Electricity Generating Public Co., Ltd. · SET:EGCO

Electricity Generating Public — Q1 2007 Earnings Presentation

40 slides from Electricity Generating Public's earnings presentation, April 2007

  1. Slide 1: Corporate Presentation: Quarterly Financial Results Ended 31 March 2007

    Corporate Presentation Quarterly Financial Results Ended 31 March 2007 www.egco.com 1

  2. Slide 2: Disclaimer Statement

    Disclaimer Statement This presentation was made from the analysis of reliable information in order to assist investment community to better understand the company's financial status and operation. It also supports the "Good Corporate Governance Project" of the Securities and Exchange Commission (SEC

  3. Slide 3: Table of Contents

    Table of Contents • Rebranding • Thailand’s Electricity Industry Overview • EGCO Group’s Investment • Financial Results • Operating Performance (REGCO & KEGCO) www.egco.com 3

  4. Slide 4: Rebranding

    | est Rebranding Energy for life www.egco.com

  5. Slide 5: Changing of Company's Trading Symbol in SET

    Changing of Company’s Trading Symbol in SET “เราไมหยุดนิ่งที่จะรวมสราง พลังงาน...เพื่อชีวิต” www.egco.com 5

  6. Slide 6: Thailand's Electricity Industry Overview

    Thailand’s Electricity Industry Overview www.egco.com 6

  7. Slide 7: Current Electricity Supply Industry

    Current Electricity Supply Industry National Energy Policy Council is the MOE’s primary committee in setting NEPC the country’s energy policies to be proposed to Cabinet for approval. MOE Ministry of Energy • Energy Policy and Planning Office is responsible for studying and analyzing energy policies

  8. Slide 8: Historical Demand Growth

    Historical Demand Growth 22,586.10 MW or 7.23% increase MW (as at 24 April 2007) 23,000 21,064 MW or 2.57% increase 22,000 21,000 2007 20,000 2006 19,000 2005 18,000 2004 17,000 2003 16,000 2002 15,000 14,000 January Fe bru ar y M ar ch Apr il M ay Jun e July Au gust Se ptemb er Octo ber Nov ember D

  9. Slide 9: Thailand's New Capacity from 2006-2010

    Thailand’s New Capacity from 2006-2010 New Allocated Power Plants Share of New Capacity by Company from 2006 - 2010 EGCO EGAT Other Players MW 4,500 4,143 4,143 3,875 4,000 3,508 OTHERS 3,500 22% EGCO 21% 3,000 2,416 Jana# 1 2,500 700 MW South BKK#3 746 MW J POWER 2,000 Ratchaburi 9% 1,500 Power#1-2

  10. Slide 10: EGCO Group's Investment

    EGCO Group’s Investment • Corporate Portfolio • 2007 COD Projects • Projects under Construction • Future Projects www.egco.com 10

  11. Slide 11: Investment Map

    Investment Map Bolikhamxay IPP Saraburi Nam Theun 1 SPP Gulf-GCC Laos Khammouane Gulf-NKCC Nam Theun 2 Gulf-GPG (Kaeng Khoi 2) Roi-Et Thailand Roi-Et Green Samutprakarn Gulf-SCC Cambodia Rayong REGCO Nakorn Sri Thammarat Chonburi BLCP KEGCO AEP TLP Cogen Philippines APBP Yala Mindanao Island Malaysi

  12. Slide 12: EGCO Group Portfolio

    EGCO Group Portfolio www.egco.com 12

  13. Slide 13: EGCO: Group Structure

    EGCO : Group Structure 4,143.4 Majority Owned Equally or Minority Owned EGCO EGCO 2,156.6 MW 1,986.8 MW 1,232.0 7.0 824.0 93.6 717.0 26.4 49.6 267.5 926.3 50% 100% 50% 99.1 25% 50% 1,852.5 100% 100% 100% EGCO JD REGCO BLCP EGCO BVI NT2 GEC KEGCO ESCO 1,070.0 1,232.0 824.0 1,434.0 40% 66.0 29.7% 49.0

  14. Slide 14: EGCO Group's Investment: 2007 COD Projects

    EGCO Group’s Investment • Corporate Portfolio • 2007 COD Projects • Projects under Construction • Future Projects www.egco.com 14

