Nordic Mining Asa · OSL:NOM

Nordic Mining Asa — Investor Presentation (September 2019)

35 slides from Nordic Mining Asa's investor presentation, September 2019

  1. Slide 1: Minerals for a sustainable future

    Large deposit with unique location Quality offtake partners Robust project Minerals for a sustainable future economics Strong competitive OAX: NOM position Valuable investment in lithium Investor presentation September 2019

  2. Slide 2: Disclaimer

    Disclaimer IMPORTANT NOTICE The presentation (the "Presentation") has been prepared by Nordic Mining ASA ("Nordic Mining" or the "Company") with the assistance of SpareBank 1 Markets AS (the "Financial Advisor") , solely for use at a presentation to future potential investors (the "Investors") in th

  3. Slide 3: Risk factors

    Risk factors Key risks specific to Nordic Mining or its industry Key risks specific to the securities • Development of the Group’s assets will depend upon the Group's ability to • The price of the Shares could fluctuate significantly obtain financing • Future sales, or the possibility for future sal

  4. Slide 4: Table of contents

    Table of contents 1 Introduction 1 Introduction 2 Engebø – rutile and Engebø – rutile and garnet 2 garnet 3 Keliber – lithium3 Keliber – lithium 4 Summary 4 Summary 5 Appendix 5 Appendix 4

  5. Slide 5: Nearing construction for two strategic assets

    Introduction Nearing construction for two strategic assets Engebø – rutile and garnet (100%) • Large resource base • Long term industrial partners • First European producer of garnet • Post tax NPV@6.8% USD 305m Keliber – lithium hydroxide (18.5%) • First European producer • Large resource potential

  6. Slide 6: Board of Directors and Management team

    Introduction Board of Directors and Management team Board of Directors Management team Kjell Roland, Chairman Ivar S. Fossum, CEO • Former CEO of Norfund • 13 years with Nordic Mining (since founding) • Previous experience as partner and CEO in ECON Management AS and • 20 years experience from manag

  7. Slide 7: Table of contents

    Table of contents 1 Introduction 1 Introduction 2 Engebø – rutile and Engebø – rutile and garnet 2 garnet 3 Keliber – lithium3 Keliber – lithium 4 Summary 4 Summary 5 Appendix 5 Appendix 7

  8. Slide 8: Key milestones completed ─ progressing towards construction

    Engebø Key milestones completed ─ progressing towards construction Q1 ‘15 Zoning plan approved and environmental permit granted Q4 ‘17 Prefeasibility study (PFS) completed Q4 ‘17 Strategic partnership with Barton Group on offtake and financing Q1 ‘19 Heads of Agreement with Japanese trading house on

  9. Slide 9: On track towards value inflection points

    Engebø On track towards value inflection points 2019 2020 2021 2022 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Definitive feasibility study FEED Offtake agreements Construction financing Construction period Production ramp- up 9

  10. Slide 10: Unique resource of rutile (titanium dioxide) and garnet

    Engebø Unique resource of rutile (titanium dioxide) and garnet Key features Large resource potential (Mt)1 • High grade rutile and garnet deposit located in TiO2(%) 3.95 3.85 3.87 3.82 western Norway Garnet (%) 44.6 43.2 44.4 42.5 • One of the world’s largest deposits of natural rutile with vast amo

  11. Slide 11: High grade rutile with low level of impurities

    Engebø High grade rutile with low level of impurities High rutile grade gives processing advantages Low levels of radioactive elements Indicative rutile grades (TiO2) for current producers and planned projects Engebø 3.9% West Balranald 3.9% Cerro Blanco Private 1.7% SRL 0.9% Snapper 0.9% Carmaspe/A

  12. Slide 12: Solid market drivers for Nordic Mining’s minerals

    Engebø Solid market drivers for Nordic Mining’s minerals Rutile Garnet Global market: Global market: ~0.7 million tonnes ~1.1 million tonnes Fundamental drivers Fundamental drivers • Titanium has unique properties as oxide and metal • Emerging mineral with strong growth and potential • Rutile is the

