Slide 1: Jayaswal Neco Urja Limited: Presentation on project and its status
JAYASWAL NECO URJA LIMITED Presentation on project and its status
Slide 2: Board of Directors
BOARD OF DIRECTORS SHRI B. L. SHAW -DIRECTOR SHRI ARBIND KUMAR JAYASWAL -DIRECTOR SHRI RAMESH KUMAR JAYASWAL - DIRECTOR SHRI ANAND JAYASWAL -DIRECTOR SHRI AVNEESH JAYASWAL - EXECUTIVE DIRECTOR
Slide 3: Highlights / Key Notes
Highlights/ Key Notes (JAYASWAL NECO URJA LIMITED- Chhattisgarh – 2 *300 MW) Sl.No Particulars Status Remarks 1. Project Location •Village-Hamirpur & Jobra •Tehsil- Tamnar •District- Raigarh •State- Chhattisgarh 2. Project Capacity (2 x 300 MW) 3 Project Cost Rs 3310.80 crores As appraised. 4 Financ
Slide 4: Status of the Projects
STATUS OF THE PROJECTS (JAYASWAL NECO URJA LIMITED- Chhattisgarh – 2 *300 MW) ITEMS STATUS REMARKS MOU Executed With Chhattisgarh State Government. Land 222.401 acres purchased Applied for acquisition Water Fully tied up 10 MCM allotted from WRD, CG. 7.7 MCM from In built reservoir. Fuel Fully t
Slide 5: Status of the Projects (Contd.)
Contd.. ITEMS STATUS REMARKS PPA In Process Implementation Agreement for sale of power as per “MoU” is in process with Government of Chhattisgarh Grant of Obtained from PGCIL connectivity Grant of Long Obtained from PGCIL BPTA to be signed. term access Technical Appointed Tata Consulting Engineers