Slide 1: Christmas Creek 2 – Analyst Site Visit
For personal use only Macmahon Holdings Limited Christmas Creek 2 – Analyst Site Visit 14 May 2013
Slide 2: Welcome to Site
2 For personal use only Welcome to Site
Slide 3: Project Overview
Project Overview $1.8 billion, 5 year Christmas Creek Mine For personal use only expansion awarded in January 2013. Limited Notice to proceed and ramp-up commenced 1 November 2012 Macmahon’s largest ever Mining contract Scope of works includes: • Drill and blast • Overburden removal • Ore harv
Slide 4: Rapid Ramp-up
Rapid Ramp-up For personal use only Successful recruitment campaign generating 21,875 Ramp-up Recruitment applications to date from 9,451 unique applicants 900 Fast-track recruitment and mobilisation of over 800 mining 800 700 and construction employees 600 500 Workforce comprised of experienc
Slide 5: Plant mobilisation
Plant mobilisation Mobilised and put to work 104 For personal use only dump trucks, 21 D10 dozers, 6 large excavators, 13 wheel loaders, 12 blast hole production drills and associated ancillary equipment Fleet includes the Komatsu 930E ultra-class trucks – some of the biggest in the country Ma
Slide 6: Infrastructure Delivery
Infrastructure Delivery For personal use only 1 x 4 bay workshop, including: • Lubricant tank farm, temporary offices, crib rooms and ablutions • 1 x dome store 2 x satellite facilities, each including: • Single bay workshop, refuelling station, office, crib rooms and ablutions 1 x minor facil
Slide 7: Production
Production For personal use only 4.00 Volume (millions BCM) 3.00 2.00 1.00 0.00 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Actual Volume Planned Volume 7
Slide 8: Production Forecast
Production Forecast For personal use only 80.00 70.00 60.00 Volume (millions) 50.00 40.00 30.00 20.00 10.00 0.00 2013 2014 2015 2016 2017 (1) Planned Volume Volume Outside Current Mine Plan (1) Current Mine Plan to May 2017 8
Slide 9: Project Update
Project Update For personal use only First ore harvested on 3 December 2012 – only 18 days after first employees landed on site Blast hole drilling commenced on 8 December 2012 Total productive material movement of approximately 10.2 million BCM at end of April 2013 Establishment and constru
Slide 10: Risk Management
Risk Management For personal use only Tyres • First year supplied by client • Increased allocation in latter years • Secured alternate sources Explosives • Supplied by client Fuel • Supplied by client Water • Ground water managed by client Initial recruitment • Full employment • Steady sta
Slide 11: Summary and Questions
Summary and Questions For personal use only 11
Slide 12: Christmas Creek – Analyst Site Visit
For personal use only Macmahon Holdings Limited Christmas Creek 2 – Analyst Site Visit 14 May 2013