Slide 1: Global Atomic Corporation: Advancing the Dasa Uranium Project
GLOBAL ATOMIC CORPORATION Advancing the Dasa Uranium Project in the Republic of Niger CORPORATE PRESENTATION FEBRUARY 2026
Slide 2: Disclaimer
Disclaimer This presentation has been prepared by Global Atomic Corporation (“Global Atomic” or the “Company”) and includes information from sources believed by management to be reliable. No representation or warranty, expressed or implied, is made as to the accuracy of the information set forth her
Slide 3: Near-Term Uranium Production & Mineral Recycling
NEAR-TERM URANIUM PRODUCTION & MINERAL RECYCLING URANIUM Republic of Niger Uranium will fuel the global reactor fleet to generate clean baseload power. HQ Canada Zinc Türkiye Uranium ZINC RECYCLING Niger Iskenderun, Türkiye Zinc concentrate produced by recycling Electric Arc Furnace Dust (EAFD), is
Slide 4: Dasa Project: Leading the Way
LEADING THE WAY DASA PROJECT THE ONLY GREENFIELD URANIUM PROJECT UNDER DEVELOPMENT TODAY 4 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 5: 2024 Feasibility Study Highlights
2024 FEASIBILITY STUDY HIGHLIGHTS ✓ Production: 68.1 Mlb U3O8 over 23 years ✓ Reserve Grade 4,113 ppm; 5,109 ppm in the first 12 years, highest grade outside of the Athabasca Basin ✓ Feasibility Study assumed a base U3O8 price of US$75/lb ✓ Actual production timelines will depend on the timing of pr
Slide 6: Value Opportunities
VALUE 2024 FEASIBILITY STUDY ESTIMATED PRODUCTION OPPORTUNITIES 6 Global Atomic’s development plan 5 includes: 4 • An infill drill program on Dasa’s Inferred Resources, 51.4 Mlbs @ Millions lbs U3O8 3 5,349 ppm, with the objective to increase minable reserves to 2 maintain average annual production
Slide 7: 2023 Mineral Resource Estimate
COMPARATIVE GRADE / TONNAGE REPORT AT VARYING CUT-OFF GRADES 2023 MINERAL RESOURCE ESTIMATE May 2023 Revised Estimate eU3O8 (ppm) Tonnes (Mt) eU3O8 Mlbs Contained Uranium Uranium Content Cut-Off Category Indicated 103.6 803 183.5 100 Inferred 71.0 636 99.5 Indicated 44.9 1,602 158.5 320 Inferred 25.
Slide 8: Flank Zone Mine Plan
FLANK ZONE MINE PLAN Flank Zone Flank Zone Completed Sept 2025 Oct 2025 Nov 2025 Dec 2025 Plan - 2026 10-year Plan • Ramp and level development advancing to provide stope access on five levels in the Flank Zone. • The Flank Zone will be mined over 10 years prior to entering the main orebody. 8 TSX:
Slide 9: Mining Team advancing underground development
Mining Team advancing underground development 9 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 10: Processing Plant is underway
Processing Plant is underway 10 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 11: Main Substation advancing
Main Substation advancing 11 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 12: Crusher concrete works in progress; ROM Pad nearing completion
Crusher concrete works in progress ROM Pad nearing completion 12 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 13: Acid Plant: steam turbine building & infrastructure
Acid Plant: steam turbine building & infrastructure 13 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 14: Various civil works underway
Various civil works underway 14 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 15: Various civil works underway
Various civil works underway 15 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 16: Substation #2 under construction
Substation #2 under construction 16 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 17: Diesel storage tank foundations; Control Room & Laboratory building
Diesel storage tank foundations Control Room & Laboratory building 17 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 18: Acid storage tank foundation & cooling tower
Acid storage tank foundation & cooling tower 18 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 19: Rebar bending and installation in progress
Rebar bending and installation in progress 19 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 20: New 260-person camp completed
New 260-person camp completed 20 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 21: Empowering our workforce
Empowering our workforce: Emergency Response Team training session 21 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 22: ESG Initiatives Since 2008
ESG INITIATIVES SINCE 2008: • Food during droughts • Medical supplies • Water wells & infrastructure • Education & training • Local, regional and national procurement of goods & services • ESIAs include significant consultation and baseline studies • Development Bank due diligence independently vali
Slide 23: Strong community relations & social engagement at the Dasa Project
Strong community relations & social engagement at the Dasa Project. 23 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 24: Uranium Supply & Demand
URANIUM SUPPLY & DEMAND URANIUM DEMAND EXCEEDS SUPPLY Source: WNA/Fuel Link 2024 24 TSX: GLO | OTCQX: GLATF | FRA: G12
Slide 25: Befesa Silvermet, Türkiye
BEFESA SILVERMET, TÜRKİYE • Joint Venture (49%) with Befesa Zinc, the market leader in zinc recycling • Processes EAFD containing 20% to 30% zinc sourced from local steel mills • Produces a 65% to 70% zinc oxide concentrate for sale to smelters • Recovers high grade zinc & removes toxic elements fro
Slide 26: Zinc Recycling JV Production & Profitability
ZINC RECYCLING JV PRODUCTION & PROFITABILITY EAFD Processed (tonnes) Sales - Zinc (000 lbs) Avg. monthly LME Zinc price (US$/lb) • New Plant loan retired. 90,000 $1.80 80,000 $1.60 • Improved availability of the 70,000 $1.40 operation’s primary feedstock— 60,000 $1.20 electric arc furnace dust (EAFD
Slide 27: Capital Structure
CAPITAL STRUCTURE C$358 M Market Capitalization Global Atomic Share Price Performance (January 2, 2020 - Feb 2, 2026) GLO Share Price (CAD) Uranium Juniors Adj. to GLO Base (CAD) TSX Composite Adj. to GLO Base (CAD) C$0.73 490.3 M $5.50 TSX Share Price Shares Issued* As of Feb 2, 2026 As of Feb 2, 2
Slide 28: Thank You!