Centamin — Investor Presentation (November 2022)
46 slides from Centamin's investor presentation, November 2022
Slide 1: Positioning for Growth & Returns
CORPORATE PRESENTATION CENTAMIN AZ = POSITIONING FOR FIVE GROWTH & RETURNS MILLION OUNCES NOVEMBER 2022
Slide 2: Disclaimers
DISCLAIMERS THIS PRESENTATION AND ITS CONTENTS ARE NOT FOR RELEASE, PUBLICATION OR DISTRIBUTION, IN WHOLE OR IN PART, DIRECTLY OR INDIRECTLY, IN OR INTO OR FROM ANY JURISDICTION WHERE SUCH DISTRIBUTION IS UNLAWFUL This presentation has been prepared by Centamin Plc ympany”) solely for information an
Slide 3: Clear and Consistent Strategy
CLEAR AND CONSISTENT STRATEGY DELIVERING LONG TERM SUSTAINABLE GROWTH AND RETURNS COMMITMENT TO STAKEHOLDER RETURNS CENTAMIN AZ 3
Slide 4: Our Portfolio
OUR PORTFOLIO AN INTEGRATED PIPELINE DELIVERING GROWTH FROM A STRONG RESOURCE BASE 10Moz 8Moz Measured & Indicated! Inferred SUKARI DOROPO ABC PROJECT GOLD MINE . J PROJECT = Cote d'Ivoire Egypt (160km2) Cote d'Ivoire (2,329km?) (1,144km?) Sukari Orebody PFS underway Fieldwork underway ri Mine Upsid
Slide 5: Production and H2-2022 Deliverables
Production (Koz) @) H2-2022 DELIVERABLES 750 SUKARI SOLAR PLANT COMMISSIONING 500 SUKARI UNDERGROUND EXPANSION STUDY CAPITAL STRUCTURE REVIEW 250 SUKARI RESOURCE & RESERVE UPDATE DOROPO PROJECT PFS FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 FY31 FY32 FY33 @Sukari Interim Case — “i Sukari UG Expans
Slide 6: 2022 Guidance
2022 GUIDANCE PRODUCTION (ounces) AISC (US$/oz sold) 430-460 000 1275-1425 YTD: 331.4koz YTD: US$1,386/oz sold Guiding to mid-range Guiding to upper end of range CASH COSTS (US$/oz produced) 900-1000 YTD: US$885/0z produced Guiding to lower end of range CAPEX SAFETY (LTIFR per one million hours) US$
Slide 7: Our Ambitious Targets
OUR AMBITIOUS TARGETS CULTURE OF CONTINUOUS IMPROVEMENTS 2020 - 2023 US$150M -25% COST SAVINGS TARGET REDUCTION IN LTIFR 2021 - 2024 +25% 10 YEARS 3Moz PRODUCTION GROWTH UNDERGROUND RESERVE LIFE GROUP RESERVES GROWTH TO 500,000 OUNCES PER ANNUM CENTAMIN Aé Bees
Slide 8: Location: Egypt's Eastern Desert
CENTAMIN 32 LOCATION EGYPT'S EASTERN DESERT City of Marsa Alam 35km Red Sea 35km Geological setting Arabian Nubian Shield Excellent infrastructure porn alia Skilled workforce Well educated Stable government a DO
Slide 9: Five Million Ounces Produced
FIVE MILLION OUNCES PRODUCED j FIVE THE STRONG CONNECTION BETWEEN GOLD PRODUCTION AND OUR PURPOSE MILLION OUNCES CENTAMIN PURPOSE STATEMENT: SUKARI HISTORIC PRODUCTION 600 “To create opportunities for » people through responsible 300 INT ” 200 mining. a [ 1 > Total workforce of 3,795 people in Egypt
Slide 10: 5.5 million hours worked with no Lost Time Injuries
5.5 million hours worked with no Lost Time Injuries Continued YoY improvement No material environmental incidents COVID-19 protocols remain in place GROUP SAFETY RECORD (per 1,000,000 workplace hours) Teiks) FY22 TARGET TRIFR: 3.99 LTIFR: 0.68 FY 2019 FY 2020 FY 2021 YTD 2022 MSTRIFR @LTIFR
Slide 11: Developing Our People
DEVELOPING OUR PEOPLE A PROGRESSIVE APPROACH TO THE EMPOWERMENT OF OUR PEOPLE THE CENTAMIN CAPABILITY FRAMEWORK AT SUKARI IDENTIFY, DEVELOP & PROMOTE Structured approach to training and educating our workforce Developing leadership and technical skills to improve operational delivery Framework is un
Slide 12: Overview
OVERVIEW GEOLOGY RESTRUCTURE RESERVE RESOURCES (INC RESERVES) 2021 RESERVE UPDATE 2021 RESOURCE UPDATE 2020 5.8Moz P&P 9.8Moz M&l growth growth % Sukari ounce growth Sukari grade growth 2021 MINERAL RESOURCES
