Cue Energy Resources Limited · ASX:CUE

Cue Energy Resources — NZ Oil & Gas Conference 2012

19 slides from Cue Energy Resources's conference presentation, Aug 9, 2012

  1. Slide 1: Cue Energy Overview - Maari Presentation

    A.B.N. 45 066 383 971 9 August 2012 For personal use only PAGES (including this page): 19 CUE ENERGY OVERVIEW Cue is an Australian based oil & gas Company Announcements Office company with projects in Australia, 10th Floor New Zealand, Indonesia and PNG. 20 Bond Street THE COMPANY HAS: Sydney NSW 20

  2. Slide 2: Maari Development - NZ Oil & Gas Conference

    OMV Exploration & Production For personal use only Maari Development NZ Oil & Gas Conference 8th August 2012 Move & More.

  3. Slide 3: Maari - Location

    Maari – Location For personal use only  The Maari Field is located in exploration permit PMP38160 in the offshore Taranaki Basin, New Zealand, approximately 35km south of the giant Maui gas field and 70km south-west of Opunaki.

  4. Slide 4: Maari - Exploration and Appraisal History

    Appraisal well For personal use only confirms Maari Moki Sandstone oil accummulation; Current JV formed. Development Manaia structure deemed sub- Maari-2 appraisal drilling at Maari 10 million barrel discovered commercial well drilled in 2003. commences. milestone at Maari. 1970 1983 1985 1998 1983

  5. Slide 5: Reservoir Intervals

    Maari – Reservoir Intervals For personal use only  Oil & Gas are recognised in a combination of three clastic reservoirs in two (maybe three) structures:  Miocene aged M2A Sands (oil)  Miocene aged Moki Formation (oil),  Eocene aged Mangahewa Formation (oil & gas)

  6. Slide 6: Moki Reservoir

    Maari – Moki Reservoir Maari-2 For personal use only Cycle 1 Cycle 2  Horizontal producers target the Cycle 1  Deviated water injectors are open Sandstone with the exception of MR2 hole completed in the Cycle 2 Lower Lateral that targets the Cycle 2 Sandstone with perforations added Sandstone in a

  7. Slide 7: Installed Infrastructure

    Installed Infrastructure For personal use only Jackup Drilling Rig Shuttle tanker FPSO Raroa 12 slot wellhead platform 10 slots used, 2 free Flowlines & umbilicals

  8. Slide 8: Current Facilities

    Maari – Current Facilities For personal use only

  9. Slide 9: Moki Development

    Maari – Moki Development For personal use only Maari Structure  Moki Sandstone (~1300mTVD)  Six horizontal oil producers including one dual lateral well giving ~11,000m horizontal section.  Three deviated water injector wells

  10. Slide 10: M2A Development

    Maari – M2A Development For personal use only Maari Structure  M2A Sandstone (~1230mTVD)  One horizontal oil producer with ~1,200m horizontal section

  11. Slide 11: Manaia - Mangahewa Development

    Manaia – Mangahewa Development For personal use only Manaia Structure  Mangahewa Formation (~2000mTVD)  One extended reach horizontal oil producer with ~1500m horizontal section.  Longest ERD well drilled in New Zealand at 7934mAH

  12. Slide 12: Growth Projects

    Growth Projects The goal -- increase production rates and extend the productive life of Maari For personal use only Appraisal Re- Development development 3D seismic acquired this New field development Additional ERD producer year at Maari, currently of the Mangaewa targeting Managewa being processed

  13. Slide 13: Growth Projects - Package

    Maari – Growth Projects – Package 1 For personal use only M2A Sst Moki Sst Mangahewa Sst F Sands New Maari Mangahewa Oil Producer (either dual lateral or splitter tree) New Manaia ERD Oil Producer Maari Structure Maari South Manaia Structure Structure

  14. Slide 14: Growth Projects - Side tracks

    Maari – Growth Projects – Side tracks For personal use only M2A Sst Moki Sst Mangahewa Sst F Sands Maari Structure Maari Moki Oil Producer Maari South Oil Producer option Maari South Manaia Structure Structure

  15. Slide 15: Growth Projects - Water Injection

    Maari – Growth Projects – Water Injection For personal use only M2A Sst Moki Sst Mangahewa Sst F Sands Maari Moki Water Injection improvement Maari Structure Maari South Manaia Structure Structure

  16. Slide 16: Drilling Workflow

    Maari – Drilling Workflow For personal use only Work-over Rig Programme Convert MR1 to water Reduce uncertainties on MR2 injector & conduct PLT to production. confirm injectivity along length of well bore Jackup Rig Programme Drill Maari Mangahewa dual lateral producer Reclaim MR7 Reclaim MR8 Reclai

  17. Slide 17: Growth Projects Timeline

    Maari – Growth Projects Timeline For personal use only Activity 2013 2014 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Appraisal/exploration drilling Rig Move Maari Mangahewa Manaia Mangahewa Moki Cycle 2 Producer New water injector Additional Maari side track producer

  18. Slide 18: Looking Forward

    Maari – Looking Forward  Maari has produced  We want to build on the For personal use only some 19 MM barrels of pioneering Maari oil so far. development by  appraising possible pools  developing new pools  infilling existing pools and  improving the Maari Moki water flood.

  19. Slide 19: For personal use only

    For personal use only I would like to thank the Maari Joint Venture for permission to present this Paper.

Cue Energy Resources — NZ Oil & Gas Conference 2012 on 6ix