Pt Vale Indonesia Tbk · IDX:INCO
Pt Vale Indonesia Tbk — Q2 2026 Earnings Presentation
16 slides from Pt Vale Indonesia Tbk's earnings presentation, Sep 5, 2026
Slide 1: Continued Growth and Progress Toward a Stronger Baseline
Public Information PT Vale Indonesia Tbk Continued Growth and Progress Toward a Stronger Baseline 2Q26 Results Presentation Material
Slide 2: Table of content
Table of content: 1. 2Q26 Financial Update 2. Operational Update 3. Growth Projects Update 4. 2H26 Strategic Direction
Slide 3: Cautionary Note & Disclaimer
Cautionary Note & Disclaimer Cautionary Note on Forward-looking Statements This presentation may contain statements regarding the business of PT Vale Indonesia Tbk (the “Company” or “PT Vale”) that are of a forward- looking nature and are therefore based on management's assumptions about future deve
Slide 4: 2Q26 Financial Update
2Q26 Financial Update PT Vale continues to build its operational foundation for long-term growth
Slide 5: Strong Q2 performance. Delivered higher production volume to capitalize favorable nickel price momentum
Strong Q2 performance. Delivered higher production volume to capitalize favorable nickel price momentum Production and Sales o Nickel matte production and deliveries totaled each 16,153 tons and 13,932 tons, reflecting stronger operational performance upon the completion of Furnace 3 Rebuild project
Slide 6: 1H26 Key Financial Highlights
1H26 Key Financial Highlights Strong financial performance through higher production volume, to capitalize the momentum of stronger nickel prices
Slide 7: Operational Update
Operational Update Stronger operational performance upon the completion of Furnace 3 Rebuild project in June
Slide 8: Among the safest operators in global mining
Among the safest operators in global mining PT Vale's recordable injury rate is 78% below the ICMM peer-group average and still improving.. Recordable injury rate 2025 — PTVI vs 24 ICMM member companies Alcoa 8.25 Boliden 7.80 BHP 4.48 Sibanye-Stillwater 3.78 South32 3.26 Teck 2.76 Freeport-McMoRan
Slide 9: The Company continues to build on its growth platform across its three mining blocks
The Company continues to build on its growth platform across its three mining in Sorowako, Bahodopi, and Pomalaa 9
Slide 10: Growth Projects Update
Growth Projects Update The strong performance from both growth projects highlights the successful ramp-up of operations
Slide 11: Indonesia Growth Project (IGP) Performance
Indonesia Growth Project (IGP) Performance PT Vale strategic investment program in mining and down streaming processing Mine HPAL - JV Project Value Production Progress Timeline Production Ownership Progress Partner Timeline 100% 5.5 Mio phase 1 FIDa Milestone 36% Construction phase 2 – 28% Sapro 3Q
Slide 12: Three growth projects in our pipeline are making progress
Three growth projects in our pipeline are making progress 12
Slide 13: 2H26 Strategic Direction
2H26 Strategic Direction Driving Growth, Discipline, and Profitability
Slide 14: 2nd Half key priorities – delivering growth with persistency and discipline
2nd Half key priorities – delivering growth with persistency and discipline Production and Sales o Additional RKAB approvals secured, reinforcing production continuity and growth visibility. o Higher nickel in matte production, with further upside anticipated following the Furnace 3 Rebuild completi
Slide 15: Shaping a brighter future through responsible mining
“Shaping a brighter future through responsible mining, where progress and care go hand in hand” Matano Lake, Sorowako
Slide 16: Contact us
Contact us Investor Relations PT Vale Indonesia Tbk Phone: +62 21 524 9000 Web: www.vale.com/indonesia Email: ptvi.investorrelation@vale.com