Slide 13: Improved Confidence in the Resource Model
IMPROVED CONFIDENCE IN THE RESOURCE MODEL MOVING FROM A GRADE-DRIVEN MODEL TO A GEOLOGICAL BASED MODEL SECTION 10480N 2020 RESOURCE WIREFRAME RELOGGING PROGRAMME > MAPPING > CONTROLS ON GOLD y GEOLOGICAL REMODELLING & ESTIMATION IMPROVED UNDERSTANDING BASALT 3 cal \ SEDIMEN Ne lise aN oa SHEAR ZONE
Slide 14: Moving Sukari to a Growth Model
MOVING SUKARI TO A GROWTH MODEL DISCOVER, DEFINE AND CONVERT RESOURCES 2020 WIREFRAME ANG “ soggort 3 00807 ‘ CURRENT PIT \y FINAL DESIGN Ex i vol EI & * TooSort Tossa IMPROVED GEOLOGICAL CONTROLS AND UNDERSTANDING 2021 WIREFRAME CURRENT PIT FINAL DESIGN CENTAMIN 32 14
Slide 15: Open Operations Overview
OPEN OPER ATIONS — OVERVIEW FIRST ORE 2009 RESERVE LIFE OF MINE ~12 years MINE LIFE INC. RESOURCES AES MINING OPERATOR Owner & contractor (waste material) MINING METHOD Conventional trackless mining OPEN PIT PERFORMANCE (Q0Q) 40.0 12 35.0 : 30.0 25.0 08 § 20.0 06 15.0 04 10.0 50 02 0.0 0 PPP OD PO O
Slide 16: Open Pit Mining
OPEN PIT MINING LOW COST, BULK TONNAGE OPERATION IMPROVING OPERATIONAL FLEXIBILITY AND CONSISTENCY Commenced accelerated waste-stripping programme in 2020: * Owner-fleet focused on ore mining and waste movement * Contractor focused on Eastern Hills waste stripping * Programme outperformance to date,
Slide 17: Underground Operations Overview
OVERVIEW FIRST ORE 2011 / RESERVE LIFE ~8 years Pt ce ; / Wwe MINING OPERATOR Owner { yy, ; ii MINING METHOD Long hole open stoping U N D E RG RO U ND ACCESS Decline OPERATIONS. — UNDERGROUND PERFORMANCE (Q0Q) (} te 350 7.0 300 6.0 ; 250 5.0 ve 5-4 = 200 405 = : § ~ 150 302 100 20 50 1.0 0 0.0 eooco
Slide 18: Underground Mining
UNDERGROUND MINING TRANSITION TO OWNER-MINING DELIVERING IMPROVED COSTS AND PRODUCTIVITIES OWNER-OPERATOR MINING * Strengthened operational team + 200% increase in underground reserves + further growth potential, supported the transition from contractor to owner operator mining in Q1 2022: * Improve
Slide 19: Processing Overview
OVERVIEW COMMISSIONED 2009 CONSTRUCTION Staged NAMEPLATE. 12-12.5Mtpa 1) Open pit material TWO CIRCUITS 2) Underground material FLOWSHEET CIL and floatation ACCESS Decline PROCESSING PERFORMANCE (Q0Q) Sis) 3.0 251 a 20) = ia) 1.0 0.5 0.0 P ®, SY OE LOVE LOGS mmm Tonnes Processed (Mt) ——Feed Grade (g
Slide 20: Processing flowsheet
Crushing Stockpiling crushed ore Grinding Flotation of a bulk sulphide concentrate Thickening of the concentrate and the flotation tailings Fine milling of the concentrate Leaching the precious metals from the concentrate and/or flotation tailings in a dilute Cyanide Solution Adsorbing the precious
Slide 21: Processing Productivity & Efficiency Gains
PROCESSING PRODUCTIVITY & EFFICIENCY GAINS SUSTAINABLE THROUGHPUT OF 12-12.5MT PER ANNUM PHASE 1 UPGRADES Operational management Processing control Efficiencies PHASE 2 UPGRADES - TARGETING RECOVERY Assessment of Gravity circuit Water detoxification plant Oxygen optimisation & maximising leach kinet
Slide 22: Culture of Continuous Improvement
CULTURE OF CONTINUOUS IMPROVEMENT CUMULATIVE COST SAVINGS PROGRAMME TARGETING US$150M IN 4YRS (2020-2023) INITIATIVES UNDER INITIATIVES IN COST SAVINGS REVIEW PROGRESS DELIVERED USS$78m AS OF 30 JUNE 2022 * Gravity Circuit test work + Mill Automation * Trialling new reagents * Recycling Mill Ii nto
