Slide 1: 2018 Institutional Investors Conference
KUNG SING Engineering Corporation 2018 Institutional Investors Conference
Slide 2: Company Profile, Operational overview, Financial summary, Business development
Company Profile Operational overview Financial summary Business development 2 工程創信譽 信譽造工程
Slide 3: Company Profile: Seventy years old history
Company Profile Seventy years old history KUNG SING Engineering Corporation was established in 1947, has been established for 70 years ,2012 The Company's listed stocks . For the domestic large-scale factory to obtain the first ISO 9001 quality management and ISO 14001 environmental management cert
Slide 4: A Summary of Corporate Governance in Recent Three Years
A Summary of Corporate Governance in Recent Three Years 1.The Fourth corporate governance evaluation results for the top 20% excellent Corporation. 2.Won 2018 TCSA Taiwan Enterprise Sustainability Award Corporate Sustainability Report Award - Silver Award. 3. Awarded the Engineering Supervision Exc
Slide 5: Business scope
Business scope Construction engineering ▪Comprehensive construction industry ▪Dredging industry ▪Anti - corrosion, anti - rust works ▪Lifting Engineering ▪Drilling Engineering ▪Waste disposal industry ▪Other environmental sanitation and pollution control services ▪Residential and building developme
Slide 6: Relationship Organization Chart
Relationship Organization Chart 6 工程創信譽 信譽造工程
Slide 7: Operational overview
Operational overview Construction in progress Construction of Danjiang Bridge and Connecting Road Network 5K+000~7K+035 KUNG SING Engineering Contract amount: NT 12.494 billion Co.,Ltd(8F.102.Civil Linkou Power Plant Renewal Boulevard Sec.4.Taipei Expansion Plan Cartridge New Construction of Guany
Slide 8: Construction in progress: Tainan Nanping to Wanrong
Construction in progress C031 agent Tainan Nanping project to Wanrong two-track civil name and tram line project owner Railway Bureau, MOTC Contract NT 1.148 billion 設立日期 price Engineering 員工人數 location East of Taiwan 8 工程創信譽 信譽造工程
Slide 9: Construction in progress: Linkou Power Plant Coal Bunker System
Construction in progress Linkou Power Plant Renewal project Expansion Plan Cartridge Coal name Bunker System Taiwan Electric Power owner Company Limited Contract NT 6.5 billion 設立日期 price Engineering 員工人數 North of Taiwan location 9 工程創信譽 信譽造工程
Slide 10: Construction in progress: Guanyin and Gufong Tunnels
Construction in progress New Construction of Guanyin Tunnel Project project name New Construction of Gufong Tunnels Project Ministry of Communications owner Traffic Authority to improve the highway office Contract NT 7.2 billion 設立日期 price NT 9.208 billion Engineering 員工人數 East of Taiwan location
Slide 11: Construction in progress: Chaozhou to Linbian
Construction in progress civil, Electrical & project Mechanical from Chaozhou name to Linbian, LOT 811, procurement case owner Railway Bureau, MOTC 設立日期 Contract NT 1.738 billion price 員工人數 Engineering Southern Taiwan location 11 工程創信譽 信譽造工程
Slide 12: Construction in progress: Taichung harbor dock No.106
Construction in progress Taichung harbor dock project No.106 new construction name project. Port of Taichung, Taiwan owner International Ports Corporation, Ltd Contract NT 1.186 billion 設立日期 price Engineering 員工人數 Central Taiwan location 12 工程創信譽 信譽造工程
Slide 13: Construction in progress: Danjiang Bridge
Construction in progress Construction of Danjiang project Bridge and Connecting Road name Network 5K+000~7K+035 Directorate General of owner Highways, MOTC Contract NT 12.494 billion 設立日期 price Engineering 員工人數 North of Taiwan location 13 工程創信譽 信譽造工程
Slide 14: In recent years the project winning record
In recent years the project winning record Concrete engineering award, non-architectural masterpiece Taiwan’s Taoyuan 2014 International Airport’s Environmental impact assessment Outside Linking MRT system audit plan selection excellence Construction Prokect Taiwan’s Taoyuan International Airport’
Slide 15: The 17th Public Works Gold Award - Water Works Project
The 17th Public Works Gold Award - Water Works Project. Ministry of Economic Affairs Public Works Quality Award. Linkou power plant renovation The General plan "outlet diversion dike, Administration of north breakwater, coal unloading terminal, connecting 2018 Communications of the Ministry of bridg
Slide 16: Financial summary
Financial summary Nearly three years of consolidated revenue 設立日期 營業額 NT $ million 2015 2016 2017 16 工程創信譽 信譽造工程
Slide 17: Consolidated income statement
2017Consolidated consolidated income statement for the first half NT (thousand) period 2018/9/30 2017/9/30 YOY Operating income 2,449,214 100% 2,930,616 100% (16.43%) Operating cost (2,470,268) (101%) (2,773,589) (95%) (10.94%) Operating margin (21,054) (1)% 157,027 5% (113.41)% Operating expenses
Slide 18: Consolidated assets and liabilities
Consolidated assets and liabilities in the first half of 2017 NT (thousand) period 2018/9/30 2017/9/30 period 2018/9/30 2017/9/30 Current 8,065,493 6,823,419 Current 4,893,750 3,478,144 assets liabilities Non-current 1,269,399 1,340,611 Non-current 662,127 401,105 assets liabilities Real estate, 6
Slide 19: Business development
Business development The future direction of the company to expand operations Cooperate with the government's forward- looking plan and continue to participate in public works and nation building. With the government Investment in the south to the policy, construction of forward ASEAN, new stores
Slide 20: The presentation ends
The presentation ends Thanks for listening 20 工程創信譽 信譽造工程