Heavy Minerals — NWR Virtual Conference (September 2022)

17 slides from Heavy Minerals's conference presentation, Sep 15, 2022

  1. Slide 1: ASX Announcement: Revised Corporate Presentation

    ASX Announcement Date: 15 Sept 2022 REVISED CORPORATE PRESENTATION - NWR VIRTUAL CONFERENCE Heavy Minerals Limited (ACN 647 831 833) (“HVY”, “Heavy Minerals” or the “Company”) would like to provide the attached revised corporate presentation. There was an omission of information in accordance with A

  2. Slide 2: Focused on Industrial Minerals

    FOCUSED ON Industrial Minerals SEPTEMBER 2 0 2 2 | A S X : H V Y

  3. Slide 3: Important Notice

    Important Notice This presentation has been prepared by Heavy Minerals Limited and its related entities (the “Company”). It does not purport to contain all the information that a prospective investor may require in connection with any potential investment in the Company. You should not treat the con

  4. Slide 4: Presentation Outline

    Presentation Outline • Investment Highlights • Capital Structure • Board of Directors • Projects Overview • Port Gregory Project • Scoping Study Results • Simple Mining • Garnet to 2030 • Red Hill Discovery • Inhambane Mineral Sands Project • Inhambane Mineral Resource • Market Outlook – Mineral San

  5. Slide 5: Investment Highlights

    Investment Highlights Heavy Minerals Limited (HVY) is an Emerging Industrial Minerals Explorer with Projects adjacent to world class deposits in pro-mining jurisdictions • Western Australia – Port Gregory Project: JORC Mineral Resource 135 MT @ 4.0% THM containing 4.9 Mt Contained Garnet Titanium In

  6. Slide 6: Capital Structure

    Capital Structure1 Directors 18.9% ASX CODE SHARES ON ISSUE1 MARKET CAP1 Retail HVY 56.43M $9M 33.5% CASH2 DEBT1 EV3 Remaining Top 20 $2.41M nil $6.6M 47.6% Position Holder Name % IC 1 CHRISTOPHER ADAM SCHOFIELD 4,104,283 7.27% 2 GLENN SIMPSON 3,963,445 7.02% 3 MR KENNETH JOSEPH HALL 3,846,071 6.81%

  7. Slide 7: Board of Directors

    Board of Directors Adam Schofield GREG JONES GLENN SIMPSON Non-Executive Chairman Non-Executive Director Non-Executive Director Mr. Schofield is a mining company Over 25 years’ experience as a mineral sands Mr. Simpson has been a Chartered executive with over 20 years’ experience Geologist with Iluk

  8. Slide 8: Projects Overview

    Projects Overview Port Gregory Garnet Project Two projects with the potential to grow into globally significant mineral sands (100 km North of Geraldton, Western Australia) resources. Both Projects adjacent to Tier 1 Assets (GMA, RDG & Rio Tinto). • 4.9 Mt contained Garnet (~5 years of Global demand

  9. Slide 9: Port Gregory Project

    Port Gregory Project JORC Mineral Resource 135 MT @ 4.0% THM THM Assemblage (2) Summary of Mineral Resource estimate (1) Classification 4.9 Mt contained garnet (96% VHM fraction in THM) Material (Mt) In Situ THM (Mt) In Situ Garnet (Mt) THM (%) SL (%) OS (%) Garnet (%) Ilmenite (%) Zircon (%) Rutile

  10. Slide 10: Scoping Study Results

    Scoping Study Results • Substantial NPV8 (real) of AUD$253M relative to HVY market capitalisation of $9.96M (at 18.5 cps) AUD$253M 4.2 years AUD$1.59B After Tax NPV Payback period LOM Revenue • 16-year mine life with the potential to extend with further successful drilling (planned for 2022) • Low C

  11. Slide 11: Simple Mining

    Simple Mining Production Method Production flow diagram • Conventional dozer trap mining (MUP) • 488 TPH to produce a slurry that is pumped to a Wet Concentration Plant (WCP) • Heavy Mineral Concentrate (HMC) is produced via processing the sand fraction through a series of gravity spirals and up-cur

  12. Slide 12: Garnet to 2030

    Garnet to 2030 HVY’S unique opportunity is the Global average (nominal) Garnet price (unrefined)1 significant and widening supply deficit Current price (USA3) forecast from 2022 onwards2 540 kt deficit in 2030 without new sources of supply TZMI 2021 long-term forecast price of US$210 per tonne (inde

  13. Slide 13: Red Hill Discovery

    Red Hill Discovery Red Hill prospect: 37 km south of Port Gregory Project HVY will continue exploration of its tenure for garnet and High grade garnet from surface other industrial minerals Analogous to the Port Gregory Project High Priority Exploration target AC drilling in Q3 2022 Red Hill highlig

  14. Slide 14: Inhambane Mineral Sands Project

    Inhambane Mineral Sands Project OWNERSHIP 213.8 km2 of tenure under mining application: Adjacent to HV power, road and the Port of Inhambane. 70% 30% Mining Concession application lodged (25-year tenure), Heavy Minerals Local pending regulatory approvals Partners JORC Inferred Mineral Resource of 90

  15. Slide 15: Inhambane Mineral Resource

    Inhambane Mineral Resource Inhambane 2022 metallurgy results1 – Highly marketable product suite (No roasting): Primary ilmenite containing 49.8% TiO2 , 0.6% SiO2, 0.4% Al2O3 and <0.1% Cr2O3 Zircon containing 66% Zr02 with < 500ppm U + Th High Titanium product containing > 90% Ti02 1 W E Potential st

  16. Slide 16: Market Outlook – Mineral Sands

    Market Outlook – Mineral Sands1 Heavy Mineral Sands Market Dynamics – Rapid uplift in pricing over the last 18 - 24 months Existing producers are seeing an increase in pricing Full suite of valuable heavy minerals (VHM) have on the full suite of valuable heavy minerals (VHM) seen growth over the pre

  17. Slide 17: www.heavyminerals.com

    Registered Office: Level 8, London House 216 St Georges Terrace Perth Western Australia 6000 Phone: (08) 9481 0389 Fax: (08) 9463 6103 Email: info@heavyminerals.com www.heavyminerals.com