Slide 1: Angas Mine – SCCC Presentation
Angas Mine – SCCC Presentation Welcome to all, our SCC Committee, local business owners, employees and interested community members. Current Status – Care and Maintenance as of 31st October Why Care and Maintenance - Economics – Currently mined 1.9Mt of the approved reserve of 2.5Mt. – Sunter
Slide 2: What's happening at Angas Zinc?
What's happening at Angas Zinc? 6 employees remaining on site Mine has been placed under Care and Maintenance Clean-up work, water and environmental management and monitoring to continue. Processing plant including mill and floatation area receiving weekly maintenance Mobile and other equi
Slide 3: Focus for Current Operations
Focus for Current Operations Working with DMITRE to ensure ongoing compliance Water, Dust and Environmental management TSF management Mine void AMD management TERRAMIN AUSTRALIA LIMITED
Slide 4: Angas Zinc Mine — Long section
Angas Zinc Mine — Long section Filled and unfilled voids Un-filled Voids Filled Voids i || Stopes gems | Drives (tunnels)
Slide 5: The Future - Potential Bird-in-Hand
The Future - Potential Bird-in-Hand Terramin has acquired 100% of the Bird-in-Hand gold project and exploration tenements Gold resource hosted in carbonate bedrock Extensive studies, modeling and risk assessments are required for regulatory approvals for both Angas Zinc Mine and Bird-in-Hand p
Slide 6: Mining and Processing (Quarter 3, 2013)
Mining and Processing (Quarter 3, 2013) Completed all development to the 380 metre level A total 98,110 tonnes of ore was processed 10,933 tonnes of zinc concentrate 6,148 tonnes of lead copper concentrate Total ore mined to date (EOM Sept 2013): 1,989,251 tonnes TERRAMIN AUSTRALIA LIMITED
Slide 7: AZM fast facts
AZM fast facts Commenced mining in March 2007 119 full time employees 120,000 tonnes of Zinc, 46,500 tonnes of Lead and 1,584,461 ounces of Silver produced Remained operating despite the GFC induced zinc price fluctuations, from $5000/tonne to a low of $1500/tonne Water management was a ch
Slide 8: Quarterly Environment Report
Angas Zinc Mine Quarterly Environment Report Quarter 3: July - Sept 2013 M. Daniel TERRAMIN AUSTRALIA LIMITED
Slide 9: Environmental Activities
Environmental Activities Updated closure plan submitted Fencing works to exclude hares from SEB areas Weed control and fire management works Native seed collection Heritage tree photo monitoring TSF ET cap pseudo trial established and seeded (October) Waste Management in preparation for
Slide 10: Community Activities
Community Activities Student placements for environmental work experience UrrbraeTafe University of Adelaide TERRAMIN AUSTRALIA LIMITED
Slide 11: Community feedback & environmental incidents
Community feedback & environmental incidents No environmental incidents were recorded during quarter 3 9 registered community complaints: Nine noise complaints from three local residents regarding noise at night – Three possibly from the paste plant, appeared to originate from the vibrator fit
Slide 12: Noise September Monitoring - West results (Boxcut side)
Noise September Monitoring - West results (Boxcut side) TERRAMIN AUSTRALIA LIMITED
Slide 13: Noise September Monitoring - East results (Mill side)
Noise September Monitoring -East results (Mill side) TERRAMIN AUSTRALIA LIMITED
Slide 14: Acid Mine Drainage - TSF Decant Pond Surface Area
Acid Mine Drainage - TSF Decant Pond Surface Area The TSF Decant pond remains in compliance (<15,000m2) Current surface area <4,000m2 at RL 66.89 on the 19th of November TERRAMIN AUSTRALIA LIMITED 7th March 2013 TSF Western Wall 19th November 2013 TSF Western Wall
Slide 15: Acid Mine Drainage - TSF Decant Pond RL
Acid Mine Drainage - TSF Decant Pond RL RL – 66.89m on 19th November 2010 2011 2012 2013 TERRAMIN AUSTRALIA LIMITED
Slide 16: Upcoming Activities for Q3 2013
Upcoming Activities for Q3 2013 Fencing out of hares from the SEB paddocks Closure Plan Updating Recycling of scrap steel and plastic TSF monitoring, water management, & injecting bore water into the mine void Grouting of exploration drill holes that are no longer required Further weed a
Slide 17: Mine Closure Plan
Mine Closure Plan The first stage plan is with the SCCC for comment, have incorporated FMEA risk assessment workshop identified risks and mitigation strategies The ML is split into four discrete domains, each with its own final land use plan Some general comments on each domain is below North Do
Slide 18: Mine Closure plan
Mine Closure plan Central Domain Land use will be industrial and Extractive Mineral Lease Underground mining voids currently 93% filled (91% required), inject water into mine void for AMD management Fill decline and vent raise, remove mill & water dams, undertake soil contamination assessment,
Slide 19: Mine closure plan
Mine closure plan Southern Domain Landuse is to be open grassland/shrub-land with biodiversity value Evaporate all remaining TSF water, when enough moisture removed, place fill onto tails and contour to design, re-vegetate Grazing excluded for 3 reasons; Ecosystem Function Analysis required by
Slide 20: Thank you
Thank you TERRAMIN AUSTRALIA LIMITED