  1. Slide 1: Southern Natural Gas Company 2024 Outage Review

    Southern Natural Gas Company 2024 Outage Review October 16th, 2024

  2. Slide 2: Welcome

    Welcome 2

  3. Slide 3: Agenda

    Agenda • Review of current and upcoming notable Outages • October/November/December/January • Unscheduled outages • North System • South System • South Louisiana System • EEC • This will be our last meeting of the year. We will start back in February of 2025. Please continue to reference our weekly

  4. Slide 4: Disclaimers

    Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas

  5. Slide 5: Color Key for Maps

    Color Key for Maps • Yellow • Restrictions are possible • With extended duration, restrictions could be necessary from time to time • Lower than normal pressures may be experienced • Meter(s) affected are noted with (PIN #) • Red • Restrictions are probable 5

  6. Slide 6: Southern Natural Gas Pipeline

    Southern Natural Gas Pipeline Chattanooga Rome Hartwell SC Muldon North System GA MS Tarrant Bell Mills Aiken McConnells Atlanta Pell City DeArmanville Louisville Fairburn Wrens Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Selma Elmore Holy Tr

  7. Slide 7: Southern Natural Gas Pipeline: Unscheduled Outage Update

    Southern Natural Gas Pipeline Unscheduled Outage Update Chattanooga Unscheduled unit outage Auburn compressor station 10-10-24 to 10-31-24 Rome Seg. 460 capacity of 1,953Mdth/d impacted Hartwell SC Muldon 65 Mdth/d 11-1-24 to 11-15-24 North System GA MS Tarrant Seg. 460 capacity of 2,095 Mdth/d Bell

  8. Slide 8: SNG North System Pigging Review

    SNG North System Pigging Review October/November/December/January Chattanooga Huntsville Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville GA Pickens Onward Bear Creek Storage AL Logansport Bienville Rankin LA Compressor Station Stora

  9. Slide 9: SNG North System Maintenance Review

    SNG North System Maintenance Review October/November/December/January Pipeline maintenance Chattanooga North Main Line and loop line at Tarrant Muldon unit maintenance 10-15-24Huntsville to 10-25-24 9-9-24 to 11-15-24 Rome Bear Creek Shut-in test 10-15-24 to 9 AM 10-21-24 AL Restrictions first into

  10. Slide 10: SNG South System Pigging Review

    SNG South System Pigging Review October/November/December/January MS Hartwell Aiken Atlanta Wrens Fairburn GA Ocmulgee AL Ellerslie Hallgate Auburn Thomaston Elba Riceboro Gallion Selma Elmore Holy Trinity York Enterprise Bay Springs Pigging on the Brunswick Line Gwinville 10-16-24 Albany to 10-24-2

  11. Slide 11: SNG South System Maintenance Review

    SNG South System Maintenance Review October/November/December/January Fairburn unit maintenance Proj-57052 Fairburn station maintenance MS 10-15-24 to 11-6-24 10-21-24 to 10-22-24 During this outage Southern This project will require a station outage. Hartwell Enterprise unit maintenance will be lim

  12. Slide 12: SNG South System Maint. Review cont.

    SNG South System Maint. Review cont. October/November/December/January Gallion unit maintenance Proj-523610 MS 10-31-24 to 11-1-24 Seg. 440 capacity of 2,300 Mdth/d Elmore unit maintenance Hartwell impacted 265 Mdth/d 11-19-24 Aiken Seg. 460 capacity of 2,293 Mdth/d Atlanta 11-4-24 to 11-15-24 impac

  13. Slide 13: SNG South Louisiana System Pigging Review

    SNG South Louisiana System Pigging Review October/November/December/January Gwinville Pearl River MS LA Franklinton West Leg White Castle Toca East Leg Shadyside Compressor Station Storage Field Southern will be conducting other general maintenance during this period 13

  14. Slide 14: SNG South Louisiana System Maintenance Review

    SNG South Louisiana System Maintenance Review October/November/December/January Pearl River station outage 10-14-24 to 10-28-24 Seg. 370 cap. of 1,123 Mdth/d impacted 280 Mdth/d SESH planned fall maintenance Gwinville affecting SNG capacity 10-21-24 to 10-23-24 Franklinton unit maintenance Capacity

  15. Slide 15: SNG South Louisiana System Maint. Review Cont.

    SNG South Louisiana System Maint. Review Cont. October/November/December/January Pipeline maintenance on FGL 10-11-24 to 11-1-24 Gwinville Seg. 370 cap. of 1,123 Mdth/d impacted 180 Mdth/d south of Pearl River Pipeline maintenance on MPF2NDLL Pearl River 12-2-24 to 12-11-24 Seg. 330 cap. of 1,010 Md

  16. Slide 16: EEC Line Pigging and Maintenance Review

    EEC Line Pigging and Maintenance Review October/November/December/January Rome Hartwell SC Muldon North System GA MS Tarrant Bell Mills Atlanta Aiken McConnells Pell City DeArmanville Hall Gate Wrens Louisville Fairburn Providence Ocmulgee Pickens Reform Ellerslie Bear Creek Onward Auburn Thomaston

  17. Slide 17: Gas Control Contacts

    Gas Control Contacts Skyler Spyker – Manager • (713) – 420 – 2386 (office) • (806)-470-7743 (cell) • skyler_spyker@kindermorgan.com Kal Dankovich – Outage Coordinator • (205) – 533 – 4795 (cell) • kalman_dankovich@kindermorgan.com Mario Murillo – Outage Coordinator • (281) – 753 – 6530 (cell) • mari

  18. Slide 18: Questions?

    Questions? 18