  15. Slide 15: BLCP

    BLCP Location : Rayong, Thailand Technology : Coal fired Power Plant Installed Capacity : 1,434 MW (2 units of 717 MW each) Type of Fuel : Coal PPA : 25-year with EGAT COD : 1 October 2006 (unit #1) 1 February 2007 (unit #2) EPC Contractor : Mitsubishi Heavy Industries 50% 50% Banpu EGCO www.egco.co

  16. Slide 16: APBP-Expansion (Amata Power Bang Pakong Expansion)

    APBP-Expansion (The Amata Power Bang Pakong Exp.) Location : Chonburi, Thailand Technology : Gas Turbine Expansion Capacity : 55 MW Type of Fuel : Natural Gas PPA : Industrial User COD : 28 April 2007 EGCO JD, 30.00% Amata Power, 70.00% Amata Power EGCO JD www.egco.com 16

  17. Slide 17: GPG (Kaeng Khoi 2) Unit 1

    GPG (Kaeng Khoi 2) Location : Saraburi, Thailand Technology : Combined Cycle Power Plant Installed Capacity : 1,468 MW (Unit #1- 734 MW) Type of Fuel : Natural Gas PPA : 25-year with EGAT COD : 5 May 2007 (unit #1) EGCO Mitpower (Thailand) 50% 1% . J. Pow er 49% J. Power EGCO Mitpower (Thailand) www

  18. Slide 18: EGCO Group's Investment: Projects under Construction

    EGCO Group’s Investment • Corporate Portfolio • 2007 COD Projects • Projects under Construction • Future Projects www.egco.com 18

  19. Slide 19: GPG (Kaeng Khoi 2) Unit 2

    GPG (Kaeng Khoi 2) Location : Saraburi, Thailand Technology : Combined Cycle Power Plant Installed Capacity : 1,468 MW (Unit #2 - 734 MW) Type of Fuel : Natural Gas PPA : 25-year with EGAT COD : 1 March 2008 (unit #2) EGCO Mitpower (Thailand) 50% 1% . J. Pow er 49% J. Power EGCO Mitpower (Thailand)

  20. Slide 20: Nam Theun 2

    Nam Theun 2 Location : Khammouane, Laos Technology : Hydroelectric Power Plant Installed Capacity : 1,070 MW Contracted capacity to EGAT : 920-995 MW Type of Fuel : Hydro PPA : 25-year with EGAT COD : November 2009 Project Progress : Construction phase EGCO LHSE* 25% 25% ITD 15% EDFI 35% EDFI EGCO L

  21. Slide 21: EGCO Group's Investment: Future Projects

    EGCO Group’s Investment • Corporate Portfolio • 2007 COD Projects • Projects under Construction • Future Projects www.egco.com 21

  22. Slide 22: IPP Bidding Expected Capacity

    IPP Bidding Expected Capacity MW Allocated to EGAT 2,100 Available for IPP bidding 3,000 2012-2014 Purchases from Neighboring countries 963 Total 6,063 MW Allocated to EGAT 4,200 Available for IPP bidding 4,200 2015-2017 Purchases from Neighboring countries 1,370 Total 9,770 www.egco.com 22

  23. Slide 23: Nam Theun 1 Project

    Nam Theun 1 Project Location : Bolikhamxay, Laos Technology : Hydroelectric Power Plant Installed Capacity : 523 MW Type of Fuel : Hydro COD : 2013 Laos 20 % EGCO 40 % Project Progress EGCO signed Tariff MoU with EGAT Gamuda 40 % www.egco.com 23

  24. Slide 24: Wind Power Project

    Wind – Power Project Location : The Southern coast of Thailand Capacity : 30-35 MW Feasibility Study : 18 Months Cost of Project : 1,800 MM Baht Eurus 20 % EGCO 30 % Project Progress EGCO signed MoU with PTT, WEGCO and EURUS conduct a feasibility study WEGCO 20 % PTT 30 % www.egco.com 24

  25. Slide 25: LNG Receiving Terminal Project

    LNG Receiving Terminal Project Location : Rayong, Thailand Capacity : Phase 1 - 5 MTA Phase 2 - 10 MTA COD : 2011 EGCO 20 % Project Progress PTT 50% EGCO signed MoU with EGAT and PTT conduct a feasibility study LNG Receiving Terminal EGAT 30% Note: Tentative por tion for investment www.egco.com 25

  26. Slide 26: Financial Results

    Financial Results www.egco.com 26

  27. Slide 27: Operating Results - Net Profit and EBITDA

    Operating Results - Net Profit and EBITDA Ended 31 March, 2007 and 2006 MM baht 1Q07 1Q06 3,355 2,824 2,538 2,070 388 64 -191 -163 -337 -286 -528 -520 EBITDA Interest Tax Depre & Amort Fx Gain (Loss) Net Profit after Fx, Tax www.egco.com 27

