Rockhaven Resources Ltd. · TSXV:RK
Rockhaven Resources — Investor Presentation (August 2021)
27 slides from Rockhaven Resources's investor presentation, August 2021
Slide 1: Corporate Presentation August 2021
Corporate Presentation August 2021 TSX-V: RK TSX-V:RK OTC:RKHNF
Slide 2: Forward Looking Statements
FORWARD LOOKING STATEMENTS Certain information contained herein may constitute forward-looking statements within the meaning of applicable securities laws. Forward-looking statements may include estimates, plans, expectations, opinions, forecasts, projections, guidance or other statements that are n
Slide 3: Corporate Summary
Corporate Summary SHARES OUTSTANDING: 208,036,470 Management / Directors / Advisors SHARES FULLY DILUTED: 251,567,729 Matt A. Turner, B.Sc. President, CEO and Director MARKET CAPITALIZATION: C$22,000,000 Manuel Estrada, B.Sc. COO WORKING CAPITAL: ~C$2,700,000 Larry Donaldson, CA CFO CORPORATE DEBT:
Slide 4: Company Highlights
COMPANY HIGHLIGHTS • Rockhaven’s road accessible Klaza project is one of Yukon’s highest grade, plus one million ounce gold deposits • Robust PEA with a Post-Tax NPV(5%) of C$378 million and an IRR of 37% ($1,450/oz Au & $17/oz Ag) • Klaza Deposit is 100% owned and royalty free • District scale land
Slide 5: Greenfields Discovery within the +15 Moz Au Dawson Gold Belt
GREENFIELDS DISCOVERY WITHIN THE +15 Moz Au DAWSON GOLD BELT Access Road to Klaza Camp Klaza Deposit TSX-V:RK OTC:RKHNF 5
Slide 6: Property Geology
PROPERTY GEOLOGY TSX-V:RK OTC:RKHNF 6
Slide 7: Property Geology Detailed
PROPERTY GEOLOGY DETAILED TSX-V:RK OTC:RKHNF 7
Slide 8: Property Ownership
PROPERTY OWNERSHIP • 100% owned by Rockhaven with no underlying royalties on resource areas • Property covers 287 sq kms • 1,273 of the total 1,478 claims are unencumbered by royalties or interests • Claims have been acquired patiently over time and in-line with our growing knowledge of the district
Slide 9: High-Grade Epithermal Gold-Silver Mineralization
HIGH-GRADE EPITHERMAL GOLD-SILVER MINERALIZATION 94.09 g/t gold, 545 g/t silver, 2.86% lead and 4.21% zinc over 2.63 m KL-17-401 KL-17-401 - Detailed TSX-V:RK OTC:RKHNF 9
Slide 10: From Rocks to Resources
FROM ROCKS TO RESOURCES Klaza Property - Total Inferred and Indicated Mineral Resource Estimate Summary1 Grade Contained Metal Category Tonnes Au Ag Pb Zn Au EQ4 Au Ag Pb Zn Au EQ4 (kt) (g/t) (g/t) (%) (%) (g/t) (koz) (koz) (klb) (klb) (koz) Indicated 5 Pit- Constrained2,3 2,447 5.3 90 0.7 1.0 6.7 4
Slide 11: Klaza Deposit Block Model
KLAZA DEPOSIT BLOCK MODEL Central Klaza Central Klaza: 325 m below surface 6.70 m grading 11.90 g/t gold Central Klaza: 450 m below surface Western Klaza: 250 m below surface 2.00 m grading 3.18 g/t gold and 1.46 m grading 15.38 g/t gold, 741 g/t silver 43.52 g/t silver Deepest Drill Intersection in
Slide 12: 2020 PEA Highlights
2020 PEA HIGHLIGHTS • NPV(5%) – After-tax C$378 m & Pre-tax C$529 million ($1450 gold, $17 silver, CAD:USD 0.72) • IRR – 37% After-tax & 45% Pre-tax • Leverage to $1,740 gold – After-tax NPV(5%) of C$540 million and IRR of 49% • Opex – LOM cash costs of $613/oz AuEq* AISC of $875/oz AuEQ* • Initial
Slide 13: 2020 PEA Details
2020 PEA DETAILS • Study completed by AMC Mining Consultants (Canada) Ltd. (mineral resource, mining, infrastructure and financial analysis), Blue Coast Metallurgy Ltd. (metallurgy and processing) and Knight Piesold Ltd (tailings). • Combined Open Pit (contractor) & UG (owner-operator) mine with a 1
Slide 14: Klaza Project – PEA Surface Overview
KLAZA PROJECT – PEA SURFACE OVERVIEW BRX Western BRX Portal Mill Area KLAZA Tailings Storage Open Pits: 1.2 Mt mined containing approximately: 90,000 oz gold, 1.3 Moz silver, 11.1 Mlbs lead, and 18.1 Mlbs zinc For additional information about the 2020 Klaza property Preliminary Economic Assessment,
Slide 15: Klaza 2020 PEA – Mine Plan
