Gsp Resource Corp. · TSXV:GSPR
Gsp Resource — Investor Presentation (August 2026)
28 slides from Gsp Resource's investor presentation, August 2026
Slide 1: Corporate Presentation
CORPORATE PRESENTATION | TSX-V: GSPR | GSPRESOURCE.COM | AUGUST 2026
Slide 2: Disclaimer
DISCLAIMER This presentation has been prepared by GSP Resource Corp. (“GSPR”) using its best efforts to realistically and factually present the Forward-looking statements are subject to a variety of risks and uncertainties, which could cause actual events, level of activity, information contained. H
Slide 3: High-Grade Copper + Silver + Gold in the Highland Valley Camp
HIGH-GRADE COPPER + SILVER + GOLD IN THE HIGHLAND VALLEY CAMP Funded and drilled in 2026 — Phase 1 complete: 1,801 metres across eight holes at Alwin and Mer, with assay results pending in stages through Q3 2026. GSP Resource Corp. (TSX-V: GSPR) holds a 100% interest in the Alwin Mine Copper-Gold-Si
Slide 4: Why Now — Fully Funded & Drilling the Re-Rate
WHY NOW — FULLY FUNDED & DRILLING THE RE-RATE The investment case has transformed since April — financed, permitted, and Phase 1 complete at two re-rating catalysts. 1 2 3 4 5 APR 22 APR 29 MAY 14 MAY 28 JUN–AUG Mer 5-yr drill permit Phase 1 program $1.22M financing Driller contracted — Phase 1 comp
Slide 5: Phase 1 Drilling Program — Complete
PHASE 1 DRILLING PROGRAM — COMPLETE 1,801 m drilled 2 targets 2-phase plan Fully funded 8 holes at Alwin + Mer — assays pending Alwin gold + Mer porphyry Phase 2 in H2 2026 $1.22M closed May 2026 ALWIN — HIGH-GRADE GOLD FOLLOW-UP MER — FIRST-PASS PORPHYRY TEST • Steps out from 2024 discovery hole AM
Slide 6: Phase 1 Drilling — Alwin & Mer
PHASE 1 DRILLING — ALWIN & MER AM-26-03 core — 2026 drilling Diamond drilling at Alwin Mine Project (June 19, 2026) — ~1,150 m over four step-out holes; samples being AM-24-06 core — 22.93 g/t Au, 1.82% Cu (2024) prepared for assay 6 | CORPORATE PRESENTATION | TSX-V: GSPR | GSPRESOURCE.COM | AUGUST
Slide 7: Investment Highlights
INVESTMENT HIGHLIGHTS Alwin Project – Past Producer (Cu, Ag, Au) Au Discovery & Porphyry Cu Potential Compelling Capital Structure • The shallow high-grade potential of the Alwin project is • Phase 1 drilling of new high-priority gold-silver & • Ground floor valuation of less than CAD$10 million com
Slide 8: Capital Structure
CAPITAL STRUCTURE Issued & Outstanding Shares: 57.9 million • Skin in the game: Management & Insiders Hold ~22% Fully Diluted: 75.7 million of I/O Shares (12.6 million shares) Working Capital: CAD $1.0 million • Legendary British Columbia mineral exploration participant Richard Billingsley is a 10%+
Slide 9: New – Potential Porphyry Source Target at Alwin
NEW – Potential Porphyry Source Target at Alwin: • 2025 NSAMT survey has confirmed and strengthened the Plan Map of Alwin Project Conductive Anomaly and HVC IP anomalies / Drilling identification of an untested deep conductive anomaly • First property-wide geophysical survey in nearly 20 years • Pro
Slide 10: New – Potential Porphyry Source Target at Alwin
NEW – Potential Porphyry Source Target at Alwin: Alwin Model Resistivity Oblique View Looking Southwest (500-1000 Ohm-m Blocks Shown) • Limited historic drilling immediately south of the conductive anomaly, returned 9.7 metres grading 0.55% copper (DH 08-06), with mineralization described as being s
Slide 11: Alwin Project – Open Pit & Underground Initial MRE
Alwin Project – Open Pit & Underground Initial MRE Highlights*: Oblique View of Alwin Mine MRE Pit Shell (beige) and Copper Block Model (gradational colour bar), historic underground development (blue), and backfilled stopes (red) • Inferred Mineral Resource comprising 1.46 million tonnes (Mt), aver
Slide 12: Fall 2025 – Alwin-Mer Drill Targeting
Fall 2025 – Alwin-Mer Drill Targeting RESULTS • Apex Zone: four samples returning 1.07–2.26 g/t Au, 33–83 g/t Ag, 0.90–3.3% Cu • Mer Showing: broad 100 x 50 m area, 12 samples returning 0.14–1.02% Cu (avg. 0.4% Cu) • Mer Eastern Trenches (650 m east): bornite-mineralized float sample yielding 3.1% C
Slide 13: 2026 Drilling – Gold Target
2026 Drilling – Gold Target • Occurrence of high-grade gold values below the vertical Alwin Mine Planned 2026 High-Grade Gold Target projection of existing “3 Zone” modelled copper resources affirms that these two contrasting mineralization styles are structurally and genetically linked, and can be
Slide 14: 2024 Drilling – New Gold Discovery
2024 Drilling – New Gold Discovery • Discovery of a new high-grade gold zone in drill hole AM-24-06 grading 5.04 g/t Au and 1.01% Cu over 7.90 m, including 22.93 g/t Au and 1.82% Cu over 1.64 m; plus an upper zone grading 1.22% Cu, 22.5 g/t Ag and 0.64 g/t Au over 2.5 m • AM-24-06 was collared south
