Black Rock Mining Limited · ASX:BKT

Black Rock Mining — 121 Conference, New York 2019

28 slides from Black Rock Mining's conference presentation, Oct 17, 2019

  1. Slide 1: Black Rock Mining and the Mahenge Project

    Black Rock Mining and the Mahenge Project Best-In-Class Graphite Mine Development For personal use only 121 Conference, New York 17-18 October 2019

  2. Slide 2: Important notices

    Important notices This presentation has been prepared by Black Rock Mining Limited (Black Rock or the Company). For personal use only The release, publication or distribution of this presentation in certain jurisdictions may be restricted by law and therefore persons in such jurisdictions into which

  3. Slide 3: Black Rock at a glance / Capital structure

    Black Rock at a glance Capital structure Emerging premium graphite player ASX ticker BKT For personal use only Share price (7 October 2019) $0.06 Australian-listed company (ASX: BKT) Shares on issue 622.5 M 100%-owner of Mahenge Graphite Project Options and performance rights 57.0 M Market capitalis

  4. Slide 4: Board

    Board The leaders John de Vries, Managing Director and CEO  Mining Engineer with over 35 years’ experience in mine development and operations; professional experience to deliver spans Africa, the Pacific, the FSU, North and South America and Australia For personal use only  Previously General Mana

  5. Slide 5: What we have delivered to date

     Largest pilot plant run of any graphite development project globally What we have  Highest TGC purity achieved at commercial scale through simple flotation delivered to For personal use only  Diverse portfolio of credible offtake partners date  Detailed offtake pricing framework agreed  Right-

  6. Slide 6: A snapshot of the Mahenge Graphite Project

    A snapshot of the Mahenge Graphite Project Simple open pit mine development with outstanding forecast returns For personal use only US$1.2B 45% 83ktpa Post-tax, ungeared, real NPV10 Post-tax, ungeared, real IRR Phase 1 output (1Mtpa ROM) 95 – 99%+ TGC purity US$116M 350ktpa 59% +80 mesh, 41% -80 Pha

  7. Slide 7: Black Rock: The premier graphite exposure

    Black Rock: The premier graphite exposure A world-class deposit with a superior development strategy For personal use only 01 Upstream focus with highly economic mine project 06 Premier location and logistics options 02 Deep evaluation work at real commercial scale 07 Fit-for-purpose project executi

  8. Slide 8: Upstream focus with highly economic mine project

    01  Core upstream, mine development strategy at Mahenge  Strongly differentiated from many of our graphite development peers Upstream For personal use only  Key competitive advantage is our resource and its properties focus with  Focussed on where our experience and expertise lets us extract val

  9. Slide 9: Deep work at real commercial scale

    02  Graphite is far from homogeneous  We have done the work needed to truly understand our: Deep work ‒ Deposit properties For personal use only at real ‒ Mine and process parameters ‒ Key product streams commercial  Our testwork results have been delivered at commercial scale scale  Two major p

  10. Slide 10: Leading product purity and residual chemistry

    03 Leading product purity and residual chemistry For personal use only A critical differentiator Product concentrates TGC range (%)  No overprint mineralisation = ability to deliver superior 100.0% 99%+ product purity and residual chemistry 99.0% 98.0%  Enables 99%+ TGC concentrate purity with sol

  11. Slide 11: Sensible market entry and growth strategy

     Sensible entry size (~85ktpa concentrate): limited enough to allow product 04 market integration but significant enough to deliver meaningful returns  Coarse distribution of Mahenge enables an effective dual project: Sensible For personal use only ‒ Approx. 60% coarse flake (+80 mesh; +180 micron

  12. Slide 12: Realistic, transparent price views

    05  Balanced approach relative to peers ‒ Lower relative large flake prices given less liquid markets and Realistic, significance to basket price calculation For personal use only ‒ Higher relative medium/fine flake prices given observed purity premium transparent and Mahenge concentrate grades pri

  13. Slide 13: Premier location and logistics

    06  Northern location of Mahenge offers significant competitive cost advantage  Proximity and access to rail and major port at Dar es Salaam Premier For personal use only  Dar es Salaam the premier coastal export option location and ‒ High-volume container port, superior logistics, no seasonal in

  14. Slide 14: Fit-for-purpose project execution plan

    07 Fit-for-purpose project execution plan For personal use only Low risk build and a plant design dedicated to product consistency  Major fabrication of plant components prior to shipping and on-site construction  Initial diesel genset power generation to minimise start-up and early supply risk 

  15. Slide 15: Responsibly sourced, sustainable graphite

     Equator Principles framework fully employed 08  Complete traceability of supply chain and proof of ethical sourcing Responsibly For personal use only  Strong community support and predominant use of local workforce  Access to hydro grid power (low emissions footprint) sourced,  Large grind siz

