  1. Slide 1: Investor Presentation July 2016

    INVESTOR PRESENTATION | JULY 2016 | PETER REEVE | EXECUTIVE CHAIRMAN | NEIL CLIFFORD | PRINCIPAL GEOLOGIST |

  2. Slide 2: Disclaimer

    DISCLAIMER This document, any attachments and the oral presentation on the slides (together the "Presentation") have been prepared and are being supplied to you by Aura Energy Limited (the "Company") solely for information purposes in connection with a potential offering of securities by the Company

  3. Slide 3: Aura Snapshot

    a AURA SNAPSHOT y Uranium exploration and development company = Gold, soda ash and lithium prospects = Portfolio of uranium development projects in Africa and Europe = Aura believes these demonstrate attractive economics and value upside potential = Potential uranium market opportunity — forecast su

  4. Slide 4: Project Portfolio

    P R O J E C T P O RT F O L I O   ₃ ₈ ★ ₃ ₈  ★     4

  5. Slide 5: Contract and Spot U3O8 Price

    ₃ ₈ ₃ ₈ ₃ ₈ CONTRACT U₃O₈ PRICE – US$42/lb* SPOT U₃O₈ PRICE – US$26.10/lb* 5

  6. Slide 6: Development Strategy: Simple Path to Cash Flow

    D E V E L O P M E N T S T R AT E G Y S I M P L E PAT H T O C A S H F L O W TIRIS INTO PRODUCTION MID 2018 TIRIS CONSTRUCTION H2 2017 – SUBJECT TO FUNDING PROJECT TIRIS FEASIBILITY FINANCE STUDY IN 12 MONTHS CONTINUE TO ASSESS NEW OPPORTUNITIES 2016 2018 6

  7. Slide 7: Uranium Drivers

    URANIUM DRIVERS Electricity 500+ reactor’s Forecast to built & under construction Rise 76% by 500+ planned & 2030 proposed by (Source: World Nuclear Association, March 1, 2016) 2030 Forecast new reactors by 2030. (Source: World Nuclear Association, March 1, 2016) 7

  8. Slide 8: Uranium Market Drivers

    aura URANIUM MARKET DRIVERS energy Aura’s view on key uranium market issues is: = Decreasing level of Long Term contract coverage to end 2014 = Short Term reliance on spot supplies by utilities Constant M Ibs U,0, US $/lb U,0, 350 ack $140 ta Spo 300 288 a ” @—@Long-Term $120 250 | —spot Price* $100

  9. Slide 9: Projects

    PROJECTS T I R I S U R A N I U M – M A U R I TA N I A TA S I A S T S O U T H G O L D – M A U R I TA N I A S O D A A S H & L I T H I U M – M A U R I TA N I A HÄGGÅN URANIUM – SWEDEN 9

  10. Slide 10: Tiris Uranium Project

    TIRIS URANIUM PROJECT    M A U R I TA N I A  ₃ ₈  10

  11. Slide 11: Tiris – Mining Region

    TIRIS – MINING REGION • • ESTABLISHED RESOURCE PLAYERS IN THE REGION          11

  12. Slide 12: Tiris Uranium Deposits

    TIRIS URANIUM DEPOSITS Soda Ash – Lithium Deposit 12

  13. Slide 13: Tiris Geology

    (2 TIRIS GEOLOGY Solid Unaltered Grey Granite Sheared “Hot” Pink Granite 1 y] 2 a i 5 GREY GRANITE U,0, Leaches from Pink Granite Carnotite (U,O, Mineral)/Gravel Mix ALTERED PINK GRANITES ~ Sheds into Surrounds Gathers in Desert Low Points _——-a Natural Processes Concentrate Carnotite into a Surfici

  14. Slide 14: Reveals Mineralisation

    R E V E A L S M I N E R A L I S AT I O N CALCRETE DEPOSIT WITH CARNOTITE URANIUM IN A W E AT H E R E D G R A N I T E H O S T FREE DIGGING MINING, NO DRILL AND BLAST URANIUM PERMITTING IN A M I N E R A L I S AT I O N REMOTE DESERT AS CARNOTITE REGION 14

  15. Slide 15: Simple Ore Upgrade

    ca SIMPLE ORE UPGRADE y Soft Friable Material That Breaks Down Easily Coarse Weathered Granite Fine Grained Carnotite Water Waste & Coarse Oversize ; leathere ranite & @ Sr ace aes eS 90% Mass & a 10% Uranium i 10% Mass Vv 90% Uranium Leach Plant 1 eo ee 25 TPH (0.2mtpa) “ * . _° Fine < eee etc ie e

  16. Slide 16: Tiris Scoping Study

    TIRIS SCOPING STUDY R E L E A S E D J U LY 2 0 1 4  ₃ ₈  ₃ ₈  ₃ ₈  ₃ ₈  ₃ ₈    16

  17. Slide 17: Feasibility Study Underway

    F E A S I B I L I T Y S T U D Y U N D E RWAY TA R G E T T O C O M P L E T E T I R I S F E A S I B I L I T Y S T U D Y I N 1 2 MONTHS AND COMMENCE MINE CONSTRUCTION IN H2 2017  Update significant portion of resource to Measured and Indicated ☐ Mining study  Beneficiation testwork on ore zones ☐  E

  18. Slide 18: Strategic Chinese MoU

    S T R AT E G I C C H I N E S E M O U          18

  19. Slide 19: Exploration Upside

    EXPLORATION UPSIDE HIGHLY PROSPECTIVE AREA - HIPPOLYTE SOUTH APPLICATION = Aura has observed strong & extensive radiometric anomalism = Between existing resources of Hippolyte & Lazare = Previously poorly tested = Magnetic data defines structural association with Hippolyte resource zones = Same stru

