  1. Slide 1: Annual General Meeting 2023

    AIM, Altx: (EUZ) Searching for new strategic assets with near term value potential US$6m Farm-In/JV with Denarius Metals Corp. “we will lead the development of this high-grade polymetallic project” Denarius Chairman and CEO, Serafino Iacono Annual General Meeting 2023

  2. Slide 2: Cautionary Statement/Disclaimer

    Cautionary Statement/Disclaimer Investors Resident in the UK: This Presentation is only being made available to the following in the United the accuracy, reliability or completeness of the information in this Presentation, or any revision thereof, or of Kingdom: persons that are "qualified investors

  3. Slide 3: Annual General Meeting 2023

    Annual General Meeting 2023 • Europa confirmed the signing of a definitive agreement, a US$6m farm-in arrangement with Denarius Metals Corp in late 2022 • The First Option over 3 years conditional upon: expenditure of US$4m, completion of a preliminary economic assessment (“NI43-101 PEA") and the co

  4. Slide 4: Denarius Farm-In Joint Venture

    Denarius Farm-In Joint Venture • Option Agreement entered into with Denarius (TSXV: DSLV) • “First Option” to subscribe for 51% of Europa subsidiary EMI, which holds the Toral Project, by spending US$4m • and a “Second Option” to potentially acquire an additional 29% for US$2m cash to Europa • Trans

  5. Slide 5: First Option

    First Option • US$4m by way of a loan (the “Loan”) to EMI (the “First Option Expenditure”) Denarius entitled to capitalise the Loan for the issue to it of 51%. • If First Option is not exercised, Denarius shall be required to assign the loan to Europa Metals for US$1 • 3 Year period, which Denarius

  6. Slide 6: Second Option

    Second Option The Second Option may be exercised by Denarius within a period of one year from the date of closing of the First Option conditional upon: • exercise of the First Option; • completion of a NI 43-101 compliant pre-feasibility study (the “PFS”) on the Toral Project at Denarius’s own cost;

  7. Slide 7: Toral

    Toral Licence boundary overlapping local municipal areas Province of León - established mining region Close cooperation with Junta of Castilla y León has allowed delivery of multiple work programmes Pro mining jurisdiction >190 Active Investigation permits 30+ Mining Licences granted in last 6 years

  8. Slide 8: Resource as of December 2022

    Resource as of December 2022 West-East long section of Toral Resource (AMS Consulting) • Indicated resource estimate of approximately 7Mt @ 8.1% Zn Equivalent* (including Pb credits) and 29g/t Ag, representing an approximate: o 19% increase in Indicated resource tonnes; o 39% increase in Indicated c

  9. Slide 9: Resource drilling 2023

    GB <200 GBB 2.00t04.00 BB 40080600 BB 6.00t08.00 GB 2.0080 10.00 @ >= 10.00 %ZnEq (Pb,Ag) Drillcollar Area of influence impact point eqxmee Indicate resources boundary EUROPA NQMetTALs

  10. Slide 10: Drilling Results 2023

    Drilling Results 2023 Hole ID From To Interval (m) Zn_% Pb_% Ag_ppm Cu_% ZnEq(PbAg)%* TOD-044 490.85 498.80 7.95 2.56 1.73 14.65 0.04 4.46 TOD-044 (including) 490.85 495.1 4.25 3.93 2.06 16.79 0.04 6.17 TOD-044 (including) 492.65 494.2 1.55 8.35 2.76 24.31 0.05 11.40 TOD-045 592.00 596.95 4.95 7.31

  11. Slide 11: Mining Licence Application (MLA) October 2023

    Mining Licence Application (MLA) October 2023 The MLA is applied for under a Mine Exploitation Project and Rehabilitation Plan and accompanied by an Environmental Impact Assessment and covers all aspects of mining, environmental and rehabilitation and includes: • A detailed description of the area w

  12. Slide 12: MLA Exploitation Plan

    MLA Exploitation Plan Underground mining is considered to be the most technically, economically, and environmentally viable development option. The application considered three main areas 1. Construction phase, in which the construction of the main facilities such as road access, treatment plant and

  13. Slide 13: Mine workings, plant and footprint

    Mine workings, plant and footprint 13

  14. Slide 14: Plant and waste dump

    Plant and waste dump » Término Municipal de Toral de los Vados Término Municipal de Carracedelo Término Municipal de Carucedo f ; 5 EUROPA METALS SENSE Ne PROYECTO DE EXRLOTACION MINA TORAL ISTALAGONES DE SUPERFIOE ZONA DE INSTALACIONES PRINCIPALES / ant “ae

  15. Slide 15: Circular Waste Management and Rehabilitation

    Circular Waste Management and Rehabilitation • The total area occupied by the project facilities is approximately 33 hectares, of which about 7 hectares are currently the disused limestone quarry, La Estrella, which as part of Toral’s restoration plan is to be rehabilitated by back filling with wast

  16. Slide 16: Environmental

    Environmental • The EIS includes a detailed characterisation of the area where the project will be developed. Specific studies have been carried out, including: • Perceptual physical media: Atmospheric dispersion study, pre-operational acoustic study, landscape integration study and a hydrological-h

  17. Slide 17: Looking forward into 2024

    Looking forward into 2024 A meeting was held in Madrid between Denarius and Europa to discuss results and remaining work schedules and next steps Remaining work for 2023: • Hydrogeological boreholes were drilled and cased in mid September with follow-on pump testwork completed in late October • Data

  18. Slide 18: Lead, Zinc, Silver

    Lead, Zinc, Silver AIM, Altx: (EUZ)