  1. Slide 1: 2023 Third Quarter Investor Call

    AV I AT I O N INFRASTRUCTURE R E A L E S TAT E 2023 Third Quarter Investor Call November 14th, 2023

  2. Slide 2: Disclaimer

    DISCLAIMER General This presentation and information provided at a webcast or meeting at which it is presented (the “Presentation") is for informational purposes only to assist investors, prospective investors and other parties in making their own evaluation with respect to Sky Harbor Group Corporat

  3. Slide 3: Disclaimer: Financial Information; Non-GAAP Financial Measures

    DISCLAIMER Financial Information; Non-GAAP Financial Measures Certain financial information and data contained in this Presentation is unaudited and does not conform to Regulation S-X or Regulation G. Accordingly, such information and data may not be included in, may be adjusted in, or may be presen

  4. Slide 4: Presenters

    Presenters Tal Keinan Francisco Gonzalez Tim Herr Founder, Chair & CEO CFO Treasurer / VP Finance Michael Schmitt Tori Petro Chief Accounting Officer Senior Finance Associate 3 ©2023 Sky Harbour Confidential and Proprietary

  5. Slide 5: On Track to Positive Operating Cash Flow on a Consolidated Basis in 2024

    On Track to Positive Operating Cash Flow on a Consolidated Basis in 2024 Cost of Construction and Constructed Assets Quarterly Quarterly Revenues Revenues Operating Expenses (in millions) (in (inmillions) millions) (in millions) 2 2 3 140 1.8 1.8 120 2.5 1.6 1.6 1.4 100 1.4 2 1.2 1.2 80 11.5 1 60 0.

  6. Slide 6: Scale: In pursuit of high-quality square footage

    Scale: In pursuit of high-quality square footage Rentable Square Footage In Development and Under Exclusive Rentable Square Footage in Operation Ground Lease Negotiation (total square feet) (total square feet) 2,000,000 3,000,000 1,800,000 2,500,000 1,600,000 1,400,000 2,000,000 1,200,000 1,000,000

  7. Slide 7: Business Updates

    Business Updates • Site Acquisition • Development – Manufacturing and Construction • Leasing • Airfield Operations • Market Landscape • Lessons Learned • Business Strategy 6 ©2023 Sky Harbour Confidential and Proprietary

  8. Slide 8: Site Acquisition

    Site Acquisition Long Cycle Time; High Throughput • Sites in Operation • SGR, BNA, OPF • Sites in Development • DVT, APA, ADS • Sites in Permitting • PWK • New ground leases expected in Q4: 2 • New ground leases expected in H1: 3 7 ©2023 Sky Harbour Confidential and Proprietary

  9. Slide 9: Development Manufacturing Construction

    Development Manufacturing Construction Moving from EFFECTIVE to EFFICIENT RapidBuilt • Integration update • Ambition for RapidBuilt Expected Estimated Cost Rentable Facility Completion Date ($mm) Square Footage In Operation SGR Q4 2020 $10.5 66,080 BNA Q4 2022 $25.7 149,069 OPF I Q1 2023 $32 160,092

  10. Slide 10: Leasing

    Leasing From experimental concept to clear value proposition Current occupancy • SGR – 94% • BNA – 86.4% • OPF – 62.5% First member evangelists Articulation of value proposition Rising rental rates and re-ups 9 ©2023 Sky Harbour Confidential and Proprietary

  11. Slide 11: Airfield Operations

    Airfield Operations Delivering a unique, truly -differentiated offering • Safety report • Service gaps report • Tenant feedback • New services 10 ©2023 Sky Harbour Confidential and Proprietary

  12. Slide 12: Market Landscape

    Market Landscape Ta i l w i n d s p r e v a i l Demand growth • OEM deliveries + • Useful airframe life growth = • Hangar deficit growing more acute each year Competitive landscape • FBO consolidation • Airport demand for hangar versus transient services Validation and recognition of Sky Harbour Mod

  13. Slide 13: Lessons Learned

    Lessons Learned Transitioning from prototype to production Site Acquisition • Target throughput versus cycle-time • Articulation of Sky Harbour value proposition to airport sponsors • Team: Veteran edge Integration Function Development • Effective integration of manufacturing and construction requir

  14. Slide 14: Our Cash is Earning Higher Rates than the Cost of our Debt

    Our Cash is Earning Higher Rates than the Cost of our Debt Series 2021 Bond Debt Service (in millions) $130,000,000 14 U.S. Treasuries and Cash As of September 30th 12 10 8 $97,015 6 4 2 0 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2054 Bond Principal Bond Interest (millio

  15. Slide 15: New PIPE Equity Provides Growth Capital for Next Several Campuses

    New PIPE Equity Provides Growth Capital for Next Several Campuses Size $42,810,000* (first close) Shares 6,586,154 Class A shares 1,141,600 Warrants Price per Share ~$6.50 (inclusive of warrant coverage) Purchaser Funds managed by Altai Capital Investors through Altai include 8VC, RAGA Partners and

  16. Slide 16: Illustrative Scaling of Business and Unit Economics

    Illustrative Scaling of Business and Unit Economics Airfields 12 20 50 Total Capital $600,000,000 $1,100,000,000 $3,000,000,000 Assumptions Total Debt $420,000,000 $792,000,000 $2,400,000,000 • Average airfield development cost projected to grow over time from current levels at CPI Leverage 70% 72%

  17. Slide 17: SkyH Capital is Fully Funded for the "2021 PABs Project" as Amended

    SkyH Capital is Fully Funded for the “2021 PABs Project” as Amended $113,500,000 U.S. Treasuries and Cash as of September 30th at Sky Harbour Capital LLC $8,417 $11,962 $80,156 $4,047 $2,459 $33,392 $86,661 Construction Capitalized Interest Debt Service Reserve Cash Treasuries Ramp Up Reserve Revenu

  18. Slide 18: Operating Cash Flow Turned Positive at Sky Harbour Capital

    Operating Cash Flow Turned Positive at Sky Harbour Capital Cost of Construction and Constructed Assets Quarterly Revenues Operating Expenses (in millions) (in millions) (in millions) 2 140 3 1.8 120 2.5 1.6 1.4 100 2 1.2 80 1 1.5 60 0.8 40 1 0.6 0.4 20 0.5 0.2 0 0 Q4'21 Q1'22 Q2'22 Q3'22 Q4'22 Q1'23

  19. Slide 19: Permanent Capital: Key to Prudent Funding of Growth Capital Opportunistically

    Permanent Capital: Key to Prudent Funding of Growth Capital Opportunistically Internally Generated Cash Flow SKYH Holding Company Equity • In lieu of a portion or all dividends in the • Public ATM or marketed offerings early years • PIPEs Growth Capital Project level Partnerships with Private Activi

  20. Slide 20: Q3 in Pictures: The Sky Harbour Team in Action

    Q3 in Pictures: The Sky Harbour Team in Action 19 ©2023 Sky Harbour Confidential and Proprietary

  21. Slide 21: Business Strategy

    Business Strategy Site Acquisition: Current position good Development: • Effective to Efficient • HR scale-up Member Leasing: Brand strategy roll-out including member-ambassadors Airfield Operations: • Near term: Continued focus on #1 safety and efficacy • Medium term: Roll-out third-party services

  22. Slide 22: A Specialized Real Estate Platform – Question & Answer Period

    AV I AT I O N INFRASTRUCTURE R E A L E S TAT E A Specialized Real Estate Platform ____________________________________ Question & Answer Period ©2023 Sky Harbour Confidential and Proprietary 21