    Ea s t C oa s t Ga s The problem There is a shortage of deliverable gas for the east coast market For both export and domestic markets 1

  3. Slide 3: The Solution: The Bowen Basin Gas Province

    The Solution “The Bowen Basin Gas Province” ~10,000 PJ of gas resource CURTIS ISLAND Wallumbilla Hub Connect the Bowen Basin to the southern market 2

  4. Slide 4: The Market

    Eas t C oa s t Ga s The Market Demand today* Curtis Island Export LNG 3,400 TJ/day ~1,300 PJ/a Domestic 1,350 TJ/day ~500 PJ/a 1,800 PJ/a Demand over next 20 years (no growth) Curtis Island ~29,000 PJ Domestic ~11,000 PJ ~40,000 PJ Supply Snapshot Proved East Coast Reserves (1P) 18,000 PJ Proved Dev

  5. Slide 5: Conversion to Reserves

    Conversion to Reserves The Process (is capital intensive) Blue has 3,100 PJ of Uncontacted Contingent Resource in the Bowen Conversion rates from Contingent Resources to reserves are up to 80% in Resource plays (that potentially gives Blue almost a train’s worth of reserves for 20 years) 4

  6. Slide 6: East Coast Gas Supply

    East Coast Gas Supply Where are the current 2P Gas Reserves? • 2P Reserves ARE NOT “flowing” molecules today • Big CAPEX is required to 3,569 PJ develop “deliverable 132 molecules” in short-medium PJ term 1,176 Surat Gas PJ committed to LNG • Bowen Basin gas province needs development and connection

  7. Slide 7: Sapphire Conceptual Development plan

    Sapphire Conceptual Development plan ATP 814P Bowen Basin • 100% Blue • Current 2P & 3P reserves suitable for domestic contract (300 PJ) • Big resource upside (~3,000 PJ) – LNG market • Province provides solution for southern gas shortages • North Qld demand potential is developing • Conceptual Deve

  8. Slide 8: Bowen Gas Province

    Bowen Gas Province Geological configuration - Moranbah • Multiple targets • Producing Fields adjacent 7

  9. Slide 9: Additional Blue Gas Acreage

    Additional Blue Gas Acreage ATP 854P Bowen Basin • Blue has uncontracted Contingent Resources (100 PJ) • Same play as Fairview and Spring Gully plus additional Early Permian targets • The block has infrastructure passing through – connected to Wallumbilla and Gladstone • There is exploration upside

  10. Slide 10: Emerging Plays for new gas resources

    Eas t C oa s t Ga s Emerging Plays for new gas resources Proterzoic Gas Plays Permian Gas Permian Tight Gas 9

  11. Slide 11: The Galilee Frontier

    East Coast Gas Solution “The Galilee Frontier” • Blue has 838 PJ Contingent Resource • Large Contingent resource base in the basin • Adjacent Operator production testing new lateral well • Export infrastructure being scoped 10

  12. Slide 12: Emerging Plays: Cooper Basin Tight Gas

    Emerging Plays Cooper Basin Tight Gas • Basin Centred Gas play identified - REAL Energy tests gas at Tamarama • Permian and Triassic stratigraphic plays • Santos JV has undeveloped structural Tamarama 1 gas test gas fields adjacent to Blue • Infrastructure passing through permit 11

  13. Slide 13: Emerging Plays: Northern Territory Proterozoic plays

    Emerging Plays Northern Territory Proterozoic plays • Proterozoic marine shales of the Greater McArthur Basin are world class source rocks • Operators have intersected prospective sections Origin Discovery well – • Origin Energy has fracture stimulated and flow gas flow = 0.8-1.2 mcfd tested Amulee

  14. Slide 14: Summary

    Eas t C oa s t Ga s Summary • Curtis Island is short gas – at least 2 trains need third party gas • Curtis Island is drawing gas from Cooper Basin and offshore Victoria • Domestic Gas contracts continue to roll off • LNG exporters will supply domestic market when the price signal is right • There is