  1. Slide 1: Gensource Potash Corp. Corporate Presentation

    Gensource POTA SH CORP Corporate Presentation TSXV:GSP June 2018

  2. Slide 2: Disclaimer

    2 Disclaimer This presentation does not constitute and offer to sell, or the solicitation for the offer to buy, the securities of Gensource. The scientific and technical information contained in this presentation has been reviewed and approved by Mike Ferguson, P.Eng., who is the President and Chief

  3. Slide 3: Gensource Potash Corp. Vision – Mission - Values

    3 Gensource Potash Corp. Vision – Mission - Values Vision: Mission: Values: Achieve food security Create a series of The core priorities by supplying the world independent, scalable for Gensource are with a key and environmentally integrity, macronutrient at an sustainable Potash forthrightness, aff

  4. Slide 4: Gensource Project Summary – Vanguard 1

    4 Gensource Project Summary – Vanguard 1 Focussed on developing 100%-owned ‘Vanguard’ Highlights project located in central Saskatchewan, Canada • Vanguard 1 Project is in the first quartile of all potash where Saskatchewan is ranked the 2nd most attractive producers worldwide: sub-US$40.00/t cash c

  5. Slide 5: Potash: Problem & Opportunity

    5 Potash: Problem & Opportunity Supply Side Development of Crop Prices Demand Side Producers Suffer From: A Historical Overview: Customers Suffer From: ❖ Lack of Competition: Potash is ❖ Lack of Competition: Potash supply is 11.5 controlled by oligopolistic controlled by oligopolistic supply-side su

  6. Slide 6: Gensource Value Proposition

    6 Gensource Value Proposition To disrupt the existing supply chain by deploying innovative extraction methods and partnering directly 100% Potash 3. JV Partnerships Direct Delivery with potash users 2. Innovative Extraction Method Gensource Potash JVCo. Mineral Reserve Potash Partner Using brackish

  7. Slide 7: High Quality Asset Base

    7 High Quality Asset Base Saskatchewan Canada Bankable Feasibility Projects situated in world’s Compelling Project NPV and IRR 1 Study completed largest potash basin May 31, 2017 (unlevered – 100% Equity Base Case) Indicator Pre Sask. Profit Tax Post Sask. Profit Tax Strong local and provincial supp

  8. Slide 8: Drilling & Geology – Reserves & Resources

    8 Drilling & Geology – Reserves & Resources Gensource Potash’s ‘Vanguard 1 Area’ Mineral Resources were The mineral resources for the Vanguard 1 Project area have been estimated by Ordinary Kriging techniques using a grid model in estimated based on the principles established by the Guidelines on Ma

  9. Slide 9: Vanguard 1 Cost Breakdown – CapEx

    9 Vanguard 1 Cost Breakdown CapEx Breakdown Project economics includes fully drawn contingency expense Item ‘000 CA$ Contingency, Mining, 8.5% 9.1% Mining $ 23,738 Wellfield, 6.2% Wellfield $ 17,304 Process Plant $ 70,610 Project Indirects, Storage & Loadout $ 957 27.9% Process Plant, 25.2% Site Inf

  10. Slide 10: Vanguard 1 Cost Breakdown – OpEx

    10 Vanguard 1 Cost Breakdown OpEx Breakdown All-in costs per tonne of $US 95.97 (Ex Works) Cash Margins OpEx, Price/ Net $ Margin % Net $ Margin % $39.57 Shipping , Tonne No Shipping With Shipping $74.35 $225 $129.03 57% $53.68 24% $250 $154.03 62% $79.68 32% Sustaining CapEx, $11.66 $275 $179.03 65

  11. Slide 11: Two Separate Projects in Vanguard Project Area

    11 Two Separate Projects in Vanguard Project Area In March of 2018, Gensource Potash signed two separate non-binding MOU’s with The Vanguard One Project Area Will Support Multiple Production large North American agriculture players. The first MOU has been successfully Modules converted into a defini

  12. Slide 12: Gensource Versus Traditional Miners

    12 Gensource Versus Traditional Miners Vanguard 1 In First Quartile Conversion Cost per Tonne @ Capacity (USD) 200 180 160 140 Sustaining Capex 120 100 Opex 80 60 40 20 0 Source: Randle Green Consulting, CRU, Integer Research, Company Reports, Gensource Potash

