Vertex Minerals Ltd. · ASX:VTX
Vertex Minerals — Mining Mondays June 2025
26 slides from Vertex Minerals's conference presentation, Jun 30, 2025
Slide 1: Vertex Minerals - Reward Gold Mine, Mining Mondays
Noosa Mining November 2024 Mining Conference VERTEX MINERALS LIMITED For personal use only REWARD GOLD MINE The High-grade gold producer and developer Roger Jackson Executive Chairman MINING MONDAYS JUNE 30th, 2025, | ASX: VTX 1
Slide 2: Disclaimer
Disclaimer The information contained in this presentation has been provided by Vertex Minerals Ltd (Company) and other sources identified herein. The information contained in this presentation is for informational purposes only and is not a recommendation as to whether to invest in the Company’s sha
Slide 3: Corporate Structure
CORPORATE STRUCTUREe Snapshot Share Price For personal use only VTX ASX Code 201m Shares on Issue ~$0.27 Share Price 118M Options and rights on Issue ~ $55M Market Capitalisation undiluted 28 JUNE 25 $1.4M +$1.6M* +$3.5M** + $7.5M*** Cash *Share Purchase Plan ** Recent Convertible loan Raise *** Rec
Slide 4: Directors and Management
DIRECTORS AND MANAGEMENTe Snapshot Roger Jackson - Executive Chairman 30+ years as a mine operator, services Management contractor and explorer. He is a geologist with strong knowledge of gold exploration and For personal use only mining General Manager Operations – Chris Hamilton Tully Richards - E
Slide 5: Flagship Project for Vertex - Reward High Grade Gold Mine, Hill End
Flagship Project for Vertex - Reward High Grade Gold Mine, Hill End ✓ Commenced Gold processing in new Gekko Gravity Gold plant For personal use only ✓ 100% owned Mining operation ✓ No hedge - No Secured debt – fully funded ✓ High Grade Gold Resource and Reserve 225 ozs at 16.7g/t + more ✓ Inherited
Slide 6: Unique Hill End Reward Gold Mine
UNIQUE HILL END REWARD GOLD MINE ✓High grade gold – Hawkins Hill 435kozs at 309 g/t ✓Reward resource 225kozs at 16.7 g/t For personal use only ✓Gold recovers up to 95% - by gravity only ✓No associated sulphide metals to speak of ✓23 fine gold ✓No gold in country rock ✓Textbook ore sorts ✓Recovers go
Slide 7: Amongst the Big Gold Systems in the Lachlan Fold Belt
AMONGST THE BIG GOLD SYSTEMS IN THE LACHLAN FOLD BELT For personal use only 7
Slide 8: Vertex Strategy
VERTEX STRATEGY CLEAR STRATEGY SET FOR HILL END For personal use only 1. To re install a refurbished a Gekko Gravity Gold plant in late 2024 2. To commence gold production from existing stockpiles in early 2025 3. Commence mining development in the high-grade Reward Mine in early 2025 4. To commence
Slide 9: Gekko Plant is installed at Hill End with an ore sorter
Gekko Plant is instated at Hill End with an ore sorter –small footprint Plant flowsheet For personal use only The New plant is located at the old plant site Utilising the existing • Gold Room • Water systems • Power generation • Offices • Change Rooms • Workshop • Storeroom • Crib Room • Jaw Crusher
Slide 10: Plant and Ore Sorter Up and Running
PLANT AND ORE SORTER UP AND RUNNING Under $9m total build cost For personal use only 10
Slide 11: Textbook Ore Sorting
TEXTBOOK ORE SORTING Reward gold mine ore sorts perfectly, with 79% mass reduction & 337.20% increase in grade in the 8mm to 50mm range. For personal use only Refer to VTX ASX announcement 11 of September 2024 To underground Mine Stope fill 11
Slide 12: For personal use only
For personal use only 12
Slide 13: Benefits of New Gravity Plant with Sorter
BENEFITS OF NEW GRAVITY PLANT WITH SORTER • New plant will be able to treat up 110ktpa • Fully Automated – Can be run off App on phone For personal use only • No Cyanide No chemicals • Only requires 2 operators- thus much lower operating costs • Processes the same ozs but in 1/3 of the time operatin
Slide 14: A Long Life Expected Beyond the Mine Plan
