    For personal use only Diggers & Dealers Presentation 2022 Executing the strategy:  Leveraging our competitive advantages  2 years of consistent project delivery  De risking on our pathway to first gold and cashflow in 2H 2023 2 August 2022 ASX:BGL 1 ASX300

  2. Slide 2: Disclaimers & Compliance Statements

    Disclaimers & Compliance Statements This Presentation has been prepared by Bellevue Gold Limited (Company) and is authorised by the Managing Director of Bellevue Gold Limited. For personal use only DISCLAIMER This Presentation has been prepared by the Company based on information from its own and th

  3. Slide 3: Disclaimers & Compliance Statements cont.

    Disclaimers & Compliance Statements cont. For personal use only JORC COMPLIANCE STATEMENTS It is a requirement of the ASX Listing Rules that the reporting of Ore Reserves and Mineral Resources in Australia comply with the Joint Ore Reserves Committee’s Australasian Code for Reporting of Mineral Reso

  4. Slide 4: BGL Investor Video Diggers 2022

    BGL Investor Video Diggers 2022 Play here For personal use only 4 https://bellevuegold.wistia.com/medias/489a38jtwu

  5. Slide 5: Bellevue Gold Overview

    Bellevue Gold Overview The “Standout” high-grade, high margin growth gold project in Australia For personal use only  Project has significant grade, scale and margin in a tier one jurisdiction  Significant and proven growth potential vs peer group  Forecast +10yr mine life producing over 200,000

  6. Slide 6: De-risking towards production

    De-risking towards production  Project is fully funded to production with $317.5m in liquidity (as at 30 June 2022) For personal use only  Project is now 62% complete from commencement of development phase (from portal to first production) which commenced in July 2020  Pre-production expenditure

  7. Slide 7: Sustainability is core to BGL's vision and purpose

    Sustainability is core to BGL’s vision and purpose Vision To be a sustainable gold mining company that enriches our shareholders, community and people For personal use only Purpose To create a high-performance organisation that delivers superior shareholder value, positive ESG outcomes and an enviro

  8. Slide 8: Growing in a world class mining jurisdiction

    Growing in a world class mining jurisdiction For personal use only Host to > 200Moz of gold endowment in a tier 1 location  West Australia globally recognised tier 1 mining jurisdiction, ranked #1 on the Fraser BELLEVUE GOLD PROJECT Index 2021 for Mining Attractiveness 3.9Moz Endowment Agnew/Wiluna

  9. Slide 9: Quality ore body with excellent grade and width

    Quality ore body with excellent grade and width 3.1moz @ 9.9g/t gold Resource inventory remains open for growth For personal use only Historic Mine- 500m 800,000 ounces @ 10.0m @ 15.4g/t gold Long Section looking east through the Bellevue Lode System 5.0m @ 31.6g/t gold 2.8m @ 46.9g/t gold +11 g/t m

  10. Slide 10: Continued organic resource growth set to deliver further outperformance

    Continued organic resource growth set to deliver further outperformance For personal use only  Since the discovery hole in November 2017, the Resource has grown at a compound annual growth rate of 63%  The Reserve has grown at a compound annual growth rate of 68% since February 2021  Reserve conv

  11. Slide 11: 10-year mine life with organic growth potential

    10-year mine life with organic growth potential  Multiple opportunities for organic growth: 1. Nameplate 1Mtpa- crushing circuit has been designed to process higher throughput rates than 1Mtpa For personal use only 2. Resource conversion - another 40% of the Resource sits outside the current mine p

  12. Slide 12: Mining - capitalising on our head start

    Mining - capitalising on our head start Then Now Future For personal use only  Portal – commenced August 2020   Stage 2 development commenced   Two production centres (North & South)  5.1km of development completed   Mining contractor Develop started 24 May 2022  >5 independent production f

  13. Slide 13: Record development and first ore heading

    Record development and first ore heading For personal use only Development intersects first ore First Ore July 2022  First high-grade Armand lode intersected  The first of 5 independent mining areas to be accessed for commercial production  Multiple production fronts will allow for maximum flexib

  14. Slide 14: Mining - key pillars in place

    Mining - key pillars in place 1 2 Robust Ground Conditions For personal use only Significant Headstart 10 available headings – increased jumbo productivity Mesh & Bolts only 3 Installed Infrastructure Future proof with a focus on emissions reduction 4 Tier 1 Contractor Elite underground mining team

  15. Slide 15: Processing – Infrastructure allows for growth

    Processing – Infrastructure allows for growth For personal use only Current  Simple layout and orientation - 1Mtpa nameplate  Simple metallurgy – 97% total recovery, including >60% gravity recovery  Simple flowsheet – tried and tested  Tier-1 contractor – GR Engineering Services  Construction c

  16. Slide 16: Camp construction now 75% complete

    Camp construction now 75% complete  The camp is now 75% complete with all 339 rooms landed and 120 rooms complete  Two 14.9Kw solar arrays have been installed to power the borefield pumps; the pumps will be run For personal use only at 100% solar power during daylight hours 16

  17. Slide 17: Consistently delivering since July 2020

    Consistently delivering since July 2020  The company is continually delivering on time and on budget; this will drive a further re-rate as we move closer to cashflow For personal use only  Project execution is significantly de-risked to cost escalation with 90% of the project capital committed; ti

  18. Slide 18: Significant re-rate potential as a future high grade, high margin producer

    Significant re-rate potential as a future high grade, high margin producer For personal use only • Gold companies that recently transitioned into production have experienced significant outperformance as the project is de-risked • BGL positioned as a high grade, high margin business with growth pote

  19. Slide 19: Investment Highlights

    Investment Highlights For personal use only World class potential Resource Growth Production Growth ESG Leader De-risking Forecast to be a Since the discovery Project mine life Project is forecast 62% through top 20 Australian hole in November has grown 25% to to have the lowest development timeline