Digilogic Systems Ltd. · BSE:DIGILOGIC
Digilogic Systems — Corporate Update (February 2026)
28 slides from Digilogic Systems's corporate update, Feb 20, 2026
Slide 1: Digilogic: Regulation 30 filing letter to BSE
A digilogic: An AS9100D Certified Compa ny MBf innovative solutions Fe bruary 20 , 2026 To B SE Limi ted Phi roze Jeej eeb hoy Towers, Da l a l Street, Mumbai-400 001. S cr ip Code ; 544684 D ea r S i r/Mad a m , S ub: Presentation on Project Udaan under Regul ati on 30 of SEB I (Listing Obligations
Slide 2: Digilogic Systems Limited - Project Udaan
DIGILOGIC SYSTEMS LIMITED Est. 2007 Project Udaan
Slide 3: Safe Harbor Statement
Safe Harbor Statement This document has been prepared for information purposes only and is not an offer or invitation or recommendation to buy or sell any securities of DIGILOGIC Systems Limited (“DSL”, “DIGILOGIC”, "Company“), nor shall part, or all, of this document form the basis of, or be relied
Slide 4: About DIGILOGIC
About DIGILOGIC • DIGILOGIC established in 2007 as Partnership Firm was converted into Private Limited in 2011 & Limited in 2025. DIGILOGIC was listed on BSE SME in January 2026. • Headquartered in Hyderabad, DIGILOGIC has a marketing office in Bengaluru with plans to expand presence Pan India. • DI
Slide 5: About Project Udaan
About Project Udaan DIGILOGIC in January 2026 successfully completed its maiden public issue on BSE SME. One of the major objectives of the issue was setting up a new facility to manufacture electronic sub-systems, environmental stress screening, section level integration of sub-systems and capa
Slide 6: Project Udaan Details
Project Udaan Details
Slide 7: Project Udaan location
Project Udaan location Site Located in Telangana Industrial Infrastructure Corporation (TGIIC) Hardware Park, Phase II, Hyderabad, Telangana State. Total Area of Land – 2 Acres
Slide 8: Various Approvals in place for Project Udaan
Various Approvals in place for Project Udaan Sr. No. Approval Authority Status 1 Permission from Ground Water Ground Water Department, Telangana Received Department to dig bore well 2 Building Plan Approval Industrial Area Local Authority (IALA) / Telangana Received Industrial Infrastructure Corpora
Slide 9: Timelines of the Project
Timelines of the Project Activity Timelines Land Purchase Sep 2025 (Since Completed) Land Development Sep 2025 – Mar 2026 (In progress) Building construction Apr 2026 – May 2027 Machinery ordering Dec 2026 – Feb 2027 Machinery erection Jun 2027 – Jul 2027 Trial Run Oct 2027 – Nov 2027 Commencement o
Slide 10: DIGILOGIC Capabilities: Existing and Project Udaan
DIGILOGIC Capabilities Existing Project Udaan ➢ Test Systems ➢ Manufacturing of Electronic Sub-Systems ➢ Automated Test Systems & Test Jigs (EMS) ➢ Checkout Systems ➢ Build to Spec ➢ Radars & Electronic Warfare Simulators ➢ Build to Print ➢ Application Software ➢ In-house capability of Environmental
Slide 11: Manufacturing of Electronic Sub-Systems (EMS) under Project Udaan
1. Manufacturing of Electronic Sub- Systems (EMS) under Project Udaan An ELECTRONIC MANUFACTURING FACILITY—often referred to as an Electronic Manufacturing Services (EMS) provider—is a specialized "one-stop shop" that handles the manufacturing, assembly, and testing of electronic components and fini
Slide 12: Proposed P&M for EMS activities
Proposed P&M for EMS activities Cleaning Machine PCB Router Machine Reflow Oven based Solder Machine Optical Inspection Machine Stencil Print Machine
Slide 13: Proposed P&M for EMS activities
Proposed P&M for EMS activities BGA Solder Station Solder Paste Inspection Hot Air Rework Station
Slide 14: In-house capability of Environmental Stress Screening & Qualification
2. In-house capability of Environmental Stress Screening & Qualification (ESS) under Project Udaan ➢ The Environment Stress Screening Facility is a specialized lab which is used to validate Line Replaceable Unit (LRU) to mechanical and extreme environment stresses. ➢ This facility helps simulate rea
Slide 15: Proposed P&M for ESS activities
Proposed P&M for ESS activities Some commonly found Machines at such Stress Screening Facilities are: Shock Test Machine Vibration Test Machine Bump Test Machine Acceleration Test Machine Environment Test Chamber
Slide 16: Capacity expansion of Test Systems under Project Udaan
3. Capacity expansion of Test Systems under Project Udaan
Slide 17: Capacity expansion of Test Systems under Project Udaan
3. Capacity expansion of Test Systems under Project Udaan Production Ready Facility Capable of Integrating Multiple Test Systems. Multiple Units can be integrated, programmed and tested simultaneously. State of the art integration facility adhering to ISO-9001 and AS-9100D standards.
