Yancoal Australia Ltd. · ASX:YAL

Yancoal Australia — Corporate Update (February 2023)

13 slides from Yancoal Australia's corporate update, Feb 23, 2023

  1. Slide 1: Community Consultative Committee

    Community Consultative Committee 23rd February 2023

  2. Slide 2: Business Arising

    2 Business Arising a.Slashing in Camberwell

  3. Slide 3: Ashton Mine Statistics YTD 2022

    3 Ashton Mine Statistics YTD 2022 Ashton Coal Key Statistics` 2023 Budget 2023 Actual (31.01.2023) (31.01.2023) ROM (Mt) 0.271 0.281 Product Coal (Mt) 0.117 0.121 Total Coal Sales (Mt) 0.120 0.130 Total Recordable Injuries (TRI) 12 1 Total Employees (FTE) 345 277.43 Complaints 0 0 Environmental Inci

  4. Slide 4: Current Mining Plan

    Current Mining Plan ULLD Seam Pikes Gully Seam 2022 As Mined smmemes 2023 Proposed Mined 2022 As Mined sme 2023 Proposed Mined| ‘ASHTON UNDERGROUND MINE ag Coal 2022 MINED AND 2023 PROPOSED | Fo Box 4 Seen NSW 200 PG/AND ULLD SEAM MGA2020 fosyenrnoes [ws ame [amy | a

  5. Slide 5: Environment Monitoring Data

    5 Environment Monitoring Data ▪ Refer to monitoring data attachment

  6. Slide 6: Complaints and Incidents

    6 Complaints and Incidents • There have been no community complaints since the last meeting and none received in 2022. • There has been one environmental incidents since the last meeting where a small hole in the Borehole Pump 6 pipe was made by an excavator. The water was contained within the trenc

  7. Slide 7: Environmental Update

    7 Environmental Update ▪ Monthly groundwater monitoring undertaken. ▪ Monthly noise monitoring undertaken. No issues identified. ▪ Ancillary approvals progressing (Mining Lease, Management Plans (etc.)). ▪ Works are upcoming on raising the western block banks in Bowman’s Creek. ▪ Unannounced inspect

  8. Slide 8: Environmental Update

    8 Environmental Update ▪ Lemington Rd Subsidence Monitoring and Maintenance Program • A-Plus Contracting conducting monitoring and maintenance works which commenced 13th Feb 2023 – ongoing for the next several months until subsidence impacts have ceased. ▪ Maintenance repairs will be ongoing (24/7)

  9. Slide 9: Environmental Update

    9 Environmental Update ▪ Aboriginal Community Consultative Forum held in December. ▪ Archaeological salvage works – LW207A. • Throughout February, our archaeologist (Liz Wyatt) from Stratum Archaeology has been onsite with representatives of the Registered Aboriginal Parties to continue artefact sal

  10. Slide 10: Ashton-Ravensworth Integration (RUMEx)

    Ashton-Ravensworth Integration (RUMEx) Modification Applications Update ◼ ML transfers from Ravensworth completed (Dec 2022). ◼ First working development commenced in January 2023 . 10

  11. Slide 11: 2023 Ashton Coal Community Support Program

    11 2023 Ashton Coal Community Support Program

  12. Slide 12: Camberwell update

    12 Camberwell update • 33 Residential Tenancy Agreements • 11 Dwellings in Asset Maintenance Program • 16 Vacant residential lots • 2 Commercial agreements • 10 rural areas occupied • Aggregated rural land Glennie St – occupied under license agreement • Significant damage to driveways has occurred d

  13. Slide 13: Any Questions?

    13 Any Questions?