Slide 23: The Challenge of Cost Inflation
THE CHALLENGE OF COST INFLATION RECOGNISING INFLATION EARLY WE MAINTAIN COST GUIDANCE ALBEIT AT THE UPPER END OF THE GUIDANCE RANGE GROUP COST BREAKDOWN 336 +1% Versus H2-21 CONSUMABLES $M CONSUMABLES USAGE AND CONTRACT SAVINGS * Ongoing optimisation of consumables and reagents in the process plant
Slide 24: Capex: Growth and Sustaining
250 200 50 US$25m Deferred capex Fy21 FY22e m Sustaining capex (US$m) FY23e Growth capex (US$m) FY24e - oobl| FY22 GROWTH CAPEX US$125.5M FY21 deferred spend Paste plant: US$10m Solar farm: US$15m TOTAL US$25m Contractor waste-stripping: US$73m UG Equipment US$10.5m Paste plant US$5m Sukari explorat
Slide 25: Investing for the Future
INVESTING FOR THE FUTURE KEY PROJECTS PASTE-FILL PLANT: ONGOING SOLAR PLANT: NEAR COMPLETE HIGH-PRODUCTION TRUCK TRAYS: COMPLETE CENTAMIN AZ 24
Slide 26: 36MW Hybrid Solar Power Plant
36MW HYBRID SOLAR POWER PLANT DECARBONISATION OF POWER GENERATION PROJECT SPECIFICS + 36MW)-solar farm & 7.5MW battery-energy storage system + 85-hectare site * Generating 25% of annual power needs FINAL STAGES OF COMMISSIONING * Consistent delivery of 36MWDC (nameplate capacity) * Saving up to 70,0
Slide 27: Delivering Operational Productivity
DELIVERING OPERATIONAL PRODUCTIVITY OPERATING MORE EFFICIENTLY OPTIMISING FLEET UTILISATION Y) High performance truck trays installed Y) Haul road maintenance improvements ~Y) Cycle time optimization CENTAMIN 32 OWNER TRUCK PRODUCTIVITY (tonnes per hour) Tonnes Per Hour Aug 2020 June 2022 +12% 400 a
Slide 28: Growth & Diversification
ENTAMIN AZ 7 - GRO| DIVER CATION *
Slide 29: 2022 Drill Highlights
2022 DRILL HIGHLIGHTS <O Bras _ CLEOPATRA | J ! pu: « 54m at 15.1g/t Au = FINAL OPEN PIT SHELL| PTAH * 23m at 7.2g/t Au AMUN ° 17m at 9.6g/t Au = HORUS a, * 8.5m at 7.6g/t Au HORUS DEEPS LEGEND : BAST Measured SE * 10m at 64g/t Au Indicated = Inferred * 4.5m at 267g/t Au ™ Conceptual ™ Unclassified
Slide 30: Underground Expansion Potential
UNDERGROUND EXPANSION POTENTIAL CONCEPTUAL PLAN UNDER DEVELOPMENT RESULTS DUE IN Q4 2022 HAULAGE OPTIMISATION Investigating twin declines, passing bays and portals from the open pit Fleet utilisation and capacity CONCEPTUAL MINE PLANNING SENSITIVITY AND SCENARIO TESTING OF PIT PORTALS Portal 910 RL:
Slide 31: Grid Power Study
GRID POWER STUDY POTENTIAL TO FURTHER REDUCE COSTS AND GHG EMISSIONS EGYPT IS A REGIONAL EXPORTER OF POWER e +483,500km* of high voltage powerlines constructed 2014 — 2020 ° CEY in active engagement with government and independent power ‘ a providers * Evaluating initial proposals to supply 30-50MWa
Slide 32: Sukari Mining Concession
SUKARI MINING CONCESSION eae ea sey SUKARI NORTH EXTENSION FULLY EXPLORE THE 160KM? SUKARI MINING CONCESSION i =| eR f 69 | SUKARI NORTH EAST MELANGE lubed -) Exploration programme commenced in 2021 Identify potential satellite feed material Grow the Mineral Resource and Reserve base f waoiaam (SUE
Slide 33: Egypt's Eastern Desert Exploration Blocks
EGYPT'S EASTERN DESERT EXPLORATION BLOCKS SECURED 3,000KN? HIGHLY PROSPECTIVE GROUND UNDER NEW MINING CODE! Two strategies; three blocks: Nugrus Block (1,086kmz2) Najd Block (1,374km?) Um Rus Block (524km?) Two-year exploration budget: US$10 million identifying and ranking drill test targets Field w
Slide 34: Doropo Mineral Resource Area