  28. Slide 28: Segmental Operating Results Ended March 31, 2007

    Segmental Operating Results Ended March 31, 2007 MM baht www.egco.com 28

  29. Slide 29: Segmental Operating Results Ended March 31, 2006

    Segmental Operating Results Ended March 31, 2006 MM baht www.egco.com 29

  30. Slide 30: Cashflow Ended March 31, 2007 and 2006

    Cashflow Ended March 31, 2007 and 2006 MM baht www.egco.com 30

  31. Slide 31: Summary of Debt Structure

    Summary of Debt Structure Total Facilities Total Outstanding Balances 31 March 2007 USD 192 M. USD 61 M. JPY 1,260 M. JPY 921 M. Baht 20,287 M. Baht 12,743 M. • Total facilities and total outstanding balances of EGCO Group (Not in EGCO’ s portion) • Total outstanding balances in Baht and Baht equiva

  32. Slide 32: Financial Ratio Highlights

    Financial Ratio Highlights www.egco.com 32

  33. Slide 33: Dividend Policy

    Dividend Policy Baht/Share 4.5 4.00 4 3.5 3.25 3.00 3 2.75 2.00 2.50 2.5 2.25 1.75 2.00 2.00 2.00 1.50 2 1.50 1.25 1.5 1.25 1.27 1.00 1 2.00 1.25 1.25 1.50 1.50 0.5 - 1.00 0 Year 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 Annual Dividend Interim Final In the absence of unforeseen ci

  34. Slide 34: Operating Performance (REGCO & KEGCO)

    Operating Performance (REGCO & KEGCO) www.egco.com 34

  35. Slide 35: Annual Net Generation & Electricity Sales 2002-2006

    Annual Net Generation & Electricity Sales for the Year 2002-2006 Net Generation Electricity Sales Million Baht GWh 7,269 6,201 6,133 6,393 6,274 5,975 5,947 5,811 5,837 5,528 5,448 5,392 5,273 5,349 5,039 4,605 4,358 4,339 4,224 3,796 2002 2003 2004 2005 2006 2002 2003 2004 2005 2006 REGCO KEGCO • E

  36. Slide 36: Major Maintenance Expenses for the Year 2007

    Major Maintenance Expenses for the Year 2007 Million Baht REGCO Quarter 1 2 3 4 Total Actual Budget Budget Budget Spare Parts 68.98 26.94 23.70 57.88 177.50 Service Charge 52.39 26.48 70.65 93.60 243.12 Total 121.37 53.42 94.35 151.48 420.62 KEGCO Quarter 1 2 3 4 Total Actual Budget Budget Budget Sp

  37. Slide 37: Major Maintenance Expenses for the Year 2006

    Major Maintenance Expenses for the Year 2006 Million Baht REGCO Quarter 1 2 3 4 Total Actual Actual Actual Actual Spare Parts 37.67 36.04 34.22 43.15 151.08 Service Charge 37.72 26.15 78.28 21.11 163.26 Total 75.39 62.19 112.50 64.26 314.34 KEGCO Quarter 1 2 3 4 Total Actual Actual Actual Actual Spa

  38. Slide 38: Operating Performance Equivalent Availability Factor

    Operating Performance Equivalent Availability Factor For the 1st Quarter of 2007 and 2006 REGCO 1Q07 1Q06 Plant Type Target EAF (%) Actual EAF (%) Target EAF (%) Actual EAF (%) CCGT #1 99.68 99.87 88.48 89.45 CCGT #2 98.81 98.13 98.55 98.75 CCGT #3 97.94 99.63 97.68 98.91 CCGT #4 71.33 74.53 84.66 8

  39. Slide 39: Net Generation and Fuel Consumption

    Net Generation and Fuel Consumption For the 1st Quarter of 2007 and 2006 R EG C O CCG T #1- 4 1Q 07 1Q 06 N e t G e ne ra tion - B y N a tura l G a s (G Wh ) 812 1 ,7 2 0 - B y S e c o nd a ry F ue l (G W h ) 0.34 0 .4 9 F ue l C o n s um ptio n - B y N a tura l G a s (M M B TU ) 6 ,969, 558 14,487,

  40. Slide 40: Q & A

    | eat O&A Energy for life www.egco.com 40