    Antofagasta plc 2020 FY Results Mauricio Ortiz Chief Financial Officer 16th March 2021 Developing mining for a better future

  2. Slide 2: Cautionary statement

    Cautionary statement This presentation has been prepared by Antofagasta plc. By reviewing and/or attending this presentation you agree to the following conditions: This presentation contains forward-looking statements. All statements other than historical facts are forward-looking statements. Exampl

  3. Slide 3: Agenda

    Agenda 1 Overview 2 Financial review 3 Growth opportunities and investment case 3

  4. Slide 4: Overview

    Overview 4

  5. Slide 5: 2020 highlights: Strong EBITDA margin and balance sheet

    2020 highlights Strong EBITDA margin and balance sheet Safety Financial results Balance sheet and dividend Record year of safety EBITDA: $2,739m Net debt of $82m performance EBITDA margin2: 53% Net debt/EBITDA of 0.03x No fatal accidents LTIFR1: 0.86 EPS3: 54.7 c/share Final dividend 48.5 c/share Co

  6. Slide 6: COVID-19 response and recovery

    COVID-19 response and recovery Focus on protecting our people and local communities COVID-19 situation in Chile Impact on operations Antofagasta’s response ▪ Some local lockdowns still in place ▪ All sites have kept operating throughout ▪ Focus on protecting our people and local ▪ Health system has

  7. Slide 7: Sustainability

    Sustainability Short-term emission and water usage targets Water efficiency and transition to sea water Approved Climate Change Strategy ▪ Centinela and Antucoya use raw sea water ▪ 5 Pillars, including energy and water transitions ▪ Currently building a 400 l/s desalination plant at Los ▪ Committed

  8. Slide 8: 2021 guidance

    2021 guidance Copper production (kt) Copper production Guidance1 • Guidance 730-760,000t 770 730-760 • Higher production as ore grades increase at 725 734 Antucoya & 130 Centinela Concentrates 120 140 125 Zaldívar Cash costs Centinela 248 277 247 275 • Cash costs before by-products of $1.65/lb • Net

  9. Slide 9: Copper market

    Copper market Short term Copper price and exchange stocks ▪ Synchronised global government stimulus through monetary and Thousand c/lb Tonnes fiscal incentives, led initially by China ▪ Cyclical recovery following pandemic’s impact on supply & demand 500 1,000 ▪ Record net long financial positions f

  10. Slide 10: Financial review

    ANTOFAGASTA PLC a lls.

  11. Slide 11: 2020 financial highlights

    2020 financial highlights Strong EBITDA margin and balance sheet Revenue Net cash cost EBITDA $1.14/lb EBITDA: $2,739m 6.6% lower than in 2019 12% higher than last year $5,129m 3.3% higher than in 2019 $197m EBITDA margin2: 53% Savings from CCP1 Increased from 49% in 2019 Underlying earnings per sha

  12. Slide 12: Operational performance

    Operational performance Guidance achieved: 733,900 tonnes at $1.14/lb Los Pelambres Centinela Antucoya Zaldívar Transport Cu production Cu production Cu production Cu production1 Tonnage 359,600 t 246,800 t 79,300 t 48,200 t transported Net cash costs Net cash costs Cash costs Cash costs 6,444 kt $0

  13. Slide 13: Production and cash costs

    Production and cash costs (36) 770 Copper 19 Production 734 (6) (3) (1) kt (45) Copper Grade Throughput Recovery Work-in-progress ROM Copper 2019 FY inventories and others 2020 FY (0.09) 1.65 0.08 0.01 1.56 Cash costs (0.05) (0.05) (0.09) by cost type 1.14 (0.42) $/lb Pre-credit FX & Input Lower Gra

  14. Slide 14: EBITDA

    EBITDA EBITDA1 and margin2 2019 FY versus 2020 FY $ million and % 49% 53% $300m (+12%) 26 7 133 3 $2,739m (44) 383 $2,439m (208) 2019 FY Sales volumes Realised Mining costs Exploration Corporate Associates Transport 2020 FY EBITDA and TC/RCs prices & evaluation costs & JVs division EBITDA 1 Results

  15. Slide 15: Balance sheet

    Balance sheet Net cash / (debt) and Net debt/EBITDA ratio $ million and times $481m 2,647 (216) (320) 0.23x 0.03x ratio1 ratio1 210 $312m $34m (1,307) (40) (81) (411) $(82)m $(563)m Net cash (debt) - Net cash EBITDA from Working Tax Capex Net interest Others and Subordinated Dividends Net cash Net c

  16. Slide 16: Capital allocation drives decision making

    Capital allocation drives decision making 2020 Operating Cash Flow1 $2,431m Copper • Stress test forecasts at various copper prices Price Free Sustaining Capex & Mine Development $748m • Future free cash flow generation Cash • Cash buffer Flow DECISION Committed Dividends (35% pay-out) $189m FACTORS

  17. Slide 17: Capital expenditure

    Capital expenditure Guidance $1.6bn Capital expenditure1 $ million $1,307m $1,079m 890 Growth $899m 571 $873m 279 144 61 276 68 37 70 Transport & corporate 32 392 341 221 310 265 Mining sustaining 371 352 347 357 375 Mine development 2017 2018 2019 2020 2021E Sustaining ratio 2017 2018 2019 2020 202