DOROPO MINERAL RESOURCE AREA (“MAIN CLUSTER”) MULTIPLE SHALLOW DEPOSITS WITHIN 7KM RADIUS Multi pit project — 9 deposits in Main Cluster Main Cluster hosts 73% of current resource base Scoped pits within a 7km radius area Kilosegui deposit 30km SE of Main Cluster — 27% of current resource base Shall
Slide 35: Doropo Project Development Potential
DOROPO PROJECT DEVELOPMENT POTENTIAL POST-TAX NET PRESENT VALUE (NPY; .,) INTERNAL RATE OF RETURN (“IRR”) DEVELOPMENT CAPITAL US$487M 33% US$275M at consensus! gold price at consensus! gold price US$234m at US$1450/oz gold price 21% at US$1450/oz gold price Including 15% contingency MINERAL RESOURCE
Slide 36: Doropo PFS workstreams
Completion of in excess of +100,000 metres of drilling Targeting conversion of Inferred Resources to the Indicated Resource growth potential has also been identified Detailed soil geochemistry sampling programme PFS completion followed by board decision on definitive feasibility study (“DFS”) MAJOR
Slide 37: World Class Asset Offering Growth + Yield
WORLD CLASS ASSET OFFERING GROWTH + YIELD VALUE MAXIMISATION AT SUKARI » Underground move to owner- mining * Commission solar plant * Drill bonanza high-grade targets » Resource & Reserve update CENTAMIN AZ GROWTH & DIVERSIFICATION » Underground expansion study * Commenced EDX field exploration * Do
Slide 38: Appendix
APPENDIX
Slide 39: Sukari Concession Agreement
SUKARI CONCESSION AGREEMENT EGYPTIAN LAW 222 OF 1994 BY WAY OF PRESIDENTIAL DECREE CENTAMIN PLC (CEY LN; CEE CN) 100% 50% operating surplus (“Profit Share”) 50% 50% operating surplus* (“Profit Share”) 50% 1 aessecscseeeseee SUKARI GOLD MINES \aam > 3% royalty to ARE LICENSE 160km? 30 year license gr
Slide 40: Delivering Operational Consistency
DELIVERING OPERATIONAL OPEN PIT Cc O NS | ST E N CY a0 mmm Ore (Mtpa) mmm Waste (Mtpa) ——Grade Mined (g/t) INTERIM CASE (RESOURCE CONVERSION) OPERATING SCHEDULES 120 LOM Strip Ratio - 8:1 (waste:ore) 100 ~Y) Improved open pit mining flexibility and consistency 80 60 Y) Balanced underground stope & d
Slide 41: Cost Structure
COST STRUCTURE LIMITED COST SENSITIVITIES MINE PRODUCTION COSTS 1% CENTAMIN 32 GROUP COST BREAKDOWN 17% 11% H1 2021 H2 2021 mLabour ™Fuel m™Consumables m Royalties H1 2022 Contractors Other FX EXPOSURE REDUCED 14% 10% ——> Baa H1 2021 H2 2021 H1 2022 Other BAUD EGP ®USD 39
Slide 42: +12 Year Life of Mine
+12 YEAR LIFE OF MINE Tonnage Gold (Mt) Content (Moz) OPEN PIT Proven 100.4 12 BY) Probable 20.8 1.0 0.6 P&P 121.1 1.2 46 UNDERGROUND Proven 21 gS 0.2 Probable 5.7 3.6 0.7 P&P 78 3.6 0.9 STOCKPILES Proven 174 0.5 0.2 Probable P&P 17.4 0.5 0.2 Sukari Mineral Reserves P&P 146.4 1.2 5.8 Open pit and st
Slide 43: Group Mineral Resources
GROUP MINERAL RESOURCES ACTIVE GROWTH PIPELINE 2021 Gold In Tonnage Grade on Category (Mit) (eft) Core SUKARI GOLD MINE Measured (M) 220 1.06 745 (updated Dec 2021) Indicated (1) 70 1.05 2.36 OP cut-off 0.3g/t; UG 1.0g/t M+l 290 1.05 9.81 Inferred 14 14 0.6 DOROPO PROJECT Measured - = = (updated 27
Slide 44: • • • • • • • • • • • • • •
• • • • • • • • • • • • • • • • • • • • • • • • •
Slide 45: 2022 Underground Drill Intercepts
2022 UNDERGROUND DRILL INTERCEPTS SUKARI UNDERGROUND SIGNIFICANT ASSAY RESULTS >16/T AU Significant intercepts are located within the Sukari Mine Concession and proximal to the mine workings Minimum down hole width reported is 3 metres with a maximum internal dilution of 4 metres. True widths are ap
Slide 46: Enquiries
a bls FIVE —— MILLION ‘muh GES. -_— —_ ENQUIRIES | ALEX BARTER-CARSE | INVESTOR@CENTAMINPLC.COM