KLAZA 2020 PEA – MINE PLAN Open Pits: 1.2 Mt mined containing approximately: 90,000 oz gold, 1.3 Moz silver, 11.1 Mlbs lead, and 18.1 Mlbs zinc Central BRX UG, 1.3 Mt mined containing approximately: 69,000 oz gold, 4.0 Moz silver, 25.6 Mlbs lead, and 26.4 Mlbs zinc Western BRX UG, 2.4Mt mined contai
Slide 16: 2020 PEA Summary
2020 PEA SUMMARY Unit July 2020 Unit July 2020 PEA PEA Total mineralized rock kt 7,464 Total net revenue C$M 1,975 Total waste production kt 10,130 Project capital costs C$M 244 Gold grade1 g/t 3.4 Sustaining capital costs C$M 114 Silver grade1 g/t 79 Operating costs (total) C$M 834 Lead grade 1 % 0
Slide 17: Production Summary
PRODUCTION SUMMARY Annual Payable Metal Production TOTAL 1 2 3 4 5 6 7 8 9 10 11 12 Gold (oz) 751,472 48,656 58,572 93,011 98,195 93,775 82,318 80,087 62,401 49,947 45,485 26,433 12,592 Silver (oz) 13,799,820 588,268 765,112 1,645,459 1,499,457 1,544,120 1,430,480 1,560,272 1,145,208 1,031,574 1,133
Slide 18: Simplified Processing Flow Sheet
SIMPLIFIED PROCESSING FLOW SHEET Lead (1.1% Mass Pull) Acacia Leach 59.8% Pb 60% Pb Sequential Flotation Crushing & Grinding 5,957 g/t Ag 4,815 g/t Ag 129.9 g/t Au 15.7 g/t Au 1,900 tpd Zinc 95% Au Recovery • High recovery of all metals to (2.2% Mass Pull) 86% to Doré three separate concentrates 48.
Slide 19: 2020 PEA Sensitivities
2020 PEA SENSITIVITIES Post-Tax Sensitivities -20% Base Case +20% Variable Unit Value NPV IRR Value NPV IRR Value NPV IRR Gold US$/oz $1,160 $211 24% $1,450 $1,740 $540 49% Silver US$/oz $13.60 $343 35% $17.00 $20.40 $407 39% $378 37% Mining Cost $/t $44.1 $417 39% $55.14 $66.2 $334 34% Processing C
Slide 20: 2021 Catalysts
2021 CATALYSTS Exploration drilling on high-grade vein and porphyry targets: • Rusk – 2.6 sq. km arsenic-in-soil anomaly with newly (2020) identified vein discoveries • Kelly/Etzel-Cyprus Porphyry – Porphyry and bulk tonnage targets adjacent to Klaza vein field • Western BRX Extension to explore exp
Slide 21: 2021 Porphyry Targets
2021 PORPHYRY TARGETS For additional information about the 2021 Klaza property exploration program see press release dated of May 10 2021 which can be viewed at www.sedar.com under the Rockhaven profile or on the Rockhaven website at www.rockhavenresources.com. TSX-V:RK OTC:RKHNF 21
Slide 22: 2021 Porphyry Targets
2021 PORPHYRY TARGETS For additional information about the 2021 Klaza property exploration program see press release dated of May 10 2021 which can be viewed at www.sedar.com under the Rockhaven profile or on the Rockhaven website at www.rockhavenresources.com. TSX-V:RK OTC:RKHNF 22
Slide 23: 2021 Infill Drilling
2021 INFILL DRILLING • Infill drilling of the Klaza Deposit will focus on upgrading inferred resources into indicated resources • A total of 5,000 m in 33 holes is planned for 2021 • Previous upgrading was done at a low cost ($4/ounce) • This drilling will also support additional metallurgical test
Slide 24: Rusk Target – 2021 Follow-Up on New Discovery
RUSK TARGET – 2021 FOLLOW-UP ON NEW DISCOVERY A Cross- A’ Section A A’ For additional information about the 2020 Klaza property and the Klaza property Preliminary Economic Assessment, please see Rockhaven’s technical report with an effective date of July 10 2020 and titled, “Technical Report and Pre
Slide 25: 2020 Discoveries at the Rusk Target
2020 DISCOVERIES AT THE RUSK TARGET 2020 Drill Highlights* from the Rusk Target Include: 16.35 g/t gold, 321 g/t silver, 1.98% lead and 1.01% zinc over 0.63 m 16.15 g/t gold, 581 g/t silver, 2.06% lead and 1.26% zinc over 0.50 m 2.10 g/t gold, 657 g/t silver, 12.98% lead and 6.17% zinc over 1.00 m 2
Slide 26: Company Goals
COMPANY GOALS • Expanded production profile to 100,000 oz Au for 10 - 15 years • Infill drilling for conversion of remaining inferred resources • Near resource expansion drilling & outboard vein field represent prime targets for drilling • Test vertical extent of high-grade system • Trade-off study
Slide 27: Thank You!
Contact Info: Matt Turner Phone: 604-688-2568 E-mail: mturner@rockhavenresources.com Website: www.rockhavenresources.com Thank You! TSX-V:RK OTC:RKHNF