Slide 1: PT Nusantara Infrastructure Tbk. Public Expose
PT Nusantara Infrastructure Tbk. Public Expose Jakarta, 15 December 2016 © 2016 PT Nusantara Infrastructure Tbk 1
Slide 2: Presentation Contents
Presentation Contents PART I : Company Overview 3 PART II : Key Development Progress 7 PART III : Financial Highlights 24 www.nusantarainfrastructure.com © 2016 PT Nusantara Infrastructure Tbk 2
Slide 3: PART I: Company Overview
PART I: Company Overview © 2016 PT Nusantara Infrastructure Tbk 3
Slide 4: Company Overview
Company Overview Founded through backdoor listing in 2006, PT Nusantara Infrastructure Tbk. is an Indonesia’s leading private infrastructure company. PT Nusantara Infrastructure Tbk. is listed at the Indonesia Stock Exchange (Ticker: META). The company manages diversified infrastructure sector
Slide 5: Geographical Coverage
Geographical Coverage The company currently serves over 103 million customers, 550,000 households, 266 factories and 210 vessels, 1,486 telecommunication tenancies. Harbor Road - Makassar Commuter Road – Greater Jakarta Toll Roads Airport Toll Road - Makassar Jakarta International Airport
Slide 6: Shareholding Structure
Shareholding Structure PT Hijau Makmur Eagle Infrastructure Public and Others Sejahtera 21.00% 22.32% 56.68% 74.98% 99.99% 99.99% 99.99% 99.99% PT Margautama PT Portco PT Potum Mundi PT Energi PT Telekom Nusantara Infranusantara Infranusantara Infranusantara Infranusantara (“MUN”) (“Portco”) (“POTUM
Slide 7: Corporate Structure
Corporate Structure 74.99% 99.99% 99.99% 99.99% 99.99% Cap Asia Partnered Partnered Partnered with invested in 2013 with LDC in 2012 with PTPP in PEP in 2014 Partnered with 2012 JEXWAY in 2014 88.93% 98.53% 25.00% 39.00% 51.00% 51.00% 64.99% 54.64% 79.64% BSD BMN JLB ISAB TBN DCC SCTK IME KIN Acquir
Slide 8: PART II: Key Development Progress
PART II: Key Development Progress © 2016 PT Nusantara Infrastructure Tbk 8
Slide 9: Toll Road
Toll Road © 2016 PT Nusantara Infrastructure Tbk 9
Slide 10: Selected Map of Makassar City and List of Key Projects
Selected Map of Makassar City and List of Key Projects Sultan Hasanuddin Airport 2 Airport Toll Road - Makassar New Makassar Port 1 3 Old Makassar Port Harbor Road - Makassar Legend: : Airport Toll Road : Harbor Road Number 1 : Tallo Bridge Area Number 2 : Frontage Road Area Number 3 : TIS
Slide 11: 1. Tallo Bridge Expansion
1. Tallo Bridge Expansion Before Expansion After Expansion The project was started in July 2015 and completed within 12 months work plan, just before the Lebaran holidays. The expansion has reduced bottleneck condition resulting greater access of mobility to users. The toll road is connecting
Slide 12: 2. Frontage Road Reconstruction
2. Frontage Road Reconstruction Before Reconstruction After Reconstruction The project was initiated together with Tallo Bridge expansion and has been completed since June 2016. Frontage road is located alongside of Airport Toll Road in Makassar with length of 10.00 Km. It serves as arterial roa
Slide 13: 3. Traffic Information System
3. Traffic Information System Project Concept CCTV placed on spots Capturing & Collecting Data Information generated in Information generated for 1 capturing real time traffic 2 and Create Output. 3 Control Center. 4 public via Videtron/Gadget. IVA SYSTEM Probe Information Inter Face Probe Data Proc
Slide 14: Renewable Energy
Renewable Energy © 2016 PT Nusantara Infrastructure Tbk 14
Slide 15: Renewable Energy Sector
Renewable Energy Sector Currently constructing a Mini Hydro Power Plant, 2 x 5 MW capacity located in North Sumatera. The project has a 20 year contract with PLN (Power Purchase Agreement). First operation is expected to start by 3Q-2018 (third quarter year 2018). The company is partnering w
Slide 16: Project Progress