Slide 18: Capacity expansion of Cable Harness under Project Udaan
3. Capacity expansion of Cable Harness under Project Udaan
Slide 19: Capacity expansion of Cable Harness under Project Udaan
3. Capacity expansion of Cable Harness under Project Udaan A cable harness is an organized assembly of electrical cables or wires bundled together to transmit power and/or signals efficiently within a system. It simplifies complex electrical layouts by consolidating multiple cables into a single m
Slide 20: Proposed Master Plan
Proposed Master Plan 65,000 to 70,000 sft of built-up area
Slide 21: Proposed Floor Plan - Ground
Y make ININDIA ial OUEOKISe ((MEEIING ROOM Proposed Floor Plan -Ground | j | Patina Partner nt Towson meen hee cevnre Wwoxne | (caraeiteta aPRo 0G oO =~ = bd | bc fa) dlp re 7/5 PLATSORM FOR CHILERS ‘2Mi/ EMC TEST FACLTY Sexe even fa as =| CORRIDOR ss vp urTLosey, wie WORKSTATION — C) FEcernoNwamnc
Slide 22: Proposed Floor Plan - First
SRECABIN-| 1204119" Y make IN INDIA oo f et ame can, Proposed Floor Plan - First nt DIGILOGIC’ innovative solutions {MEETING ROOM 267X117 TESTING AND EVAWATION ROOM " 7 sseney WORK sTADON > 3031 (carne 12 A980) a fof PASSAGE 100" WIDE CoRRDOR 10" ‘sou orator sexta INTERGRATION ROOM, BELOW . eee eisr
Slide 23: Proposed Floor Plan - Second
Y make ININDIA Proposed Floor Plan - Second Platinum Partner n a a LANDSCAPE 0) eos Seem Cay ae eB | — c VP LOUNGE 2eaKI7e of ‘ANTE ROOM WOXI8s PASSAGE 100° WIDE KITCHEN/STORE Ioxies" HANDWASH KITCHEN 133xI70" U! oa | kL ems ini ioe eRe) CoRRDOR 80” XY qi/bd|pq | Pir cHaserrivakice DEPARTMENT Topas
Slide 24: Visual representation of proposed facility
Visual representation of proposed facility
Slide 25: Visual representation of proposed facility
Visual representation of proposed facility
Slide 26: Visual representation of proposed facility
Visual representation of proposed facility
Slide 27: DIGILOGIC Estimates including Project Udaan
DIGILOGIC Estimates including Project Udaan Value in Crores Overall FY 26 FY 27 FY 28 FY 29* FY 30* FY 31* Revenue 84 ~ 90 105 ~ 111 133 ~ 140 179 ~ 189 242 ~ 255 328 ~ 346 (Overall) Existing 84 ~ 90 105 ~ 111 133 ~ 140 168 ~ 176 214 ~ 225 271 ~ 285 New N/A N/A N/A 11 ~ 13 28 ~ 30 57 ~ 61 EBITDA 17
Slide 28: Please feel free to reach out for further information
Please feel free to reach out for further information on Mr. Sri Harsha, CFO #102, 1st Floor, DSL Abacus Tech Park, Beside DSL Virtue Mall, Uppal, Hyderabad, Telangana – 500039 Ph: 040 - 4547 4601 / 02 / 03 Investor.relations@digilogicsystems.com