Slide 1: Rye Park Wind Farm CCC Meeting
RYE PARK WIND FARM CCC MEETING 28 FEBRUARY 2023
Slide 2: Contents
CONTENTS 1. PROJECT UPDATE 2. SCHEDULE OF WORKS 3. ENVIRONMENT AND COMPLIANCE MODIFICATION TO PROJECT APPROVALS 4. STAKEHOLDERS AND COMMUNITY FEEDBACK, ENQUIRIES & COMPLAINTS CCC MEMBERS 5. PROJECT BENEFITS EMPLOYMENT BENEFIT SHARING PROGRAMS RPWF CCC Presentation 2
Slide 3: Schedule of Works: Indicative Schedule
SCHEDULE OF WORKS INDICATIVE SCHEDULE Project Programme: Construction includes road upgrades, wind farm construction (not including pre-construction activities) and commissioning - Construction Commencement – 1 December 2021 - Public Road Upgrades are largely complete with remaining works (Grassy C
Slide 4: Schedule of Works: Transport, Road Upgrades & Schedule
SCHEDULE OF WORKS TRANSPORT, ROAD UPGRADES & SCHEDULE Road Upgrades Update: • Cooks Hill Road – Works are well progressed with all cross-drainage pipes installed, subgrade placement complete and sealing planned for early March 2023. • Public roads repair and maintenance – the project and respective
Slide 5: Project Update: What Have We Been Up To
PROJECT UPDATE WHAT HAVE WE BEEN UP TO • 3 of 66 wind turbines are now fully erected • Earthworks on site ongoing - approx. 90% complete • 51 Foundations poured. • Underground cable trenching is continuing. • All overhead 330kv and 33kv poles have been stood and line stringing commenced. • Construct
Slide 6: Project Update: Works on Site
PROJECT UPDATE WORKS ON SITE 330kV Overhead Line using a helicopter First turbine Northern Substation Progress Tilt Renewables Presentation Title - Date 2019 6
Slide 7: Environment & Compliance: Compliance
ENVIRONMENT & COMPLIANCE COMPLIANCE Safety • 1 reportable incident recorded and closed out relevant regulatory notifications undertaken, leading indicator reporting trending positively. • COVID-19 Management Protocols remain in place in accordance with NSW regulations/guidelines incl. • 2nd independ
Slide 8: Environment & Compliance: Compliance
ENVIRONMENT & COMPLIANCE COMPLIANCE Biodiversity Management • Pre clearance surveys continue prior to works commencing: Heritage management • Focusing on underground cable works Cooks Hill Rd prior to construction • Cultural heritage salvage has been undertaken by archaeologists and Local works occu
Slide 9: Stakeholder & Community Engagement: Feedback, Enquiries & Complaints
STAKEHOLDER & COMMUNITY ENGAGEMENT FEEDBACK, ENQUIRIES & COMPLAINTS Communication • Newsletter (November issue released, March newsletter to be released soon) • Fortnightly construction updates focused on public road upgrades and OSOM deliveries (email, SMS and community noticeboards) • Monthly land
Slide 10: Stakeholder & Community Engagement: Upcoming Activities
STAKEHOLDER & COMMUNITY ENGAGEMENT UPCOMING ACTIVITIES Planned upcoming activities • Site visit for state and local government representatives (1st March) • Blade viewing deferred to mid year • Stakeholder briefings and updates Rye Park Wind Farm 10
Slide 11: Project Benefits: Benefit Sharing
PROJECT BENEFITS BENEFIT SHARING Benefit Sharing initiatives update • Revegetation grants (jointly funded by Zenviron and Vestas) – five awarded including Boorowa Central School • Commencement of funding for psychological assessments for students with learning difficulties • Sponsorship of the Yass
Slide 12: Project Benefits: Employment
PROJECT BENEFITS EMPLOYMENT Employment Opportunities • Goods & Services Register – monthly update to contractors • ICN Gateway – monthly report to contractors 12 Rye Park Wind Farm
Slide 13: Discussion