  13. Slide 13: Rutile prices forecasted to increase with growing demand

    Engebø Rutile prices forecasted to increase with growing demand Global rutile demand is outpacing supply… ….driving rutile prices up ‘000 TiO2 units U$/tonne FOB 1,000 High Long term forecast: 750 US$ 1,118 / tonne FOB (real 2018 dollars) 500 Low 250 0 Others China Australia Demand India US Sierra L

  14. Slide 14: Favorable long term price trend for garnet

    Engebø Favorable long term price trend for garnet Price trend of garnet (2016 – H1 2018) USD / tonne (CIF) 1,000 Australia Trend India PFS price assumption (USD 250/t) 800 600 400 200 0 Jan-16 Apr-16 Jul-16 Oct-16 Jan-17 Apr-17 Jul-17 Oct-17 Jan-18 Apr-18 Jul-18 Note: USD/EUR = 0.9 used for price ca

  15. Slide 15: Quality offtake partners with participation in construction financing

    Engebø Quality offtake partners with participation in construction financing Rutile offtake Garnet offtake Japanese trading house The Barton Group • Heads of agreement for rutile offtake and construction • Heads of agreement for garnet offtake and financing financing • Offtake for garnet to the Amer

  16. Slide 16: Attractive mining conditions

    Engebø Attractive mining conditions Long term open pit mining with rich ore and low stripping ratio Mine life of 21 years1 Run of mine of 1.5 Mtpa Stripping ratio of 1.34 Easy transition to underground mining beyond the open pit phase Mine life of 13 years Run of mine of 1.5 Mtpa Operational flexibi

  17. Slide 17: Logistical and freight cost advantages

    Engebø Logistical and freight cost advantages Engebø mine Process plant and port Markets ~ 500 meters from mine to quay European customers two sailing days away Process plant with integrated quay Close proximity to European markets • Comminution and processing conducted • Deep sea ice-free quay allo

  18. Slide 18: Existing quay enables modular construction

    Engebø Existing quay enables modular construction Modularized process plant Process plant units • Improved schedule with use of offsite modular construction • Proven technology with high degree of automation • Yard construction allows for proper quality assurance and pre-commissioning • Process modu

  19. Slide 19: Sustainable mining – minimizing footprint

    Engebø Sustainable mining – minimizing footprint Environmental focus from detail engineering… • Energy efficient motors and variable speed drives to be used in comminution and process plant • Waste heat recovery system on dryers for heating of process plant • Compact design on process modules reduce

  20. Slide 20: Completion of DFS ─ a major milestone

    Engebø Completion of DFS ─ a major milestone DFS provides key technical outputs… • Engineering and 3D model of facilities • Engineering and 3D model of process modules • Detailed specifications of equipment packages • Detailed description of all key aspects of the Engebø project • Construction sched

  21. Slide 21: Financing plan

    Engebø Financing plan Clean funding strategy applied in development phase • Zero debt on the balance sheet to date • Approximately NOK 70m in capital requirement for pre-construction phase • DFS provides robust basis for further financing Further funding options to be explored post DFS • Several wor

  22. Slide 22: Financial highlights from PFS study

    Engebø Financial highlights from PFS study Base case financial metrics Post-tax NPV1 Post-tax IRR Life of mine Payback time Capex 305 21 29 <5 207 USDm % years years USDm With further upside potential Life of mine Sales Extension of life of mine by Increased garnet sales in initial including inferre

  23. Slide 23: Industry leading revenue-to-cost position for rutile

    Engebø Industry leading revenue-to-cost position for rutile Industry revenue-to-cash cost1 curve for TiO2 feedstock (2021) 1st quartile 2nd quartile 3rd quartile 4th quartile 4.2 3.6 Engebø R/C-ratio of 3.92 3.0 2.4 2021 Industry weighted average: 1.85 1.8 1.2 0.6 0.0 0% 25% 50% 75% 100% Cumulative

