Slide 1: Boral Deer Park Operations
Build something great™ ® Boral Deer Park Operations Deer Park Quarry Environmental Review Committee 17 March 2016
Slide 2: Agenda
Build something great™ ® Agenda Deer Park Quarry Environmental Review Committee- 17 March 2016 Welcome, introductions and apologies (5.00pm- 10 mins) Previous minutes and actions (10 mins) Business reports (30 mins) • Concrete • Asphalt • Quarry Environment (10 mins) Deer Park Quarry Plant
Slide 3: Boral personnel
Build something great™ ® Boral personnel Deer Park Quarry Environmental Review Committee- 17 March 2016 Paul Hodges Quarry Manager- Deer Park Michael Suddes (Apology) Operations Manager- Concrete West David Karstens (Apology) Plant Manager- Asphalt Cassi Sartori (Apology) Environment Coordin
Slide 4: Previous meeting minutes and actions
Build something great™ ® Previous meeting minutes and actions Erin Furmanczyk, Stakeholder Relations Advisor (Southern Region) No. Action Responsibility Due date 1 Provide information on blasting audit at next meeting (audit was GG TBA conducted by Earth Resource Regulation in December 2015) 4
Slide 5: Boral Operations Reports - Concrete
Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Concrete Michael Suddes, Operations Manager, Concrete West
Slide 6: Boral Operations Reports - Asphalt
Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Asphalt David Karstens, Plant Manager- Asphalt
Slide 7: Boral Operations Reports - Quarries
Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Quarries Paul Hodges, Quarry Manager, Boral Deer Park Quarry
Slide 8: Quarry – Monitoring Locations
Build something great™ ® Quarry – Monitoring Locations Deer Park Quarry Environmental Review Committee- 17 March 2016 Dust Monitors Blast Monitors A B
Slide 9: Quarry – Ambient Air - Ash
Build something great™ ® Quarry – Ambient Air- Ash Deer Park Quarry Environmental Review Committee- 17 March 2016 Deer Park Quarry - Ambient Air - Ash 70.0 65.0 60.0 Lab technicians reported evidence 55.0 of bird droppings in the vicinity 50.0 45.0 40.0 Ash (g/m2/month) 35.0 30.0 Train station const
Slide 10: Quarry – Blast Reports - Air Vibrations
Build something great™ ® Quarry – Blast Reports- Air Vibrations Deer Park Quarry Environmental Review Committee- 17 March 2016
Slide 11: Quarry – Blast Reports - Ground Vibrations
Build something great™ ® Quarry – Blast Reports- Ground Vibrations Deer Park Quarry Environmental Review Committee- 17 March 2016
Slide 12: CV T08 & transfer chute and dust control
CV T08 & 09 transfer chute and dust control Project – Deer Park For more details contact: Abs Nouh BEFORE AFTER Transport Inventory Motion Waiting Over Production Over Processing Defects Concern Cause Countermeasure Outcome After an RCA was completed on CV No dust extraction system causing Install a
Slide 13: Deer Park Quarry – Entry and Exit
Deer Park Quarry– Entry and Exit For more details contact: Tate Cromie – 0466 655 612 Tate.Cromie@boral.com.au BEFORE AFTER Transport Inventory Motion Waiting Over Production Safety Defects Concern Cause Countermeasure Outcome EPA Pin notice was given to Boral Entry and exit roads are unsealed Aspha
Slide 14: Environment
Build something great™ ® Environment Cassi Sartori, Environmental Coordinator, Boral OHS Functional Group
Slide 15: Deer Park Quarry Plant Replacement Project Update
Build something great™ ® Deer Park Quarry Plant Replacement Project Update Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project
Slide 16: Deer Park Quarry Replacement Project
Build something great™ ® Deer Park Quarry Replacement Project Luke Brown, Project Sponsor- Deer Park Quarry Replacement Project Replacement Plant Project Next Steps: Received Planning Approval 18th November from MCC All permit conditions submitted and approved to commence construction. Concr
Slide 17: Deer Park Quarry Replacement Project
Build something great™ ® Deer Park Quarry Replacement Project Luke Brown, Project Sponsor- Deer Park Quarry Replacement Project EPA and Melton City Council Planning Department advised to relocate OS2 monitor from South East to alongside construction site. Key Reason: Better manage dust created from
Slide 18: Deer Park Quarry Replacement Project
Build something great™ ® Deer Park Quarry Replacement Project Luke Brown, Project Sponsor- Deer Park Quarry Replacement Project Construction Dust Management: Monitor 2- PM10 4/3 Monitor relocated in-line with EPA and MCC advice Monitor 1- PM10 Monitor 1 no exceedance recorded Monitor 2 shifted fro
Slide 19: General business and community news
Build something great™ ® Boral Deer Park Operations General business and community news Erin Furmanczyk, Stakeholder Relations Advisor (Southern Region)
Slide 20: General business
Build something great™ ® General business Erin Furmanczyk, Stakeholder Relations Advisor (Southern Region) Correction of Boral information in newsletter Deer Park Quarry Plant Replacement Project- site tour proposed next meeting Erin Furmanczyk- 12 months maternity leave from early April Nex
Slide 21: Thank you for your attendance
® THANK YOU FOR YOUR ATTENDANCE Boral Deer Park contacts deerparkenquiries@boral.com.au Quarry – 9363 7850 Asphalt – 9360 4255 Concrete – 9361 2196 Erin Furmanczyk– Stakeholder Relations Advisor 03 9981 2925 or erin.furmanczyk@boral.com.au Paul Jackson – Stakeholder Relations Manager 0