Ampol Limited · ASX:ALD
Ampol — Corporate Update (May 2022)
9 slides from Ampol's corporate update, May 4, 2022
Slide 1: Kurnell community update
ner 5 \ \ EOE Mita a \ E ws, | | ‘ by a mes | ae | : ' es Us Hy] Kurnell community upd 4 May 2022 ao y/"
Slide 2: Remediation zones map
Zone 3 West Zone 8 Zone 3 East Zone 4 Zone 5 Zone 2 Zone 6 Zone 7
Slide 3: Remediation progress by zone
Remediation progress by zone Remediation work is progressing in impacted areas, working with local stakeholders and asset owners Testing work is being done in parallel to validate works || Zone % complete comments North side of Torres Street and Captain Cook Drive 1 (includes soil testing) Horse Are
Slide 4: Ampol Kurnell project plan
Ampol Kurnell project plan In addition to the ongoing clean up and remediation activities shared, Ampol has developed a plan with defined workstreams to sustainably address the consequences of this incident and to prevent a re-occurrence of another similar incident Develop and implement an EPA suppo
Slide 5: Emergency response
Emergency response In the event of a future incident regardless of whether the impact is on-site or off-site the Kurnell Terminal Emergency Response Plan will be activated. The plan includes — Sounding of the site alarm and safe shutdown of all operational activities on-site Activation of the Local
Slide 6: Updates and getting in touch
Updates and getting in touch Ampol continues to post daily updates on remediation and clean-up works — these can be accessed on our website - Kurnell Update | Ampol A new 24/7 community email and phone number has been established — 1800 719 669 or community@ampol.com.au to connect community directly
Slide 7: Ongoing communications and engagement
Ongoing communications and engagement * The community has provided great feedback, we are listening, and we want to work with you * Anew community relations role is being recruited to be based in Kurnell * The community has advised that it wants more information on the remediation and wants to be in
Slide 8: Testing results and ongoing work
Testing results and ongoing work Further sampling of public areas . Soil sampling was undertaken within the football field on 20 April 22. Five (5) locations analysed - all concentrations below relevant criteria for the protection of human health * Water sampling from the Marton Park (13 April 22) a
Slide 9: Thank you
VA AMPOL Thank you