  16. Slide 16: Blended, risk-adjusted finance process

    09  Targeting a blended project financing model  Matching risks to participants best placed to manage them Blended, For personal use only  Key potential finance stakeholders include EPC vendor, offtake risk- counterparties and Tanzanian government  ICA Partners mandated as finance adviser adjust

  17. Slide 17: Superior stakeholder engagement

    10  Major project drives embedded national value  Focus on building appropriate, long-term sustainable relationships Superior For personal use only  Tanzania remains an excellent domicile – stable and LT conflict-free stakeholder  Permits received: ‒ Environmental permit engagement ‒ Mining lice

  18. Slide 18: Black Rock and the Mahenge Project

    Black Rock and the Mahenge Project The leading graphite development proponent For personal use only  Simple open pit project with outstanding forecast returns  Sector-leading product purity and residual chemistry proven at commercial scale  Premier project location and logistics  Risk-appropriat

  19. Slide 19: John de Vries, Managing Director and CEO

    For personal use only John de Vries Managing Director and CEO T: +61 438 356 590 E: jdv@blackrockmining.com.au A: 45 Ventnor Avenue West Perth WA 6005 www.blackrockmining.com.au

  20. Slide 20: Appendix: Mahenge Project Detail

    For personal use only Appendix: Mahenge Project Detail

  21. Slide 21: Mineral Resource and Ore Reserve estimates

    Mineral Resource and Ore Reserve estimates For personal use only Contained Category Tonnes (Mt) Grade (%TGC) Graphite (Mt) Ore Reserves Proven 0 0 0 Probable 69.6 8.5 6.0 Total Ore Reserves 69.6 8.5 6.0 Mineral Resources Measured 25.5 8.6 2.2 Indicated 88.1 7.9 6.9 Total Measured and Indicated Resou

  22. Slide 22: Enhanced DFS: Projected economics

    Enhanced DFS: Projected economics For personal use only Financial performance summary Unit LOM Project life Years 27.5 Operating life Years 26.0 Total LOM net revenue US$M, real 9,619 Graphite price (real) US$/t 1,301 Total project development capital costs US$M 337 C1 cost: real (including withhold

  23. Slide 23: Enhanced DFS: Forecast cashflow profile

    Enhanced DFS: Forecast cashflow profile Mahenge Graphite Project: 4-Phase Option Cashflow Profile For personal use only 400 Project Net Cashflow Post-Tax Project Net Cashflow Pre-Tax 350 6,250 Project Net Cashflow Pre-Tax Cumulative Project Net Cashflow Post-Tax Cumulative 300 5,250 Cumulative Cashf

  24. Slide 24: Enhanced DFS: Mining profile

    Enhanced DFS: Mining profile For personal use only Following release of the Enhanced Definitive Feasibility Study (DFS) on the Mahenge Graphite Project in July 2019 (see Black Rock ASX release dated 25 July 2019, Mahenge Enhanced DFS with Executive Summary), Black Rock confirms that it is not aware

  25. Slide 25: Enhanced DFS: Process flowsheet

    Enhanced DFS: Process flowsheet For personal use only Following release of the Enhanced Definitive Feasibility Study (DFS) on the Mahenge Graphite Project in July 2019 (see Black Rock ASX release dated 25 July 2019, Mahenge Enhanced DFS with Executive Summary), Black Rock confirms that it is not awa

  26. Slide 26: Enhanced DFS: Operating cost estimates

    Enhanced DFS: Operating cost estimates For personal use only Onsite power Grid power Cost Unit generation (rental) (TANESCO) Charge to provide services (fixed cost) US$/month 176,000 70,118 Power supply (variable cost) US$/kWh 0.263 0.067 LOM average Area US$M pa US$/t ore feed US$/t graphite produc

  27. Slide 27: Enhanced DFS: Capital cost estimates

    Enhanced DFS: Capital cost estimates For personal use only Stage 1 Stage 2 Stage 3 Stage 4 Total Area (WBS Level 1) '000 US$ '000 US$ '000 US$ '000 US$ '000 US$ Mining 10,165 - - - 10,165 Ifakara 1,366 1,041 727 682 3,816 Infrastructure 14,315 3,325 53,705 40,976 112,321 Process plant 50,877 45,300

  28. Slide 28: Enhanced DFS: Graphite pricing (at 98% LOI)

    Enhanced DFS: Graphite pricing (at 98% LOI) For personal use only Enhanced DFS Segment pricing Basket weight Shipping Channel & agent Contract discounts Basket FOB price deck segments (US$/t) (%) (US$/t) (US$/t) (US$/t) (US$/t) (Mesh #) +32 1,579 5 1.65 1.97 1.97 73 +50 1,449 18 5.96 6.52 6.52 242 +

Black Rock Mining — 121 Conference, New York 2019 on 6ix