Slide 15: 2024 Drilling – High Grade Copper – Open Pit Expansion Potential
2024 Drilling – High Grade Copper – Open Pit Expansion Potential • Drill hole AM-24-01 intersected multiple zones of high-grade copper-silver-gold mineralization over a combined 36.2 m core interval. Main zone averaging 2.41% Cu, 35 g/t Ag and 0.68 g/t Au over 17.4 m, including 4.11% Cu, 60 g/t Ag a
Slide 16: 2023-24 Drilling Highlights
2023-24 Drilling Highlights DDH From (m) To (m) Interval* (m) Cu % Ag g/t Au g/t CuEQ** % AM-24-05 33.62 38.40 4.78 3.93 5.77 0.10 4.04 AM-24-06 142.20 144.68 2.48 1.22 22.48 0.64 1.78 and 155.70 163.60 7.90 1.01 5.30 5.04 4.04 including 157.36 159.00 1.64 1.82 7.56 22.93 15.50 AM-24-01 91.68 97.20
Slide 17: Mer Property — Maiden Drilling Complete
MER PROPERTY — Maiden Drilling Complete Porphyry Cu-Mo zone; 2026 soils expanded Cu footprint to 175 x 120 m (open NW) Historic percussion holes returned 30 m @ 0.53% Cu, 21 m @ 0.51% Cu, 15 m @ 0.50% Cu and 9 m @ 0.47% Cu from shallow depths (6-18 m) Confirming diamond hole cut 24 m @ 0.29% C
Slide 18: Alwin Mine Historic 3D and Drilling Compilation
Alwin Mine Historic 3D and Drilling Compilation • Digital and 3D spatial capture of 646 drill holes totaling 51,304 metres completed from surface and underground between 1967-1981, in addition to 36 recent surface exploration diamond core holes totaling 5,600 metres drilled by GSPR and previous oper
Slide 19: Alwin Mine Historic Dataset
Alwin Mine Historic Dataset • 425 drill holes totaling 2,062 copper assay samples with partial gold-silver data • Global length weighted average copper grade of 1.8% from 3,287 metres sampled, compares favorably to 1.5% copper diluted head grade of historic production* • Majority of historic drillin
Slide 20: 2023 Drilling Sections
2023 Drilling Sections • All five 2023 drill holes intersected sulphide mineralization, with multiple intervals encountered in drill holes AM-23-01, -02 and -03 targeting the historic 4 Zone at depth. Drill holes AM-23-04 and -05 targeted the historic 4 Zone near surface. • Mineralization comprising
Slide 21: Satellite Images Showing Expansion Trend of HVC
SATELLITE IMAGES SHOWING EXPANSION TREND OF HVC 21 | CORPORATE PRESENTATION | TSX-V: GSPR | GSPRESOURCE.COM | AUGUST 2026
Slide 22: Recent Milestones & Upcoming Catalysts
RECENT MILESTONES & UPCOMING CATALYSTS COMPLETED — MOMENTUM BUILDING UPCOMING CATALYSTS NOW PHASE 1 COMPLETE — ASSAYS PENDING 2024 JAN 2025 2025 APR 2026 MAY 2026 PHASE 1 PHASE 2 Potential RE-RATE Maiden MRE + gold Consolidated 100% 348 g/t Ag, 12% Cu Mer 5-yr drill permit Fully funded — Alwin gold
Slide 23: Management & Directors
MANAGEMENT & DIRECTORS Mr. Dyakowski is President & CEO of GSP Resource Corp. Mr Dyakowski brings to GSP over 12 years of corporate development and capital markets experience, with an expertise in strategic planning and Simon C. Dyakowski CFA, MBA execution, financing, and marketing of exploration c
Slide 24: Technical Advisors
TECHNICAL ADVISORS Mr. Heyl brings to GSP's technical advisory board more than 40 years of experience in the mining industry, including senior corporate and technical positions with both major A. David V. Heyl BSc, P.G. mining companies and junior exploration companies, working mostly in the Andean
Slide 25: Alwin Project – Open Pit & Underground Initial MRE
Alwin Project – Open Pit & Underground Initial MRE * Table 1 Summary of Inferred Mineral Resources on the Alwin Project. (1-9) Table 2 Sensitivities of the Pit-Constrained 2024 Alwin MRE. Cut-off Tonnes Cu Cut- Cu Tonnes Cu Cu Classification off Cu (%) (t) (%) Classification (Mlbs) Cu (t) (%) (Mlbs)
Slide 26: Regional Portfolio
REGIONAL PORTFOLIO GSP holds two projects in BC’s prolific Quesnel Trough copper-gold belt — the Alwin Mine and Olivine Mountain — surrounded by producing mines and recent discoveries. The 3,020-hectare Olivine Mountain property lies 25 km northwest of Princeton and is optioned to Full Metal Mineral
Slide 27: Olivine Mountain
OLIVINE MOUNTAIN ASP 14 showings Zone: The showings are above a series of old machine trenches that extend for more than 400 m down the hill side from the logging road to Olivine Creek. The largest and most intense soil-copper anomaly in the 2018 GSP grid area extends northeastward toward the trench
Slide 28: Social & Environmental Responsibility
Social & Environmental Responsibility Creating jobs for British Columbia based crews, Adding Value in BC’s Interior Simon Dyakowski, CFA, MBA President & CEO, Director Mobile: +1-604-619-7469 #1030 - 505 Burrard Street Email: simon@gspresource.com Vancouver, BC V7Y 1M5