  13. Slide 13: Comparative Mining Methods

    13 Comparative Mining Methods Conventional Selective Dissolution Specifications Conventional Solution Mining Vanguard 1 Min. Viable Production Rate 2.5 Mt/a 2.0 Mt/a 250 kt/a CapEx per Tonne (USS) $ 1,990 * $ 1,620 * $ 840 ** Operating Costs (US$) $ 80/t * $ 118/t * $ 39.57/t ** Development Time 7-1

  14. Slide 14: Economics

    Each module and partnership creates significant cash flows to Gensource Potash Corp, creating a potash streaming company 14 Economics Assumptions Gensource’s small-scale concept facilitates a development timeline of approximately two Resource/Engineering Investment $ 8,000,000 years from constructio

  15. Slide 15: Development Timelines

    15 Development Timelines* Proposed production horizon less than 3 years 2016 2017 2018 2019 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PEA / Scoping Study Completed Market Partner JV Vanguard Potash Corp. Announced Exploration Drilling Completed NI 43-101 Resource Update Completed 3D Seismic Complete

  16. Slide 16: Development Upside: Project 2

    16 Development Upside: Project 2 Overview Resource Area A second project area, known as the ‘Lazlo Project’, is also The resource in the Lazlo area is rich and widespread, and is an ideal candidate for a selective dissolution operation. located along a well-serviced infrastructure corridor. Located

  17. Slide 17: Management & Board

    17 Management & Board Management Directors Mike Ferguson, P. Eng. - President & CEO Mike Ferguson, P. Eng. - President & CEO Led the world-class team that developed Potash One’s Legacy Led the world-class team that developed Potash One’s Legacy Project, Project, the only Saskatchewan greenfield pota

  18. Slide 18: Capital Structure

    18 Capital Structure Market Capitalization $52.7 Million Recent Share Price $0.15 52 Week Range $0.06 - $0.20 Basic Shares Outstanding 351 M Options 30.5 M Warrants 38.8 M Cash Position ~ $2.07M Debt $0 Management, Directors & ~ 27% Business Associates

  19. Slide 19: Contact Us

    19 Contact Us Mike Ferguson, P. Eng. Rob Theoret, B.Comm., CIM President & CEO CFO mike@gensource.ca rob@gensource.ca 306-974-6414 306-974-6406 Suite 1100, 201 1st Ave. South Website Saskatoon, Saskatchewan www.gensource.ca S7K 1J5

  20. Slide 20: Appendix

    Appendix Gensource POTASH CORP

  21. Slide 21: Technical Strength

    21 Technical Strength These individuals, together with Mike Ferguson, comprised the core Potash One team responsible for the project’s success Max Ramey, P.Eng. – Solution Mining Solution mining lead for the Potash One - Legacy Project (as well as the Rio Tinto - Potasio Rio Colorado Project in Arge

  22. Slide 22: Existing Mines have Environmental Issues

    22 Existing Mines have Environmental Issues Gensource is NOT a conventional Potash Mine Gensource facility is 300 metres by 300 metres Conventional = HUGE environmental footprint ❖ Massive salt tailings stored on surface for indefinite period ❖ Large fresh water consumption ❖ Large demand on utiliti

  23. Slide 23: Selective Dissolution

    23 Selective Dissolution Cost effective and efficient recovery method Horizontal Well Pattern Horizontal Cavern for Selective Dissolution ❖ Using brackish formation water, an extraction brine is pumped through horizontal caverns where only KCl (potash) is dissolved ❖ The saturated brine (NaCl and KC

  24. Slide 24: Proven Technique – Intrepid Potash

    24 Proven Technique – Intrepid Potash Cane Creek Mine (Moab, UT) - has historically experienced many production challenges but deployed selective dissolution methods to overcome the problems Complex geology ❖ Significant faulting and folding associated with Cane Creek anticline ❖ Cannot be mined usi

  25. Slide 25: Proven Technique – Intrepid Potash

    25 Proven Technique – Intrepid Potash Selective dissolution successfully deployed at Cane Creek Mine (Moab, UT) starting in 2006 Pitchfork Well Pattern Before and After Selecting Mining ❖ Inject saturated brine to selectively mine potash – saturated brine targets potash only, salt matrix remains int