Canadian Utilities Limited Class A · TSX:CU

Canadian Utilities Limited Class A — Q4 2024 Earnings Presentation

20 slides from Canadian Utilities Limited Class A's earnings presentation, Feb 27, 2025

  1. Slide 1: Q4 2024 Earnings Call

    Q4 2024 Earnings Call Canadian Utilities Limited February 27, 2025

  2. Slide 2: Legal Notice: Forward-Looking Information Advisory

    Legal Notice Forward-Looking Information Advisory Certain statements made by company representatives and information provided in this presentation may be considered forward-looking information. Forward-looking information is often, but not always, identified performance, words such as "anticipate",

  3. Slide 3: Legal Notice: Non-GAAP and Other Financial Measures Disclosure Advisory

    Legal Notice Non-GAAP and Other Financial Measures Disclosure Advisory This presentation contains various “total of segments measures”, “non-GAAP financial measures” and “non-GAAP ratios” (as such terms are defined in National Instrument 52-112 – Non-GAAP and Other Financial Measures Disclosure ("NI

  4. Slide 4: FY 2024 Adjusted Earnings Waterfall

    Financial Highlights FY 2024 Adjusted Earnings1 Waterfall $61 $4 ($2) ($12) $647 +9% Year-over-Year $596 Growth FY ATCO ATCO ATCO Corporate & Other 2 FY 2023 1 Energy Systems 2 EnPower 2 Australia 2 2024 1 Note: Millions of Canadian dollars. 1. Total of segments measure (as defined in NI 52-112). Th

  5. Slide 5: Strong Cash Flows Support Capital Program

    Financial Highlights Strong Cash Flows Support Capital Program Cash Flows from Operating Activities Capital Expenditures $1,917 $1,780 $1,611 $1,360 FY 2023 FY 2024 FY 2023 FY 2024 Portfolio of cash flow generating assets support our strategic investments that underpin long-term growth Note: Million

  6. Slide 6: Energy Systems

    Energy Systems Canadian Utilities Limited Q4 2024 Presentation 6 ATCO Energy Systems [ CONFIDENTIAL ] • June 2024

  7. Slide 7: Capital Expenditures (3-year plan)

    ATCO Energy Systems Capital Expenditures (3-year plan) $5.8B 5.4% 3 Year 3 Year Mid-Year Capital Expenditure Plan Rate Base1 CAGR2 $2.5B $1.8B $1.5B $1.6 $1.4B $0.2 $0.4 $0.9 $0.4 $0.4 $0.3 $0.4 $0.4 $0.3 $0.2 $0.2 $0.5 $0.4 $0.3 $0.3 2024 2025E 2026E 2027E Electricity Distribution Electricity Trans

  8. Slide 8: Yellowhead Mainline

    ATCO Energy Systems Yellowhead Mainline Existing pipeline Yellowhead pipeline Needs application filed with AUC Production in September 2024 Fort McMurray 200-230 km length Total investment for the project is estimated at $2.8 billion 1.1 Bcf/d capacity Construction to start in 2026; expected to be o

  9. Slide 9: Yellowhead Mainline Timeline

    ATCO Energy Systems Yellowhead Mainline Timeline Q2 2024 Q3 2024 Q2 2025 Q3 2025 Q2 2026 Q3 2026 Q4 2027 Pre-FEED AUC Need AUC Need Approval Land Acquisition Regulatory and Construction Target Complete Application FEED Complete Complete Permitting Start In-service Date AUC Facility Complete Long Lea

  10. Slide 10: Central East Transfer-Out Project (CETO)

    ATCO Energy Systems PROJECT TIMELINE Central East Transfer-Out Project (CETO) Aug 2021 Needs and Facility Application approved ATCO is building 85 km of 240 kV double-circuit powerline and expanding Dec 2022 the Tinchebray Substation to connect customers to renewable generation AESO direction to beg

  11. Slide 11: EnPower

    EnPower Canadian Utilities Limited Q4 2024 Presentation 11

  12. Slide 12: ATCO Heartland Hydrogen Hub (AH3)

    ATCO EnPower ATCO Heartland Hydrogen Hub (AH3) Achievements to date ATCO Heartland Business update Energy Center • Signed Letter of Intent with Linde Canada Inc. (Linde). • Working alongside Linde and other parties to further the development and Heartland Hydrogen Hub Site commercial success of the

  13. Slide 13: Generation Portfolio

    ATCO EnPower Generation Portfolio Owned Capacity Operating Assets Type Gross Capacity (MW) (MW) Forty Mile Wind 225 225 Adelaide Wind 40 30 Empress Solar 39 39 Grew generation Deerfoot Solar 41 20 portfolio to Electricidad del Golfo Oldman Hydro Hydro 35 32 35 24 457 MW from 70 Barlow Solar 31 15 MW

  14. Slide 14: Alberta is Well Positioned for the Data Center Build Out

    ATCO EnPower Alberta is Well Positioned for the Data Center Build Out Gas Power Generation Gas Renewable Distribution Power and Storage Generation Abundant Regulatory Natural Gas Alberta’s Environment Resources Data Center Advantage Abundant Water Land Access Resources Canadian Utilities Limited Q4

  15. Slide 15: ATCO's Asset Base Spans the Entire Data Center Value Chain

    ATCO EnPower ATCO’s Asset Base Spans the Entire Data Center Value Chain Inputs Pipelines & Storage Generation Transmission Market ✓ CO Sequestration 2 CO2 ✓ Natural Gas Supply ✓ Gas Pipelines ✓ Gas Storage ✓ Natural Gas Power ✓ Data Centers ✓ Electricity Transmission ✓ Water Supply ✓ Renewable Power

  16. Slide 16: Australia

    Australia Canadian Utilities Limited Q4 2024 Presentation 16

  17. Slide 17: Sixth Access Arrangement (AA6)

    ATCO Australia Sixth Access Arrangement (AA6)1 Total Tariff Revenue $1,375M $1,375. 00 Nominal Return on Equity +$536M +3.21% 8.23% $839M AA5 AA6 Accelerated Depreciation $38M 5.02% $0 AA5 AA6 AA5 AA6 Canadian Utilities Limited Q4 2024 Presentation 17 1. AA6 will be implemented for the period Januar

  18. Slide 18: Canadian Utilities Limited Q4 2024 Presentation

    Canadian Utilities Limited Q4 2024 Presentation 18

  19. Slide 19: Questions & Answers

    Questions & Answers InvestorRelations@atco.com Canadian Utilities Limited Q4 2024 Presentation 19

  20. Slide 20: Corporate & Other

    Appendix Corporate & Other ➢ Preferred Dividends ($83M) ➢ Net Interest1 ($1M) ➢ Head Office & Other $1M ➢ ATCO Energy Ltd.2 $6M Total FY 2024 Adjusted Earnings ($77M) 1. Includes Investment income and Interest expense. 2. Includes 7 months of adjusted earnings of ATCO Energy Ltd. due to the sale of

Canadian Utilities — Q4 2024 Earnings Presentation on 6ix