  1. Slide 1: Performance Based Contracting

    Slide 1: Performance Based Contracting

    Workable solutions to help you make the difference. Performance Based Contracting Jan-2003 The Credit Rating Information Services of India Limited

  2. Slide 2: Agenda

    Slide 2: Agenda

    Agenda  PBC Defined  Evolution of PBC  Percolation of PBC to Industry  Spread of PBC Globally  PBC in Construction ΠKey performance parameters in construction ΠPBC Contracts in construction and examples  PBC in Private Sector Participation projects  Conclusion Workable solutions to help you

  3. Slide 3: PBC defined

    Slide 3: PBC defined

    PBC defined Performance-based contracting means structuring all aspects of an acquisition around the purpose of the work to be performed with the contract requirements set forth in clear, specific, and objective terms with measurable outcomes. [Source:Federal Acquisition Regulations FAR 2.101, USA]

  4. Slide 4: Evolution of PBC

    Slide 4: Evolution of PBC

    Evolution of PBC  PBC as a concept evolved around the WW-II as national security depended on appropriate execution of contracts ΠKey performance parameters were timely delivery and secrecy  Federal Acquisition Regulations (FAR) in the US institutionalised PBC.  Office of Federal Procurement Poli

  5. Slide 5: Percolation of PBC to industry

    Slide 5: Percolation of PBC to industry

    Percolation of PBC to industry  President Truman called upon corporate chiefs to provide technical experts for the war  Many key executives from companies like GE and Dupont were deputed in the war  They brought back the military purchasing systems as a legacy of the war to their respective corpo

  6. Slide 6: Spread of PBC globally

    Slide 6: Spread of PBC globally

    Spread of PBC globally  USA- 1950’s  New Zealand- 1980’s  France-1990  Belgium- Early nineties  Denmark- 1992  Finland-1995 Workable solutions to help you make the difference. 6

  7. Slide 7: PBC in construction

    Slide 7: PBC in construction

    PBC in construction Workable solutions to help you make the difference. 7

  8. Slide 8: Key parameters in construction

    Slide 8: Key parameters in construction

    Key parameters in construction Stage Impact of this step on Fraction of project Degree of Benefits of project Cost(C), Time(T) Cost and Time spent outsourcing innovation and Quality(Q) in this step Project C – Average-High C – Low Low High planning T – Average-High T – Low Q – Low Preliminary C – Av

  9. Slide 9: Types of PBC in construction

    Slide 9: Types of PBC in construction

    Types of PBC in construction  A+B Bidding  Lane Rental  Design-Build  Interim Completion Date  Target Price Contracts  Design-Build- Warranty  Design-Build-Operate Workable solutions to help you make the difference. 9

  10. Slide 10: A+B Bidding

    Slide 10: A+B Bidding

    A+B Bidding  Performance Parameter ΠTime taken for project completion  Selection criteria ΠLowest of traditional contract unit price based bid (A) + time value component proposed by the bidder to complete the project (B)  Applicability ΠConstruction of flyovers on busy interchanges ΠRail over

  11. Slide 11: Lane Rental

    Slide 11: Lane Rental

    Lane Rental  Performance Parameter ΠMinimum time taken for project implementation  Selection criteria Πcost to perform the work (A component) + cost of the impact to the public (B component) to provide the lowest cost to the public  Applicability ΠLaying of utilities below roads or maintenance

  12. Slide 12: Design Build

    Slide 12: Design Build

    Design Build  Performance Parameter ΠInnovative design and value engineering  Selection criteria ΠLowest design and build cost  Applicability ΠExpressways on new alignment ΠComplex bridges, viaducts and tunnels ΠMetro rail projects ΠPort projects Workable solutions to help you make the diff

  13. Slide 13: Interim Completion Dates

    Slide 13: Interim Completion Dates

    Interim Completion Dates  Performance Parameter ΠCompletion of project portions/milestones in specified timeframes  Selection criteria ΠUsual criteria used  Applicability ΠFoundation for bridges/dams prior to monsoon ΠSafety features in public buildings under construction ΠOPD facilities in

