    Outline NHPC Today Financial Highlights Investment Plan Other Business Development Initiatives Financial Ratios Projects At a Glance

  3. Slide 3: NHPC Today

    NHPC-Today A Mini Ratna Category–I Enterprise of Govt. of India with a Paid Up Capital of Rs. 11070.67 Crore.

  4. Slide 4: NHPC – Physical Snapshot

    NHPC –Physical Snapshot  Projects Completed on Standalone basis-18 Nos. (4987 MW)  Projects Completed with Subsidiary 2 Nos. (1520 MW)  Total Operational Projects – 20 Nos. (6507 MW) Installed Hydro Power  Projects Under Construction 4 Nos. (3290 MW) (40531) is 16.68% of All India Installed Capa

  5. Slide 5: NHPC's Track Record – A Ten Year Digest

    NHPC ‘s Track Record – A Ten Year Digest Standalone Generation in (M.U) Country Generation 13-14 9,66,379 MU 18604 18683 18923 18386 16689 16960 14813 Share of Hydro Power- 13049 12567 1,34,731 MU (14%) 11286 Share of NHPC- 18,386 MU (14%) 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011

  6. Slide 6: NHPC - Financial Highlights

    NHPC- Financial Highlights

  7. Slide 7: Profit & Loss (Rs. in Crore)

    PROFIT & LOSS (Rs. in Crore) FY 2013-14 FY 2012-13 Power Station (No.) FY 2013-14 18 [ 4857 MW] 14 [4050 MW) Rest of 18386 (16741+1645) 18904 (18162+902) Generation (MU) Subansiri Lower & Others 15942 (14611+1331) 16397 (15821+576) TLDP-IV Unit Sold (MU) : Net Sales/Income from Operations 0 5335 533

  8. Slide 8: Factors Affecting PAT FY 2013-14 vs FY 2012-13

    FACTORS AFFECTING PAT (F.Y. 2013-14 v/s F.Y. 2012-13) (Rs. in Crore) Factors for increase in PAT Total Increase in Net Sales 286 Decrease in Tax 250 Increase In Other income 464 Increase (A) 1000 Factors for decrease in PAT Decrease due to charging off expenditure during interruption period - 1327 S

  9. Slide 9: Incentive Position

    Incentive Position Details of Incentives, Secondary Energy, UI Charges (Rs. In Crores) FY2014 FY2013 Particulars S.N of Q1 Q2 Q3 Q4 Total Q1 Q2 Q3 Q4 Total o Incentives Secondary 1 63.39 22.39 20.43 -20.15 86.06 63.14 41.46 22.53 -15.96 111.17 Energy 2 Incentives 93.85 92.6 20.51 -35.58 171.38 83.94

  10. Slide 10: Factors for Decrease in Net Profit

    FACTORS FOR DECREASE IN NET PROFIT REASONS FOR DECREASE IN PROFIT 1 Owing to interruption of construction activities at Subansiri Lower and TLDP IV Project, the Borrowing Cost and Administration & Other Cost is Charged to P&L in line with the opinion of EAC ( Expert Advisory Committee) of the ICAI.

  11. Slide 11: Sale of Power-Debtor Details

    Sale of Power-Debtor Details Debtors as on 31.03.2014 Beneficiary wise Debtors (Top Five) as on 31.03.2014 S.No. Particulars Amount (in Crs.) S.No. Particulars Amount (in Crs.) 1 Beneficiary wise Debtors 1838.69 1 PDD, J&K 1064.25 2 UI Charges 6.61 2 UPPCL, UP 179.61 3 Unbilled Debtors 426.04 3 PSPC

  12. Slide 12: Gross Block v/s CWIP

    Gross Block V/s CWIP S.No. Particulars Gross Block CWIP Amount CWIP % to Gross Amount (In Crs.) Block (In Crs.) 1 As on 31.03.2014 32931.02 14657.13 44.51 % 2 As on 31.03.2013 25720.04 19709.04 76.63 % 3 As on 31.03.2012 23060.93 19349.74 83.91 % 4 As on 31.03.2011 22874.93 15962.77 69.78 %

  13. Slide 13: NHPC - Achievements During the Current Fiscal

    NHPC-Achievements During the Current Fiscal Achievements during the FY 2013-14 1 Projects Commissioned during the FY 2013-14 Project Capacity Design CCEA Revised Regulate Remark Added Energy Cost (Rs. Cost (Rs. d Equity (MW) (Mus) in Crore) in Crore) (Rs. in Crore) TLDP III 132 594 769 1973 577.74 U

  14. Slide 14: NHPC - Achievements

    NHPC-Achievements Achievements during the FY 2013-14 3. Parbati-II - Awarding of Contract for HRT Works. • HRT works by TBM (Lot-PB-2A) has been awarded to M/S Gammon-CMC JV on 13.08.13. • HRT works by DBM (Lot-PB-2B) has been awarded to M/s Valecha Engg. Ltd on 21.11.2014. • The work is in progress

