  1. Slide 1: Sika

  2. Slide 2: Sikadur 55 SLV Application Instructions

    Construction Sikadur 55 SLV Application Instructions Sika Corporation

  3. Slide 3: Sikadur 55 SLV

    Construction Sikadur 55 SLV  Epoxy crack healer and penetrating sealer  Fast tack-free time  100% solids  Super low-viscosity  Moisture-tolerant  High-strength  Two-component Sika Corporation

  4. Slide 4: Where to use

    Construction Sikadur 55 SLV  Where to use: • Structurally repairing cracked concrete • Interior and above-grade slabs • Elevated horizontal decks, parking garages and other structures exposed to foot and pneumatic tire traffic Sika Corporation

  5. Slide 5: Packaging and coverage

    Construction Sikadur 55 SLV  Packaging: • 3 gal. units (2 gal. ‘A’ + 1 gal. ‘B’)  Coverage: • 1 gal. yields 231 in3 Sika Corporation

  6. Slide 6: Surface Preparation

    Construction Surface Preparation  Surface must be clean and sound.  Remove dust, laitance, grease, curing compounds, impregnations, waxes and any other contaminants by mechanical means before application  Substrate should be dry for best results  Surfaces prepared by Low Pressure Water Cleaning

  7. Slide 7: Tools Required

    Construction Tools Required  ½” drill motor  Low speed drill (400-600 rpm)  Drill and paddle for mixing  Spatula Sika Corporation

  8. Slide 8: Mixing

    Construction Mixing  Mix 1 part Component ‘B’ to 2 parts Component ‘A’ by volume into a clean pail  Mix thoroughly for 3 minutes with Sika paddle on low-speed (400-600 rpm) drill until uniformly blended  Mix only that quantity that can be used within pot life Sika Corporation

  9. Slide 9: Application: gravity feed into cracks

    Construction Application  To gravity feed into cracks: • Sikadur 55 SLV is applied to horizontal surfaces by flat squeegee or broom. • Spread material over area and allow to pond over cracks. • Let material penetrate into cracks and substrate. • Remove excess epoxy with roller leaving no visible su

  10. Slide 10: Application: gravity feed into cracks (continued)

    Construction Application  To gravity feed into cracks: • A second treatment may be required on very porous substrates. • Apply second treatment before broadcasting • After treatment, wait at least 20 minutes at 73°F (23°C). • Cover with broadcast of an oven- dried 20/40 silica sand or similar sand.

  11. Slide 11: Application: pressure-inject cracks

    Construction Application  To pressure-inject cracks • Use automated injection equipment or manual method. • Set appropriate injection ports based on system used. • Seal ports and cracks with Sikadur 31, Hi-Mod Gel, Sikadur Injection Gel or Sikadur AnchorFix-3/4 • When the epoxy adhesive has cured,

  12. Slide 12: Precaution

    Construction Precaution  Avoid skin and eye contact  Wear • chemical resistant gloves • goggles  Ventilate area  Dispose of in accordance with local, state and federal regulations  Uncured material can be removed with approved solvent  Follow manufacturer’s warnings and instructions for use Si

  13. Slide 13: Sika Product Data Sheets

    Construction Sikadur 55 SLV Sika Product Data Sheets can be obtained via: http://usa.sika.com Refer to data sheets for specific information on each Sika product. Sika Corporation