  20. Slide 20: Tasiast South gold drill intercepts

         TGRC 022 71m @ 0.3 g/t Au incl: •5m @ 1.2 g/t Au, •3m @ 1.0 g/t Au  •11m @ 0.5 g/t Au  TGRC 007 38m @ 0.4 g/t Au incl: •1m @ 6.1 g/t Au •6m @ 0.7 g/t Au 20

  21. Slide 21: Tiris - Soda Ash & Lithium

    TIRIS - SODA ASH & LITHIUM        21

  22. Slide 22: Sweden

    ONE OF THE LARGEST UNDEVELOPED URANIUM PROJECTS IN THE WORLD, WITH 803 Mlbs INFERRED URANIUM RESOURCE  SWEDEN ★         22

  23. Slide 23: Excellent Locality

    EXCELLENT LOCALITY       23

  24. Slide 24: Low Capex – Bio Heap Leach

    process scale-up tests bacterial cultures & develops study on the applicability of bioflotation for monito Preliminary research activities focused on isolating and identifying novel microorganisms A numb LOW CAPEX – BIO HEAP LEACH (and those available in personal culture investiga collections) that

  25. Slide 25: Low Cost, High Margin Project

    L O W C O S T, H I G H M A R G I N P R O J E C T [ 1 ] M T PA APPROX OP COST U₃O₈ Mlbs Mo MLBS Ni MLBS CAPEX* US$/lb p.a. p.a. p.a. $m 5* 190 18.00- 1.4 0.6 2.4 22.00 30.0 540 13.50 7.8 4.3 14.8 25

  26. Slide 26: Key Company Data

    K E Y C O M PA N Y D ATA 0.024 12 C O R P O R AT E S T R U C T U R E Millions 0.022 10 Share Price A cents 1.8cps 0.02 Shares On Issue 457m 8 Cents Per Share 0.018 Options On Issue 197m 6 0.016 Market Capitalisation A$8.2m 4 0.014 Cash (30/9/15) A$0.427 2 0.012 Enterprise Value A$7.78m 0.01 0 Jun 15

  27. Slide 27: Why Aura Energy?

    WHY AURA ENERGY?           27

  28. Slide 28: Peter Reeve

    PETER REEVE EXECUTIVE CHAIRMAN preeve@auraee.com +613 9516 6500

  29. Slide 29: Tiris Feasibility Team

    TIRIS FEASIBILITY TEAM George has over 40 years’ experience in the metallurgical and mineral processing industries in Australia, North and South America, Africa, Europe and Asia. His project and study involvement has included gold, silver, copper, lead, zinc. uranium and mineral sands. George was a

  30. Slide 30: Uranium Resources

    URANIUM RESOURCES T I R I S R E S O U R C E - M A U R I TA N I A 100ppm cut-off To n n e s Grade M l b s U 3O 8 Indicated 2 300 2 Inferred 64 335 47 Total 66 334 49 100ppm TONNES U 3O 8 V NI ZN U 3O 8 c u t - (BT) (PPM) MO (PPM) (PPM) (PPM) (PPM) off  ₃ ₈    30

  31. Slide 31: Water Infrastructure

    WAT E R I N F R A S T U C T U R E        31

  32. Slide 32: Uranium Supply vs Demand

    URANIUM SUPPLY VS DEMAND RJL Global Uranium Supply vs. Demand (Mlbs/yr) 325 300 275 250 ie] Q 225 2 = 200 2 = 175 150 125 100 N cal t+ w wo nt i) a Oo a N nm t+ wo wo n oe a So a a a a a a a a N N N N N N N N N N isa) fo) fo} fo} Oo Oo Oo Oo Oo Oo Oo Oo Co Oo Oo Oo Oo Oo N N N N N N N N N N N N N N

  33. Slide 33: Primary Supply Forecast

    aura PRIMARY SUPPLY FORCAST energ RJL Global Primary Supply Forecast (Mlibs/yr U308eq) 200 4 Today 175 150 125 100 ~ uw uw o Global Mine Supply (MIbs/yr) N wn 0 SRESESSESSSHRES HBR HHS HRHRESHRER EBB o So So o So So a a a a a a a a a a N N Nn N Nn N N N N N ical coc OUCOCUCUCOCUCOCUCOCCOCCcOCUClCOOC

  34. Slide 34: Secondary Supply Forecast

    S E C O N D A RY S U P P LY F O R E C A S T 34

  35. Slide 35: Nuclear Capacity

    dUfa energy NUCLEAR CAPACITY RJL Global Operating Nuclear Capacity by Country/Region (GW gross, end of period) 650 600 uw uw oO Global Ope rating Nuclear Capcity (GW) 8 o 2011A 2012A Today —? —? w w w Ww w Ww w Ww w Ww w w w w w w ~m t+ w wo Lt °c a oO a N m <5 w wo ined co Dp So a a a a a a a N N N

  36. Slide 36: Incentive Price Curve

    INCENTIVE PRICE CURVE RJL Incentive Price Curve for New Mines = UxC: >50% production have production costs >US$35/lb U308 = RJL: amongst potential new mines, incentive price averages >US$/75 = Developers unlikely to sign contracts unless they incent new production 120 7 110 + 100 + 50 oe | — —— = =e

  37. Slide 37: Tiris Process Flowsheet

    TIRIS PROCESS FLOWSHEET      ₃ ₈  37

  38. Slide 38: Tiris Permitting Process

    TIRIS PERMITTING PROCESS Project Phases Mining License Application EIA Process Conduct, Prepare and Submit EIA and Environmental Mat it Plan in line with TOR Pate tna snide (30 days) completed by Elementary Bib Opinion of Local jes (5 days) and writing of j | EIA Review by the ‘of Environment end ot