Project Progress Development Progress – Upstream Area A B C (A) Inlet Tunnel (B) Deterrent Drainage (C) Bekisting Work at Penstock Development Progress – Downstream Area A B C (A) Power House Zone (B) Shotcrete Ramp Power House (B) Tailrace Zone Overall progress has reached 22.0% and scheduled to
Slide 17: Port
Port © 2016 PT Nusantara Infrastructure Tbk 17
Slide 18: Port Sector Development
Port Sector Development Development of Biodiesel Plant Opening Ceremonial Photo As per completion of Biodiesel Plant, from May to November 2016, ISAB has served more than 76,000 tons distribution of biodiesel supply for state-owned oil and gas company Pertamina. The Biodiesel Plant has annual pr
Slide 19: Location Map of Lampung Port
Location Map of Lampung Port Lampung Port - Liquid Area 4 3 Lampung Port - Dry Area 1 2 Legend: PELINDO : Lampung Port Area Port Number 1 : Jetty Area Number 2 : Warehouse Area Number 3 : Liquid Tank Farm Area Number 4 : Biodiesel Plant Up to November 2016, number of vessels has increase
Slide 20: Water
Water © 2016 PT Nusantara Infrastructure Tbk 20
Slide 21: Water Sector Project Progress
Water Sector Project Progress Current Plant Expansion Plant (In Progress) A B (B) New Reservoir Tanks (2 x 3,000 m3) (A) Water Treatment Plant 1 & 2: Capacity 2 x 50 lps (Total 100 lps) C Expansion Plant of East Serang Water Treatment Plant has reached finalization stage. It is expected that the
Slide 22: Telecommunication Tower Sector
Telecommunication Tower Sector © 2016 PT Nusantara Infrastructure Tbk 22
Slide 23: Summary Chart KIN Tower Evolution 2014 – 3Q-16
Summary Chart KIN Tower Evolution 2014 – 3Q-16 Size Growth +4.2x in 2.5 years period 1,024 72 51 3 M&A transactions 901 (portfolio size ~10 – 230 156 towers per acquisition) 80 368 591 In closing process of new portfolio acquisition for more 5 M&A transactions than 180 microcell (portfolio size ~20
Slide 24: PART III: Financial Highlights
PART III: Financial Highlights © 2016 PT Nusantara Infrastructure Tbk 24
Slide 25: Revenues Growth
Revenues Growth NI Consolidated Revenues(1) Trend 2012 – 3Q-16 IDR Billion; unless otherwise stated CAGR 3 Years 1Q-16 1H-16 3Q-16 (2012 – 2015) Revenue(1) Revenue(1) Revenue(1) Revenue 31.7% +24.7% YoY +24.5% YoY +23.0% YoY +32 Billion +64 Billion +91 Billion 618 518 489 426 398 324 270 260 163 131
Slide 26: Operating Income and EBITDA Growth
Operating Income and EBITDA Growth NI Consolidated Operating Income and EBITDA Trend 2012 – 3Q-16 IDR Billion; unless otherwise stated CAGR 3 Years 1Q-16 1H-16 3Q-16 (2012 – 2015) Operating Income Operating Income Operating Income +30.4% YoY +49.0% YoY +46.9% YoY Operating Income 34.4% 50.1% Margin
Slide 27: Net Income Growth
Net Income Growth NI Consolidated Net Income and EPS Trend 2012 – 3Q-16 IDR Billion for Net Income and IDR for EPS; otherwise stated CAGR 3 Years 1Q-16 1H-16 3Q-16 (2012 – 2015) Net Income(1) Net Income(1) Net Income(1) Net Income 44.6% +40.2% YoY +55.5% YoY +42.7% YoY 22.7% Margin 33.6% Margin 29.4
Slide 28: Financial Position Trend
Financial Position Trend NI Consolidated Financial Position Trend 2014 – 3Q-16 IDR Billion; unless otherwise stated 3Q-16 3Q-16 3Q-16 Debt(1) to Assets Ratio Debt to EBITDA(2) Debt(1) to Equity Ratio 29.3% 3.84x 58.6% Debt(1) Service Net Debt(3) to EBITDA Equity Multiplier Ratio Coverage Ratio 2.32x
Slide 29: Key Growth Drivers
Key Growth Drivers 1 Consistent Growth in Company’s Performance. 1. Total Assets 9 Years CAGR (2006 – 2015) = 29% Consistent Growth 2. Total Revenues 9 Years CAGR (2006 – 2015) = 21% 3. EBITDA 9 Years CAGR (2006 – 2015) = 29% 2 Low leverage position benefits the company to upscale with potential
Slide 30: Thank You
www.nusantarainfrastructure.com Thank You © 2016 PT Nusantara Infrastructure Tbk 30