost component Phase 1 Phase 2 (after Cu credits and royalty) (US$/t) (1.5mtpa) (3mtpa) Mining 3.46 3.46  Capital Cost US$96m Processing 8.62 7.09  Base Case NPV US$130m G&A 3.38 1.69 – US$1,000/oz Au & US$2.75/lb Cu Total 15.46 12

  4. Slide 4: Project Funding

    Slide 4: Project Funding

    ANDASH PROJECT Project Funding  Project Capital Cost US$96m  Macquarie Bank to provide project debt of US$50m  No compulsory hedging  Cash in the bank US$71m (end of March 2011) 4

  5. Slide 5: Andash and Aktash

    Slide 5: Andash and Aktash

    ANDASH PROJECT Andash and Aktash 5

  6. Slide 6: Andash

    Slide 6: Andash

    Andash  Fully funded through to production  Developing one of the world’s lowest cost gold mines  Growing the resource base  Negotiations with local community  12 month construction programme 6

  7. Slide 7: Jinka Minerals

    Slide 7: Jinka Minerals

    Jinka Minerals  Kentor Gold has taken over 94% of Jinka Minerals  Near term development of Gold and Copper Resources 7

  8. Slide 8: Location of Projects

    Slide 8: Location of Projects

    Location of Projects Burnakura (100%) 50km south of Meekatharra Gabanintha (100%) 45km southeast of Meekatharra Jervois (100%) 280km northeast of Alice Springs 8

  9. Slide 9: Key terms of offer

    Slide 9: Key terms of offer

    Key terms of offer  A$7.8m for all Jinka shares and options on issue  Repayment of Jinka loans of A$4.95m  All cash offer to be funded from existing cash reserves 9

  10. Slide 10: Murchison Projects

    Slide 10: Murchison Projects

    Murchison Projects Burnakura - Gabanintha • The Burnakura and Gananintha projects are within 20km of each other, approximately 750km NE of Perth and south of Meekatharra • Good access from Great Northern Hwy and Meekatharra-Sandstone Road • Planned work aimed at early conversion of mineralisation to

  11. Slide 11: Burnakura Gold Project - Summary

    Slide 11: Burnakura Gold Project - Summary

    Burnakura Gold Project - Summary • 100% interest • Located 50km south of Meekatharra, WA • 47.5 km2 gold prospective tenements of pre-1994 granted mining leases • Open pit historic production of 216,250 oz (1.8 million tonnes at 3.8 g/t) • Open pit production ceased in 1998 when the gold price fell

  12. Slide 12: Burnakura Project

    Slide 12: Burnakura Project

    fe _. Burnakura Project KENTOR GOLD LTD

  13. Slide 13: Burnakura Aerial View

    Slide 13: Burnakura Aerial View

    Burnakura Aerial View KENTOR GOLD LTD

  14. Slide 14: Burnakura NOA 7 and 8 Targets

    Slide 14: Burnakura NOA 7 and 8 Targets

    Burnakura NOA 7 and 8 TARGETS Cut-back and underground potential of existing pit Northern and down dip extensions of NOA8 Northernmost intersections are 6m @ 20.5g/t Au 14m @ 3.0g/t Au 8m @ 2.9¢/t Au KENTOR GOLD LTD

  15. Slide 15: Burnakura Authaal Targets

    Slide 15: Burnakura Authaal Targets

    Burnakura Authaal TARGETS Cutback and underground potential Intersections below the Authaal Central pit include 5m at 15.2g/t 4m at 18.0g/t 7m at 5.8g/t 6m at 21.5g/t 7m at 16.4g/t 3m at 23.8g/t. The deepest pit is Authaal South at ~50m depth. KENTOR GOLD LTD

  16. Slide 16: Gabanintha Copper-Gold Project

    Slide 16: Gabanintha Copper-Gold Project

    Gabanintha Copper-Gold Project TARGETS • Key prospect - Yagahong North Copper-Gold Deposit • Recent exploration success on adjacent tenements at Lady Alma and Copper Hills 16

