Slide 1: Investor Presentation H1 2026
Investor Presentation H1 2026 CORPORATE FINANCE FINANCIAL RESTRUCTURING FINANCIAL AND VALUATION ADVISORY August 2026 HL.com
Slide 2: Financial Highlights H1 2026
FINANCIAL HIGHLIGHTS H1 2026 REVENUE (EURm) • Revenue declined to 6.9m EUR in comparison to H1 2025, reflecting major customer inventory H1 2026 6.9 build-up at prior year-end and the production shutdown in Q2 2026. H1 2025 10.4 EBITDA (EURm) • EBITDA remained slightly positive at 0.1m EUR, despite
Slide 3: Profit and Loss H1 2026
PROFIT AND LOSS H1 2026 EURm • Revenue totaled 6.9m EUR, due to the factory shutdown and advanced customer orders end of the previous year. Income Statement H1 2026 H1 2025 Revenues 6.9 10.4 • Capitalized own work rose to 2.1m EUR, driven by the final R&D phase of Increase in contract assets portfol
Slide 4: Cashflow H1 2026
CASHFLOW H1 2026 EURm Cash Flow Statement H1 2026 H1 2025 Cash and cash equivalents at beginning of period 3.1 -2.8 Cash flow from operating activities 1.3 3.3 Cash flow from investing activities -2.2 -2.2 Cash flow from financing activities 0.8 -0.7 Net change in cash and cash equivalents 0.0 0.5 F
Slide 5: Balance Sheet H1 2026
BALANCE SHEET H1 2026 EURm Balance Sheet Jun 30, 2026 Dec 31, 2025 Total Assets 39.9 39.6 A. Non-current assets 29.5 27.6 B. Current assets 10.3 12.0 Equity and liabilities 39.9 39.6 A. Equity 13.8 14.6 B. Non-current liabilities 11.1 10.3 C. Current liabilities 14.9 14.8 • Total assets increased sl
Slide 6: Current Status Production SE09 & NMC+
CURRENT STATUS PRODUCTION SE09 & NMC+ 1. Production of SE09 battery packs ended • Last packs produced 24.04.26 • Production of spare parts finalized 30.04.26 • SE09 shipments to customers until August´26 • Modules, Packs and other components (BMS, S-boxes) available as spare parts 2. Serial producti
Slide 7: NMC+ Serial Production & Electronic Integration
NMC+ SERIAL PRODUCTION & ELECTRONIC INTEGRATION 1. NMC+ Serial batteries shipment to bus customers • started in July 2026 2. Integration project ongoing for BMW i3 conversion • First cars running, working on passenger car homologation and electronic integration for BMW vehicle communication 3. First
Slide 8: Immersion Cooled Battery Technology
IMMERSION COOLED BATTERY TECHNOLOGY 1. Ongoing projects with truck OEM • Order intake in steps, simulation phase finalized soon, final strategic decisions pending – informed by the customer that it will take some time • Next step: Prototype immersion cooled modules 2. Technical feasibility discussio
Slide 9: Operational Highlights BESS
OPERATIONAL HIGHLIGHTS BESS Good business progress since signed cooperation agreement with LEAP Energy in April 2025 • Finsterwalde 1+2: Germany 5 MW / 20 MWh (4h-system) – connected to the grid, final tests performed in July 2026 • 2nd project won: Germany Northern Bavaria project 5 MW / 10 MWh – c
Slide 10: Operational Highlights BESS
OPERATIONAL HIGHLIGHTS BESS • Customer base extended to over 20 companies, prospect list exceeds 60 potential clients in the wind and photovoltaic sector. • Supplier strategy: o DC: 1st LEAP Energy, 2nd source Sunwoda supplying IBC Solar AG projects o AC: Sinexcel, Power Electronics and Sineng as al
Slide 11: Sales Team BESS
SALES TEAM BESS Build up Sales team BESS • Strong BESS team in place: 3x Sales & Business Development 1x Head of Strategy 1x Business Development Italy 1x Technical Solution Manager • Additional Sales Manager Italy position opened (Italy 2 nd largest EU market for BESS) • Hildburghausen as BESS serv
Slide 12: Disclaimer