Txnm Energy, Inc. · NYSE:TXNM

Txnm Energy — PNM Resources — Q2 2019 Earnings Presentation

24 slides from Txnm Energy's earnings presentation, Aug 2, 2019

  1. Slide 1: Q2 2019 Earnings Review

    Q2 2019 Earnings Review August 2, 2019

  2. Slide 2: Safe Harbor Statement

    Safe Harbor Statement Statements made in this presentation for PNM Resources, Inc. (“PNMR”), Public Service Company of New Mexico (“PNM”), or Texas‐New Mexico Power Company (“TNMP”) (collectively, the “Company”) that relate to future events or expectations, projections, estimates, intentions, goals,

  3. Slide 3: Opening Remarks and Overview

    Opening Remarks and Overview Pat Vincent-Collawn Chairman, President and CEO

  4. Slide 4: Financial Results and Key Highlights

    Financial Results and Key Highlights Financial Results Q2 2019 Q2 2018 YTD 2019 YTD 2018 GAAP EPS ($0.95) $0.48 ($0.72) $0.67 Ongoing EPS $0.37 $0.53 $0.50 $0.73 • Significantly milder temperatures impacted Q2 2019 earnings • GAAP earnings include $104 million after tax write-off from items previous

  5. Slide 5: San Juan Abandonment, Securitization and Replacement Power

    San Juan Abandonment, Securitization and Replacement Power ● Requests ● $283M undepreciated ● Recommended Abandonment Replacement Power Securitization abandonment of San investment in San Juan, scenario balances Juan coal plant after proceeds available to environment, cost and participation fund rep

  6. Slide 6: PNM and TNMP Regulatory Agenda

    PNM and TNMP Regulatory Agenda Filing Action Timing Docket No. PNM: Consolidated Application for NMPRC decision on abandonment/ San Juan (Abandonment, PNM filed July 1, 2019; NMPRC bifurcated application on securitization expected by April 2020, 19-00018-UT Securitization and July 10, 2019 decision

  7. Slide 7: Financial Overview

    Financial Overview Chuck Eldred Executive Vice President and CFO

  8. Slide 8: Q2 2019 Ongoing EPS Financial Summary and 2019 Guidance

    Q2 2019 Ongoing EPS Financial Summary and 2019 Consolidated Ongoing Earnings Guidance Q2 EPS Summary Q2 2019 Q2 2018 Change PNM Resources $0.37 $0.53 ($0.16) PNM $0.23 $0.38 ($0.15) TNMP $0.19 $0.19 $- Corporate/Other ($0.05) ($0.04) ($0.01) Note: Segment drivers included in appendix $2.05 2019 Earn

  9. Slide 9: Load and Economic Conditions

    Load and Economic Conditions • Weather was the most significant driver to sales volumes in Q2 2019 Q2 2019 Q2 2019 Weather Impacts Q2 2019 Q2 2018 Normal(1) vs. vs. Q2 2018 Normal(1) PNM Cooling Degree-Days 318 674 507 (52.8%) (37.3%) PNM EPS Impact ($0.07) $0.07 TNMP Cooling Degree-Days 1,015 1,097

  10. Slide 10: 2019 – 2023 Investment Plan

    2019 – 2023 Investment Plan $3.6B investment plan reflects $298M replacement power; $278M generation investment and $20M transmission investment $1,013 $26 $208 $699 $635 $27 $665 $34 $20 $22 $30 $47 $285 $571 $71 $44 $20 $59 $88 $43 $128 $88 $79 $82 (in millions) $98 $171 $169 $181 $201 $137 $366 $

  11. Slide 11: 2019 - 2023 Potential Earnings Power

    2019 - 2023 Potential Earnings Power Earnings Growth Target 5-6% Reflects recommended replacement power scenario, adds 2023 • Partial year of San Juan rate base in 2022, no remaining rate base in 2023 • Interim financing supports replacement power until securitization proceeds received mid-2022 2019

  12. Slide 12: Questions and Answers

    Questions and Answers

  13. Slide 13: Appendix

    Appendix

  14. Slide 14: Replacement Power Scenarios Considered

    Replacement Power Scenarios Considered Recommended Scenario 2 Scenario 3 Scenario 4 Scenario 1 - Hybrid San Juan Location No Fossil Fuel All Renewable • 280 MW gas(1) • 476 MW gas(1) • 40 MW battery(1) PNM Owned Resources - • 70 MW battery • 110 MW battery PNM Capex $298M $331M $243M $37M • 350 MW s