  14. Slide 14: Target Price Contracts

    Slide 14: Target Price Contracts

    Target Price Contracts  Performance Parameter Î Overall project cost  Selection criteria Î lowest of Target Price + Project execution fee Î project cost is reimbursed on actuals and the contractor’s execution fee is reduced (in agreed proportions) if the actual project cost is above tendered cost

  15. Slide 15: Design-Build-Warranty

    Slide 15: Design-Build-Warranty

    Design-Build-Warranty  Performance Parameter ΠProject maintenance costs and downtime  Selection criteria Πthe combined lump sum design cum build fee quote  Applicability ΠConstruction of ships ΠLocomotives Workable solutions to help you make the difference. 15

  16. Slide 16: Design-Build-Operate

    Slide 16: Design-Build-Operate

    Design-Build-Operate  Performance Parameter ΠLife Cycle Cost of Project  Selection criteria Πthe combined lump sum design cum build fee quote  Applicability ΠMetro rail ΠWater and waste treatment plants Workable solutions to help you make the difference. 16

  17. Slide 17: PBC in the Indian Context

    Slide 17: PBC in the Indian Context

    PBC in the Indian Context Workable solutions to help you make the difference. 17

  18. Slide 18: Highways Construction

    Slide 18: Highways Construction

    Highways Construction  Construction of National Highways under the annuity scheme ΠJaipur-Kishangarh, Panagarh-Palsit and Tambaram-Tindivanam sections of National highways  Annuity is Build-finance-operate contract, where contractor is also given the option to review and modify project design  T

  19. Slide 19: Contract Structure

    Slide 19: Contract Structure

    Contract Structure Performance Performance Penalties Incentives Parameters requirement Pro-rata reduction in Life cycle cost Timeliness in Annuity payment Pro-rata construction increase in Lane availability annuity amount Selection based on Lane Reduction in annuity NA. lowest annuity payable availa

  20. Slide 20: Water Project

    Slide 20: Water Project

    Water Project  Water treatment and distribution project in Delhi  Design-Build-Operate with the contractor had to minimise life cycle cost  The payment mechanism comprised two components: Πa pre-determined lumpsum component towards construction Πand fixed O&M costs as also a variable component

  21. Slide 21: Contract Structure

    Slide 21: Contract Structure

    Contract Structure Performance Performance Penalties Incentives parameters requirement Liquidated All parameters that have Quality and timeliness in damages Performance a bearing on the plant’s construction Retention money bonus long-term lifecycle cost Performance were identified and guarantee fact

  22. Slide 22: PBC in PSP Projects

    Slide 22: PBC in PSP Projects

    PBC in PSP Projects Workable solutions to help you make the difference. 22

  23. Slide 23: Port Sector

    Slide 23: Port Sector

    Port Sector  The contract for construction of terminals in major ports specifies minimum guaranteed traffic as performance parameter  The minimum guaranteed traffic ensures: Πthe Major Port recovers not only its investment in the waterside and linkage infrastructure Πopportunity cost of developm

  24. Slide 24: Power

    Slide 24: Power

    Power  In power generation projects, the developer is incentivised to increase the Plant Load Factor (PLF)  Conversely there are penalties for operation below a certain PLF Workable solutions to help you make the difference. 24

  25. Slide 25: Conclusion

    Slide 25: Conclusion

    Conclusion  Internationally more than 50% of all contracts have performance parameters specified  Increasingly we will find PBC replacing traditional contracting methods in India also  New techniques of PBC can and will be developed based on need  For continued growth in construction industry, g

  26. Slide 26: Thank You

    Slide 26: Thank You

    Workable solutions to help you make the difference. Thank You Contact Details: Phone: +91 (22) 5691 3001- 09 The Credit Rating Information Services Fax: +91 (22) 5691 3000 of India Limited www.crisil.com