  15. Slide 15: NHPC – Regulated Equity

    NHPC – Regulated Equity Parbati-III* 691.37 Regulated Equity for FY Uri-II 506.49 13-14 = ` 9848.63 crs Nimmo Bazgo 209.66 TLDP-III* 577.74 ROR Projects-` 2387.73 Chutak 203.25 Chamera-III 514.52 Sewa-II 317.48 Testa-V 1112.78 Dulhasti 1986.69 Dhauliganga 475.6 Chamera-II 614.59 Rangit 186.74 Uri-I

  16. Slide 16: NHPC - Other Business Development Initiatives

    NHPC- Other Business Development Initiatives  Solar Energy  Wind Energy  Thermal Energy

  17. Slide 17: Renewable Energy Initiatives

    Renewable Energy Initiatives Wind Power Project •MOU signed with Government of Kerala on 06.01.2014 for development of grid interactive wind energy project with proposed installed capacity of 82MW in Palakkad District of Kerala on BOOT basis. •C-Wet has been engaged for preparation of DPR, which is

  18. Slide 18: Thermal Power

    Thermal Power MOU With IFFCO & CSPHCL 1320 MW MOU With BSPGCL & PIRPAINTI BIJLEE (660x2) COMPANY 1320 MW (660x2)  Signed an MOU with IFFCO and CSPHCL for  MoU has been signed on February 22, 2014 acquisition of IFFCO share (74%) in existing amongst NHPC Limited, Bihar State Power joint venture in

  19. Slide 19: NHPC - Financial Ratios

    NHPC- Financial Ratios

  20. Slide 20: NHPC – Financial Ratios FY 2013-14

    NHPC – Financial Ratios FY 2013-14 S.No Particulars FY 2014 FY 2013 Standalone Consolidated Standalone Consolidated 1. EPS 0.82* 1.02 1.91 2.13 2. Book Value 23.90 25.87 22.63 24.69 3. PB Ratio 0.80 0.74 0.88 0.81 4. PE Ratio 23.38 18.78 10.42 9.35 S. No. Particulars FY 2014 FY 2013 1. Market Capita

  21. Slide 21: NHPC - Projects At Glance

    NHPC- Projects At Glance

  22. Slide 22: NHPC – Projects in Operation

    NHPC – Projects in Operation Tariff Installed Design S.N NHPC Project & Year of Completion 2013-14 Capacity Energy Type of the project o State comm. Cost (Rs. (MW) (MU) /Kwh) 1 Baira Suil , HP 180 (3x60) 779.28 1981 148.08 1.54 Run of River (ROR) with small pondage 2 Loktak, Manipur 105(3x35) 448.00

  23. Slide 23: NHPC – Projects in Operation

    NHPC – Projects in Operation Installed Design Tariff Completion S.No. NHPC Project Capacity Energy Year of Comm. 2013-14 Type of the project Cost (MW) (MU) (Rs. /Kwh) 11 Teesta-V, Sikkim 510(3x170) 2573.00 2008 2656.95 2.34 ROR with small pondage 12 Sewa-II, J&K 120(3x40) 533.52 2010 RC-1108.83 4.33

  24. Slide 24: NHPC – Operational Projects with Subsidiary

    NHPC – Operational Projects with Subsidiary S. Installed Design Year of Tariff 2013-14 Type of the N Project Capacity Energy Completion Cost Comm. (Rs./Kwh) project o (MW) (MU) Projects Completed with Subsidiary 1 Indirasagar, M .P 1000 1846.19 2005 4520.18 3.00 Storage (8x125) 2 Omkareshwar, 520 (8

  25. Slide 25: NHPC – Projects Under Construction

    NHPC – Projects Under Construction CCEA Provisional Estimated Anticipate Project Likely Installed Design Type of *Expected Cost (Rs. d Project Expenditur Tariff NHPC Project Capacity Energy the Commissioni Crore) Cost (Rs. e till – (Rs. (MW) (MU) project ng Schedule (Price Crore) Mar’14 (Rs. /kwh) L

  26. Slide 26: NHPC Standalone Projects Under Clearance

    NHPC Standalone Projects Under Clearance Installed Design Cost S.No. Projects Capacity Energy (In Crore) Status (MW) (MUs) & PL In the PIB Meeting on 23.10.2013, project was Kotli Bhel–IA (3x65) 2091.85 recommended for investment subject to 1 195 1025 (Uttarakhand) (May 13) clearance from Supreme Co

  27. Slide 27: NHPC - Projects Under Clearance

    NHPC -Projects Under Clearance Projects Under JV Installed Design Cost (In Cr.) S.No Projects Capacity Energy Status & PL (MW) (MUs) Chenab valley Power Projects Ltd. 1 (JV between NHPC (49%) JKSPDC (49%), & PTC (2%) Pakaldul (4x250) 8814.25 i) 1000 3330.18 The PIB Proposal is agreed in principle. J

  28. Slide 28: NHPC – Projects Under Pipeline

    NHPC –Projects Under Pipeline S. No. Projects State Installed Capacity (MW) Projects Under FR/DPR Preparation 1 Bursar Jammu & Kashmir 1020 2 Dhauliganga Intermediate Uttarakhand 210 3 Gauriganga-IIIA Uttarakhand 120 Total 1350 Foreign Assignment Projects (FAP) 1 Chamkharchhu Bhutan 770 (Under discu