  24. Slide 24: Table of contents

    Table of contents 1 Introduction 1 Introduction 2 Engebø – rutile and Engebø – rutile and garnet 2 garnet 3 Keliber – lithium3 Keliber – lithium 4 Summary 4 Summary 5 Appendix 5 Appendix 24

  25. Slide 25: First European producer of battery grade lithium hydroxide

    Keliber First European producer of battery grade lithium hydroxide Lithium-ion giga factories planned in Europe Planned Li-ion production capacity by 20281 Lithium-ion battery production capacity, 2028 (GWh) 1 Gwh demands 0.8 kt of lithium carbonate equivalent Project progress • By 2023 Giga-factori

  26. Slide 26: Solid project economics in updated DFS

    Keliber Solid project economics in updated DFS Key financials - updated DFS (Feb. 2019) Keliber ownership as of May 2019 State of Finland2 Post-tax NPV Post-tax IRR 57.2% Private and 1 432 24 institutional investors USDm % Development of mineral resources3 Thousand metric tonnes, measured and indica

  27. Slide 27: Table of contents

    Table of contents 1 Introduction 1 Introduction 2 Engebø – rutile and Engebø – rutile and garnet 2 garnet 3 Keliber – lithium3 Keliber – lithium 4 Summary 4 Summary 5 Appendix 5 Appendix 27

  28. Slide 28: Key investment highlights – two attractive mineral projects

    Key investment highlights – two attractive mineral projects Engebø (100%) Large deposit with unique location Keliber (18.5%) Quality offtake partners ▪ OAX: NOM for rutile and garnet Robust project economics Minerals for a sustainable future Strong competitive position Valuable investment in lithium

  29. Slide 29: Table of contents

    Table of contents 1 Introduction 1 Introduction 2 Engebø – rutile and Engebø – rutile and garnet 2 garnet 3 Keliber – lithium3 Keliber – lithium 4 Summary 4 Summary 5 Appendix 5 Appendix 29

  30. Slide 30: Short payback period and long term cash flow

    Engebø Short payback period and long term cash flow Revenue split1 USDm 40% 60% (Price USD 250 pmt) (Price USD 1070 pmt) Source: Engebø PFS, extended by one year 1) Based on first ten years 30

  31. Slide 31: PFS - Engebø

    Appendix PFS - Engebø Assumptions Value Unit Output Value Unit Garnet price 250 USD/tonne Pre-tax NPV @ 8% 332 USDm Rutile price 1 070 USD/tonne Pre-tax IRR 23.8 % Garnet sales (from ~2027) 261 000 Tonnes per annum Life of mine 29 years Rutile sales (average) 32 500 Tonnes per annum Payback period L

  32. Slide 32: Flowsheet of rutile and garnet process

    Appendix Flowsheet of rutile and garnet process Source: Engebø PFS 32

  33. Slide 33: Shareholder information

    Appendix Shareholder information Shareholder overview (as of 16 September 2019) Key shareholder information # Shareholder Country # of shares % of total Current # of shares outstanding: 143 791 772 1 Nordnet Bank AB Sweden 12,343,545 8.58% Share price (as of 16 September 2019): NOK 1.53 2 VPF Nordea

  34. Slide 34: Income statement reflecting project progress and gain in Keliber

    Appendix Income statement reflecting project progress and gain in Keliber Comments Income Statement (NOKm) H1 2019 H1 2018 Operating expenses -7.4 -4.7 1 EBIT Other operating expenses -28.5 -21.1 • Operating loss reflects the cost of ongoing DFS activities EBIT 1 -35.9 -25.8 2 Financial Income Share

  35. Slide 35: Balance sheet with no interest bearing debt

    Appendix Balance sheet with no interest bearing debt Balance Sheet (NOKm) 31.06.2019 31.12.2018 Comments Evaluation and exploration assets 25.8 25.6 PP&E 0.2 0.2 1 Financial assets Investment in associate - 21.3 • Financial assets comprise investment in Keliber Oy Financial assets 1 113.1 - 2 Cash a

Nordic Mining — Investor Presentation (September 2019) on 6ix