Slide 1: Mozambique Projects Update
Triton Minerals Ltd For personal use only Mozambique Projects Update 5th Graphite & Graphene Conference London 8 December 2015 Alfred Gillman Technical Director
Slide 2: Introduction
Triton Minerals Ltd For personal use only Introduction Company Introduction Project Location Project Status Projects Nicanda Hill Nicanda West DFS Product range Ancuabe
Slide 3: Disclaimer – Competent Person's Statement
Triton Minerals Ltd Disclaimer For personal use only Competent Person’s Statement The information in this presentation that relates to Mineral Resource estimate at the Nicanda Hill deposit on Balama North project is based on, and fairly represents, information and supporting documentation prepared b
Slide 4: Board and Management
Triton Minerals Ltd Board and Management For personal use only Board of Directors Chris Catlow B.Sc. Eng, F.ICC; Strong corporate finance background with 25 years experience in international Non Executive Chairman resource industry Alfred Gillman B.Sc (Hon), F.Aus.IMM (CP) 35 years of international
Slide 5: Location and Infrastructure
Triton Minerals Ltd Location and Infrastructure Cabo Delgado Province, Mozambique For personal use only 110kV power 2015 deep water port expanded capacity 2019/2020 sealed road 110kv power 2021 Nacala Port 200km
Slide 6: Key distinguishing elements
Triton Minerals Ltd Triton today … For personal use only KEY distinguishing elements 1 Two Flagship and World Class Projects in Mozambique Balama North 1.45Bt at 11.1%TGC ‐ world’s largest flake graphite deposit Ancuabe Jumbo‐dominant flake graphite deposit with untapped potential Economic Significa
Slide 7: TMG – Triton Mozambique Graphite
Triton Minerals Ltd TMG For personal use only Triton Mozambique Graphite Provides for a full range of concentrate products to suit off take customers US$/tonne 99 98 97 96 94 93 92 91 90 89 88 87 86 85 Concentrate Value Matrix
Slide 8: Targeted Relative Growth Profile
Triton Minerals Ltd Targeted Relative Growth Profile For personal use only Grid power to Pemba Port Upgrade Grid power to Nicanda Ancuabe installed complete Hill installed Steady-state production Triton-Yichang Manufacturing JV (Moz) R Balama North low production profile Balama North high production
Slide 9: Project Status
Triton Minerals Ltd For personal use only Project Status Project Deposit Recce Exploration Resource Scoping DFS Study Balama North Nicanda Hill Balama North Nicanda West Ancuabe T12 Ancuabe T16 Balama South
Slide 10: Nicanda Hill Resource
Triton Minerals Ltd Nicanda Hill Resource For personal use only Competent Person’s Statement The information in this report that relates to the Mineral Resource estimate at Nicanda Hill is based on, and fairly represents, information which has been compiled by Mr James Ridley. Mr Ridley is a Princip
Slide 11: Nicanda Hill Resource
Triton Minerals Ltd Nicanda Hill Resource For personal use only
Slide 12: Nicanda West
Triton Minerals Ltd Nicanda West For personal use only
Slide 13: Nicanda West
Triton Minerals Ltd Nicanda West For personal use only Nicanda West Nicanda West Flake Size standard hi-spec Mesh Micron Mass % Mass % 50 >300 12.6 6.7 -50 to100 150-300 40.2 37.1 Total >150 52.8 43.8 100 to -200 75-150 25.0 30.2 200 <75 22.2 26.0 Total <150 47.2 56.2 Recovery 97.4 96 Grade 96.1 97.
Slide 14: Definitive Feasibility Study
Triton Minerals Ltd Definitive Feasibility Study For personal use only Commenced on Nicanda Hill Nominal 100,000t/annum Phase 1 Binding off take for 100,000t/annum with Yichang Xincheng Graphite Co. Ltd (YXGC) Expanded DFS to incorporate Nicanda West DRA Global Flotation test work (SGS) Flowsheet De
Slide 15: Targeted Applications for Nicanda Graphite
Triton Minerals Ltd Targeted Applications For personal use only for Nicanda Graphite Expanded Emerging Graphite Technology Products Applications Foils Spherical graphite Composite sheets (LIB) Fire retardant insulation foam Graphene
Slide 16: Successful production of Value-added Materials using TMG
Triton Minerals Ltd Successful production of Value-added For personal use only Materials using TMG
Slide 17: Ancuabe
Triton Minerals Ltd For personal use only Ancuabe
Slide 18: Ancuabe
Triton Minerals Ltd Ancuabe For personal use only Regional VTEM completed Oct 2014 Drilling commenced June 2015 T12 discovery – August 2015 T16 discovery – October 2015 Initial resource estimate Q1-2016
Slide 19: Encouraging Flotation Results
Triton Minerals Ltd Encouraging Flotation Results For personal use only Ancuabe Ancuabe Flake Size Standard Battery‐spec Mesh Micron Mass % Mass % Super Jumbo 35 >500 43.2 42.6 Jumbo ‐35 to +48 300‐500 29.4 30.3 Large ‐48 to +80 180 to 300 15.6 13.8 Medium ‐80 to +100 150 to 180 3.3 2.5 Total >150 9
Slide 20: Ancuabe graphite positioned to attract highest possible basket prices
Triton Minerals Ltd Ancuabe For personal use only Ancuabe graphite positioned to attract highest possible basket prices US$/tonne 99 98 97 96 94 93 92 91 90 89 88 87 86 85
Slide 21: Key distinguishing elements
Triton Minerals Ltd Triton today … For personal use only KEY distinguishing elements 1 Two Flagship and World Class Projects in Mozambique Balama North 1.45Bt at 11.1%TGC ‐ world’s largest flake graphite deposit Ancuabe Jumbo‐dominant flake graphite deposit with untapped potential Economic Significa
Slide 22: Thank you
Triton Minerals Ltd For personal use only Thank you
Triton Minerals — 5th Graphite & Graphene Conference London 2015 on 6ix