  18. Slide 18: Growth opportunities and investment case

    Growth opportunities and investment case 18

  19. Slide 19: Growth opportunities

    Growth opportunities 2020 2021 2022 2023 2024+ LOS PELAMBRES EXPANSION - PHASE 1 (in construction) PHASE 2 (in FS stage) Cu +60 ktpa | Capex $1.7 bn1 (including desalination plant) Cu +35 ktpa | Capex $0.5 bn2 15 year LOM extension Organic ESPERANZA SUR PIT (in construction) CENTINELA 2ND CONCENTRAT

  20. Slide 20: Los Pelambres Expansion - Phase I

    Los Pelambres Expansion - Phase I 60,000 tonnes1 of additional copper • Optimise throughput within the limits of the existing operating, environmental and water extraction permits • Increasing plant capacity from 175ktpd to 190ktpd • Annual copper production will increase by an average of 60,000 ton

  21. Slide 21: Centinela's Esperanza Sur pit

    Centinela´s Esperanza Sur pit 10-15,000 tonnes of additional copper • Will improve Centinela’s flexibility to supply its concentrator • Over the initial years, the higher grade material from the pit will increase copper production by 10–15,000tpa • Once pre-stripping is completed, autonomous trucks

  22. Slide 22: Zaldívar Chloride Leach

    Zaldívar Chloride Leach 10-15,000 tonnes of additional copper • Increase copper recoveries by approximately 10 percentage points • Upgrade SX plant, new reagents facilities and additional washing ponds • Project completion planned for H1 2022 • $190 million capital cost unchanged 22

  23. Slide 23: Transformational innovation - key to strategy

    Transformational innovation - key to strategy Integrated Remote Operations Centre ▪ Primary sulphides leach (Cuprochlor-T®) industrial scale (IROC) in the city of Strategic testing underway Antofagasta for Centinela Initiatives ▪ Low cost bulk material movement technologies ▪ Thickened tailings and

  24. Slide 24: Our priorities for 2021 and beyond

    Our priorities for 2021 and beyond Continuing our record of zero fatalities and protecting employees and communities from COVID-19 Embed climate change and sustainability strategy across all decision making and update climate change targets Maintaining operating resilience and flexibility Continuous

  25. Slide 25: Investment case: Responsible copper producer

    Investment case Responsible copper producer Sustainability High quality assets Operating efficiency Financial position ▪ Zero fatalities culture ▪ Strong and growing ▪ Constant focus on unit costs ▪ Strong balance sheet ▪ Safety and health model production ▪ Continuous productivity ▪ Healthy cash fl

  26. Slide 26: Appendix

    . ANTOFAGASTA PLC » Appendix

  27. Slide 27: Revenue

    Revenue Revenue 2019 FY versus 2020 FY1 $ million $164m 348 70 $5,129m (153) (11) $4,965m (90) 2019 FY Copper price Copper sales By-products TC/RC Transport division 2020 FY 1 Excludes Zaldívar (JV) 27

  28. Slide 28: Net earnings

    Net earnings Net earnings 2019 FY versus 2020 FY $ million $38m 344 (128) (19) (52) (40) $539m $506m $501m (67) (36) 2019 FY EBITDA from Depreciation Associates Net Tax Non-controlling 2020 FY Exceptional 2020 FY Net earnings subsidiaries and and JVs finance costs interests Net earnings items and Ne

  29. Slide 29: Cash flow

    Cash flow Cash flow in 2020 FY1 $ million $1,480m 2,647 (216) 210 (320) 918 $3,673m (411) (1) (1,307) (40) $2,193m Cash at EBITDA from Working Tax Capex Net Net Capital Dividends Others Cash at 1 Jan 2020 subsidiaries capital1 interest borrowings increase 31 Dec 2020 (Marubeni) 1 Excludes Zaldívar (

  30. Slide 30: 2020 FY production cost breakdown

    2020 FY production cost breakdown 0.31 $1.67/lb Others 0.42 $1.56/lb Energy 7% 12% Other inputs 8% (0.20) Sulphuric acid 4% 14% Labour $1.14/lb Fuel and Lubricants 5% $2,705m Materials and spare parts 14% 17% Services 14% Net cash costs By-products Pre-credit TC/RC & Mine Production costs Maintenanc

  31. Slide 31: Production and metals prices

    Production and metals prices Group production Metal prices 2017 2018 2019 2020 2021E1 2017 2018 2019 2020 Copper ('000 tonnes) Copper ($/lb) Los Pelambres 343.8 357.8 363.4 359.6 340-350 Realised 3.00 2.81 2.75 2.98 Centinela Concentrates 163.9 155.5 195.5 153.5 LME 2.80 2.96 2.72 2.80 270-280 Centi

  32. Slide 32: Unit cash costs

    Unit cash costs Group cash costs 2017 2018 2019 2020 2021E1 Group cash costs ($/lb) Los Pelambres 1.44 1.52 1.40 1.27 1.45 Centinela 1.81 1.89 1.83 1.85 1.75 Antucoya 1.68 1.99 2.17 1.82 1.80 Zaldívar2 1.62 1.94 1.75 1.80 1.75 Cash costs before by-products credits ($/lb) 1.60 1.72 1.65 1.56 1.65 By-

  33. Slide 33: Antofagasta contacts

    Antofagasta contacts Andrew Lindsay alindsay@antofagasta.co.uk Andrés Vergara avergara@antofagasta.co.uk Director, London Office Tel: +44 20 7808 0988 Investor Relations Manager Tel: +44 20 7808 0988 33

  34. Slide 34: www.antofagasta.co.uk