  1. Slide 1: PNG Mining & Petroleum Investment Conference

    PNG Mining & Petroleum Investment Conference Hidden Valley – PNG’s Newest Mine December 2010

  2. Slide 2: Harmony Gold Disclosure Statement

    Harmony Gold Disclosure Statement This presentation contains "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended, and 21E of the Securities Exchange Act of 1934, as amended, that are intended to be covered by the safe harbour created by such secti

  3. Slide 3: Newcrest Mining Disclaimer

    Newcrest Mining Disclaimer Competent Persons Statement The information in this presentation that relates to Exploration Results, Mineral Resources and Ore Reserves is based on information compiled by C. Moorhead, EGM Minerals for Newcrest Mining Limited who is a Member of The Australasian Institute

  4. Slide 4: Contents

    Contents ƒ The Hidden Valley mine ƒ Transition to operations ƒ Foundations ƒ Future priorities and growth Movie

  5. Slide 5: Morobe Mining Joint Ventures

    Morobe Mining Joint Ventures ƒ MMJV is a 50:50 joint venture between Harmony Gold Mining Company Limited and Newcrest Mining Limited ƒ Our Mission – Discovering, developing and operating gold mines in Morobe Province to build a sustainable long term business to benefit all our stakeholders ƒ 3 joint

  6. Slide 6: Hidden Valley Mine

    Hidden Valley Mine ƒ Mine officially opened September 2010 ƒ Two open pit mines – Hidden Valley and Hamata ƒ The plant treats 4.6 million tonnes of ore per year – Hidden Valley Mine will produce on average: +250,000 ounces of gold per year 4 million ounces of silver per year ƒ 14 Year mine life base

  7. Slide 7: Safety

    Safety ƒ Improving year on year trend for Serious Injuries frequency. ƒ Key areas of focus: – Operational risk management and risk reduction programs – Contractor safety management systems – Work management systems ( training / procedures)

  8. Slide 8: People

    People ƒ Employment > 800 direct employees Over 90% are PNG citizens 50% are landowners 15% are female ƒ Contractors >1,000 contractor employees Over 85% are PNG Citizens

  9. Slide 9: Environment

    Environment ƒ Site is permitted under the Environment Act (2000) ƒ Extensive on and off site monitoring program supported by scientific studies ƒ Progressive rehabilitation since 2007 ƒ Environmental Management system with strong focus on water quality ƒ Information sharing and consultation with gov

  10. Slide 10: Waste Management

    Waste Management The Hidden Valley Mine has an engineered tailings storage facility No mine processing residue, or tailings, is discharged into the environment Major commitment (+100 million Kina) – PNG’s only large scale tailings storage facility. All waste rock is placed in engineered Waste Dumps

  11. Slide 11: Construction Impact on the Watut River

    Construction Impact on the Watut River • Construction Phase Sediment Impacts - Mine related sediment entered the Watut River during construction, contributed to flooding events which affected river communities. - Post-construction mitigating actions have substantially reduced suspended sediment leve

  12. Slide 12: Infrastructure

    Infrastructure ƒ Mine is supported by some world-class infrastructure ƒ 4.5km overland pipe conveyor – reduces reliance on diesel-powered truck haulage in mountainous terrain ƒ Connection to the Yonki Hydro scheme to provide >90% of electrical power needs ƒ Benefits delivered by PPL to local communi

  13. Slide 13: Performance

    Performance ƒ Operational performance continues to improve ƒ Excellent resource grade reconciliation ƒ De-bottlenecking program aimed at lifting nameplate by 12% ƒ Intensive training and development program to support localisation targets

  14. Slide 14: Nationally Significant Project

    Nationally Significant Project ƒ ,ŝĚĚĞŶsĂůůĞLJŚĂƐďĞŐƵŶƚŽĐŽŶƚƌŝďƵƚĞƐƵďƐƚĂŶƚŝĂů ƌĞǀĞŶƵĞƚŽƚŚĞůŽĐĂůĐŽŵŵƵŶŝƚLJĂŶĚWE''ŽǀĞƌŶŵĞŶƚ͗ – Mine construction 1.4B Kina – Life of mine expenditure (estimate) >3 Billion Kina – PNG tax and royalties (estimate) >0.9 Billion Kina LOM – Royalty flows to community, governme

  15. Slide 15: Sustainability – Business Development

    Sustainability – Business Development ƒ Landowner company NKW participates in significant mine related business opportunities ƒ Involved in a number of key mine support contracts – solely or with JV partners ƒ Approximately 300 employees ƒ Business turnover >60 million Kina per year ƒ Maiden dividen

  16. Slide 16: Community & Sustainable Development

    Community & Sustainable Development ƒ Delivering on Mine Village and broader Watut River community projects – Village infrastructure – Water supplies – Aquaculture – Agriculture – Educational – Health ƒ Partnering with Government & NGOs to bring infrastructure development to the Bulolo District ƒ Si

  17. Slide 17: Hidden Valley Growth

    Hidden Valley Growth ƒ Build production towards 300kozs Au per annum ƒ De-bottlenecking and minor capital expenditure program to lift mill throughput to +5mtpa ƒ Continuing brownfields exploration and resource definition programs to increase resource base Plan to drill 37,000 meters this year ƒ Eval

  18. Slide 18: In Conclusion

    In Conclusion ƒ Hidden Valley is building up its production rate post-commissioning ƒ Already a world class mineral resource base - and growing ƒ Inclusive Stakeholder engagement processes ƒ Environmental programs established ƒ Investing in sustainable community development ƒ Benefits being delivere

  19. Slide 19: Em Tasol

    Em Tasol