A LONG LIFE EXPECTED BEYOND THE MINE PLAN Exploration Target at Fosters, approx. 400m south of Reward Gold Mine. Fosters sits within ground already covered by Vertex Mining Licenses and existing Development Consent. Fosters is accessed by an existing Adit and development drive. For personal use only
Slide 15: Reward Underground Gold Mine - Fully Developed
REWARD UNDERGROUND GOLD MINE- FULLY DEVELOPED The Reward gold mine is well-placed for a simple start-up: ✔ The existing gravity processing plant is located adjacent to the underground mine access point/Adit For personal use only ✔ Mine access point extends into the resource, so little development is
Slide 16: Reward Underground Gold Mine
REWARD UNDERGROUND GOLD MINE The Reward gold mine is near MINE READY: ✔ Gold Ore Ready to Mine ✔ Multiple headings to advance on For personal use only ✔ Advanced Underground Mining Equipment on site/near to ✔ Highly skilled Miners on boarded – The Vertex way – Owner Operator – Grade is KING ✔ Produc
Slide 17: 2009-2010 Underground Development
2009-2010 Underground Development with declines developed to first production for Vertex Circa $25m spent on development - all in infrastructure estimated at $80M+. For personal use only Reward Shaft Legend 2008 and Prior Development 2009 Development 2009 Development Rises 2009 & 2010 Development 20
Slide 18: Mining Sequence
For personal use only MINING SEQUENCE 18
Slide 19: Hill End Gold Production Financials from PFS
HILL GOLD PRODUCTION FINANCIALS from PFS does not include stockpile processing Note: based on Indicated Resource only – This is a JORC rule. (The model uses 50kozs of the 225kozs at 16.7 g/t) First 6 months day shift only at a reduced input. For personal use only Project Life Gold Production Gross R
Slide 20: We Purchased Our Own Underground Diamond Rig
We purchased our own underground diamond rig The diamond rig will be utilised to target ✔ the ultra high grade vein system that For personal use only runs down plunge of Reward ✔ to bring the Reward Resource into Indicated- 225 kozs @16.7 grams ✔ The exploration target • Vertex plan to run the mine
Slide 21: Scratching the Surface: Fosters Adit Channel Sampling
SCRATCHING THE SURFACE: FOSTERS ADIT CHANNEL SAMPLING Plan view: 1m interval channel sample across two veins (g/t Au) For personal use only Fosters Adit 6.6% 6.2% Channel sample results referred to in ASX Announcement 29 August 2023 21
Slide 22: Scratching the Surface: Large Tenement Holding and Multiple Targets
Scratching the surface Large Tenement Holding and Multiple Targets For personal use only • 34km of prospective strike that was the source of the largest Gold specimen ever to be found globally - discovered at Hill End • Most lodes only mined to the water table (60 feet) • Lidar survey completed6.6%
Slide 23: Environmental and Sustainable Mining Objectives
Environmental and Sustainable Mining Objectives Environmentally Responsible and Sustainable Gold Miner For personal use only • Gravity Recoverable Gold • Low Capex and Low Operating cost • Minimal grind 200 to 650 micron • Benign tails – potential commercial sand • Benign waste • Low water usage • R
Slide 24: Vertex Summary
VERTEX SUMMARY • Australia's next high grade gold producer For personal use only • 100% ownership of Hill End gold production and exploration assets in HILL END NSW with historical gold production more than 1.8 million oz gold from within our tenements • Only 40 odd kms from Australia's largest gold
Slide 25: Contact Us
CONTACT US For personal use only ROGER JACKSON roger@vertexminerals.com.au HEAD OFFICE – HILL END Bowen Street Hill End +61 2 7229 4849 www.vertexminerals.com.au admin@vertexminerals.com.au ACN – 650 116 153 25
Slide 26: Robust and Primed to Grow Gold Inventory
ROBUST AND PRIMED TO GROW GOLD INVENTORY For personal use only Where statements in this announcement refer to exploration results which previously been reported, the Company confirms that it is not aware of any new information or data that materially affects the information included in the original