  17. Slide 17: Gabanintha - Yagahong North

    Slide 17: Gabanintha - Yagahong North

    Gabanintha - Yagahong North  Yagahong North is located just north of the Yagahong open pit  Granted mining lease  Aim to delineate and quantify a JORC compliant resource.  Quality gold and copper drill results beneath and lateral to existing shallow pits  Trucking distance to Burnakura Plant fo

  18. Slide 18: Gabanintha - Yagahong North Section

    Slide 18: Gabanintha - Yagahong North Section

    Gabanintha - Yagahong North Section 18

  19. Slide 19: Gabanintha - Yagahong North Section

    Slide 19: Gabanintha - Yagahong North Section

    Gabanintha - Yagahong North Section 19

  20. Slide 20: Jervois Base Metals Project – Summary

    Slide 20: Jervois Base Metals Project – Summary

    Jervois Base Metals Project – Summary  100% Interest  Land holding 38km2  12km strike of prospective sequence  All tenements granted prior to introduction of Native Title legislation  Advanced multi-metal prospect with over $5 million incurred on past exploration 20

  21. Slide 21: Magnetics

    Slide 21: Magnetics

    7492000 7491000 y yaa Killeen Copper «\ 7 (SDA 1994 IGA Zone 53 JERVOIS PROJECT SAM - Magnetics " P LEGEND Prospect (1 tenure © Drill Collar 7491000 KENTOR GOLD LTD

  22. Slide 22: SAM Conductivity

    Slide 22: SAM Conductivity

    SAM Conductivity 629000 S 3 8 3 8 8 8 g § § x x JERVOIS PROJECT ‘SAM -EQMMR y S 2 8 8 8 8 3S S x x LEGEND Prospect Xockfac / ’ (Tenure , © Drill Collar - j A Rockhole / ( “it Cy ‘2. g a) i ‘ ti | y J. aaa oo mM 628 7 4 629000, Hales 630000 KENTOR GOLD LTD

  23. Slide 23: Jervois - Exploration

    Slide 23: Jervois - Exploration

    Jervois - Exploration Reward Longitudinal Section Bellbird Longitudinal Section 23

  24. Slide 24: Jervois

    Slide 24: Jervois

    A series of copper and lead-zinc- silver-copper deposits identified Bellbird and Marshall-Reward Copper deposits: 6,000 TPVM at]. 2.5% — 3.0% Cu Ore is free milling and concentrates easily Planned work aimed at defining } resources and reserves Recent down-hole MMR geophysical survey — targets ident

  25. Slide 25: Reward looking east

    Slide 25: Reward looking east

    Reward looking east KENTOR GOLD LTD

  26. Slide 26: Reward looking north

    Slide 26: Reward looking north

    Reward looking north KENTOR GOLD LTD

  27. Slide 27: Reward looking south

    Slide 27: Reward looking south

    Reward looking south

  28. Slide 28: Bellbird looking north

    Slide 28: Bellbird looking north

    Bellbird looking north

  29. Slide 29: Bellbird looking south

    Slide 29: Bellbird looking south

    Bellbird looking south

  30. Slide 30: Planned work programme

    Slide 30: Planned work programme

    Planned work programme • Delineate and quantify a JORC compliant resource at Gabanintha and Burnakura • Complete feasibility studies at Burnakura and Gabanintha for Open Pit extensions • Recommission the Burnakura Plant and possible increase in capacity • Complete infill drilling program at Jervois

  31. Slide 31: For more information contact

    Slide 31: For more information contact

    KEY CONTACTS For more information contact Simon Milroy on +61 7 31213206 ASX Code: KGL or visit www.kentorgold.com Level 36, Riparian Plaza, 71 Eagle St, Brisbane, QLD, AUSTRALIA 4000 Fax: +61 7 3121 3030 Forward-Looking Statements: Competent Persons Statement: This presentation includes certain “Fo