  1. Slide 1: Vickery Extension Project – CCC Meeting

    Whitehaven Coal Limited VICKERY EXTENSION PROJECT – CCC MEETING 11 APRIL 2016

  2. Slide 2: Agenda

    Agenda Topic Introduction Project description Environmental assessment update Community consultation General business Date and agenda for next meeting 2

  3. Slide 3: Introduction

    Introduction  Present and apologies.  Declaration of pecuniary or other interests.  Previous minutes. 3

  4. Slide 4: Project Description

    Project Description  Vickery Coal Project (Approved Mine) approved by DP&E 19 September 2014.  Vickery Extension Project: • Increase in ROM extraction rate from 4.5 Mtpa to 10 Mtpa. • Increase in open cut mining footprint (including mining of Vickery South). • Construction and operation of an on-s

  5. Slide 5: Project Description - Approved Mine

    Project Description - Approved Mine 5

  6. Slide 6: Project Description - Extension Project

    Project Description - Extension Project 6

  7. Slide 7: Project Description - Rail

    Project Description - Rail > WHITEHAVEN COAL ‘Mining Tenement Boundory (MLB Cl) Eeplration Tenement Boundary (EL & AUTH) Segab Coal Nine - oposed Ally Infrostrudure Areas Extension Project Components Extent of Open Cut Extent of Out of Pit Waste Rock Emplacement Inhostrocture Area. Topol Stedgile In

  8. Slide 8: Operational Workforce

    Operational Workforce  Operational workforce of approximately 450 full time equivalent personnel (increase of approximately 200 personnel from the Approved Mine).  In keeping with Whitehaven’s local employment policies it is anticipated that approximately will be 70% local hires distributed across

  9. Slide 9: Construction Workforce

    Construction Workforce  Construction workforce of approximately 500 full time equivalent personnel.  Assumed to be non-local hires for purpose of impact assessment.  Estimate that 90% of construction workforce would reside in the Boggabri accommodation camp. 9

  10. Slide 10: Employee Vehicle Movements

    Employee Vehicle Movements  Access to site via existing sealed roads from Gunnedah and Boggabri: • Blue Vale Road • Rangari Road • WHC private haul road  Road Transport Assessment to assess potential impacts to road network. 10

  11. Slide 11: Environmental Assessment Update

    Environmental Assessment Update  State Significant Development   assessment process     11

  12. Slide 12: Environmental Impact Statement

    Environmental Impact Statement  Environmental Impact Statement currently being prepared.  Anticipate EIS lodgement mid 2016. Specialist Assessments Groundwater Assessment Road Transport Assessment Surface Water Assessment Socio-economic Assessment Flooding Assessment Historic Heritage Assessment N

  13. Slide 13: Community Consultation

    Community Consultation  CCC meeting 11 April 2016.  Project newsletter to be distributed.  Community information session and second CCC meeting to be held late May.  One-on-one meetings with neighbours.  Engagement with local councils. 13

  14. Slide 14: Community Consultation

    Community Consultation  General business.  Date and agenda for next meeting.  Questions? 14

  15. Slide 15: Thankyou for your attendance

    Thankyou for your attendance 15