  15. Slide 15: Q2 2019 vs Q2 2018 EPS (Ongoing): PNM

    Q2 2019 vs Q2 2018 EPS (Ongoing): PNM PNM $0.38 Q2 2019 Key Performance Drivers ∆ EPS Decommissioning/reclamation trust income, net of fees $0.05 Interest expense savings $0.02 $0.23 Retail rate phase-in, including excess deferred income taxes $0.01 (before impacts resulting from lower sales volumes

  16. Slide 16: Q2 2019 vs Q2 2018 EPS (Ongoing): TNMP and Corporate

    Q2 2019 vs Q2 2018 EPS (Ongoing): TNMP and Corporate TNMP $0.19 $0.19 Q2 2019 Key Performance Drivers ∆ EPS Rate relief, including TCOS $0.02 Depreciation and property tax ($0.01) Weather ($0.01) Q2 2018 Q2 2019 Corporate Q2 2019 Key Performance Drivers ∆ EPS ($0.04) ($0.05) Lower effective tax rate

  17. Slide 17: 2019 - 2023 Potential Earnings Power

    2019 - 2023 Potential Earnings Power 2019 Ongoing Earnings 2020 Earnings 2021 Earnings 2022 Earnings 2023 Earnings Allowed Guidance Midpoint Potential Potential Potential Potential Return / Equity Avg Avg Avg Avg Avg Rate Ratio Return EPS Rate EPS Rate EPS Rate EPS Rate EPS Base Base Base Base Base

  18. Slide 18: EBITDA Guidance (Ongoing)

    EBITDA Guidance (Ongoing) Ongoing EBITDA (In millions) 2019E Midpoint Consolidated PNM Resources $566 PNM $373 TNMP $172 18

  19. Slide 19: Weather Impact

    Weather Impact PNM Q2 2019 Q2 2018 2019 Normal(1) Heating Degree Days 71 22 70 Cooling Degree Days 318 674 507 Net EPS Impact ($0.07) $0.07 compared to normal TNMP Q2 2019 Q2 2018 2019 Normal(1) Heating Degree Days 60 85 50 Cooling Degree Days 1,015 1,097 1,012 Net EPS Impact $0.00 $0.01 compared to

  20. Slide 20: PNM Scheduled Plant Outages

    PNM Scheduled Plant Outages San Juan Four Corners Palo Verde Duration Time Duration Time Duration Time Unit Unit Unit in Days Period in Days Period in Days Period 2019 planned outages completed 2019 planned outages completed 3 44 Q4 2019 20

  21. Slide 21: Balance Sheet and Credit Metrics

    Balance Sheet and Credit Metrics

  22. Slide 22: Liquidity as of July 26, 2019

    Liquidity as of July 26, 2019 PNMR PNMR PNM Develop- Corporate Resources PNM TNMP ment /Other Consolidated Financing Capacity(1): (In millions) Revolving credit facilities $440.0 $75.0 $40.0 $300.0 $855.0 As of 7/26/19: Short-term debt and LOC balances $56.9 $0.1 $32.9 $72.4 $162.3 Remaining availab

  23. Slide 23: Selected Balance Sheet Information

    Selected Balance Sheet Information (In millions) Dec 31, 2018 June 30, 2019 Long-Term Debt (incl. current portion) (1) PNM $1,656.5 $1,707.3 TNMP 575.4 626.4 Corporate/Other 438.2 438.6 Consolidated $2,670.1 $2,772.3 Total Debt (incl. short-term) (1,2) PNM $1,698.9 $1,749.5 TNMP 592.9 681.4 Corporat

  24. Slide 24: Credit Ratings

    Credit Ratings PNMR Consolidated S&P Moody’s Issuer rating BBB+ Baa3 Outlook Negative Stable Senior unsecured rating BBB Baa3 PNM S&P Moody’s Issuer rating BBB+ Baa2 Outlook Negative Stable Senior unsecured rating BBB+ Baa2 TNMP S&P Moody’s Issuer rating BBB+ A3 Issuer outlook Negative Stable Senior

PNM Resources — Q2 2019 Earnings Presentation on 6ix