  1. Slide 1: Denver Gold Forum

    Denver Gold Forum September 20-23, Virtual TSX: IMG l NYSE: IAG

  2. Slide 2: Cautionary Statement

    Cautionary Statement All information included in this presentation whether in narrative or chart form, including any information as to the Company’s future financial or operating performance, and other statements that express management’s expectations or estimates of future performance, other than s

  3. Slide 3: Technical Information and Qualified Persons

    Technical Information and Qualified Persons The mineral resource estimates contained in this news release have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). The Qualified Person (“QP”) responsible for the review and approval o

  4. Slide 4: IAMGOLD – Positioned for Profitable Growth

    IAMGOLD – Positioned for Profitable Growth • Three operating mines on three continents with 2020 guidance of 645-700koz1 Diversified Operating I • Disciplined approach to realizing value – targeting a self-funding model at each operation Portfolio • Operating improvements: Essakane optimization, Sar

  5. Slide 5: Strategic Focus

    Strategic Focus TRANSFORMATION THROUGH ORGANIC GROWTH TO REALIZE VALUE Strategic Deliverables Strategic focus • Improved consolidated costs / increased margins • Achieve self-funding at each operating site • Increased gold production • Greater operational flexibility • Sequence development of organi

  6. Slide 6: Diversified Operating Portfolio

    I Diversified Operating Portfolio Diversified Operating Portfolio GLOBAL OPERATING, DEVELOPMENT AND EXPLORATION PROJECTS HISTORICAL GOLD PRODUCTION (Attributable Gold Production, koz) Operating Mine 1,000 – 1,300 Development Project 882 882 Advanced Exploration 806 813 762 Strategic Equity Interest

  7. Slide 7: Improving Operating Performance Creates Foundation for Growth

    I Diversified Operating Portfolio Improving Operating Performance Creates Foundation for Growth Manage operating costs to maintain positive cash flow • Reinforcing the Self-Funding model at each operation • Retain conservative reserve cut-off based on gold price Essakane, Burkina Faso of $1,200/oz (

  8. Slide 8: Meaningful Production Growth

    II Compelling Value & Production Growth Meaningful Production Growth FULLY FUNDED PEER-LEADING ORGANIC GROWTH PROFILE SUPPORTED BY SOLID OPERATING BASE (2020 Attributable Gold Production, koz2) 2024 +71% 1,375 Target1 1,000 – 1,300 Achievable 2020 923 905 Guidance Pathway to 890 786 780 746 645 – 70

  9. Slide 9: Industry Leading Reserve Growth

    II Compelling Value & Production Growth Industry Leading Reserve Growth 17.9Moz 18 16.7Moz IAMGOLD P&P Reserves 14.5Moz 13 11.3Moz 10.1Moz 8.6Moz +101% Growth in Reserve Base 7.7Moz 7.8Moz 8 512Moz 87 3 422Moz (18%) Decline in Reserve Base 24 395Moz 19 78 365Moz -2 349Moz 60 75 328Moz 23 69 314Moz 1

  10. Slide 10: Côté Gold – Potential Global Tier I Gold Asset

    II Compelling Value & Production Growth Côté Gold – Potential Global Tier I Gold Asset A WORLD-CLASS PROJECT WITH DISTRICT SCALE POTENTIAL IN MINING-FRIENDLY CANADA Tier I Asset Criteria* I Mine Life >10 Years I 18+ Year Mine Life with district expansion potential  • Based on only current mineral r

  11. Slide 11: Compelling Value Proposition

    II Compelling Value & Production Growth Compelling Value Proposition ATTRACTIVE UPSIDE RELATIVE TO MID-TIER PEER GROUP Financial Metrics1 Mineral Reserves2 PRICE / 2021E OPERATING CASH FLOW (P/CF, x) PROVEN & PROBABLE RESERVES (MOZ) Estimated Reserve Life3 (Au Moz) 10.9x 20.4 9.9x 9.7x Substantial M

  12. Slide 12: Compelling Value Proposition

    II Compelling Value & Production Growth Compelling Value Proposition ATTRACTIVE UPSIDE RELATIVE TO MID-TIER PEER GROUP Price / Net Asset Value (NAV)1 (P/NAV, x) DIVERSIFIED GOLD PRODUCTION SPLIT 2024 Annual Production Target2 1.67x 1.62x 1.60x North America Africa 33% 1.37x +1 Moz 44% 1.33x Mid-Tier

  13. Slide 13: Maintaining a Strong Balance Sheet

    III Strong Financial Position Maintaining a Strong Balance Sheet LIQUIDITY WELL ABOVE $1 BILLION Available Cash & Cash Credit Facility $500 M $832 M Equivalents1 Total Liquidity $1.3B 2 Senior Notes Outstanding Coupon: 7%; Maturity: April 15, 2025 Corp Rating: B1 (Moody’s) and B+ (S&P) Short-term In

  14. Slide 14: Leader Among Peers: Leverage and Liquidity

    III Strong Financial Position Leader Among Peers: Leverage and Liquidity 2.4x FAVOURABLY POSITIONED AMONG PRODUCER PEER GROUP Debt / 2021E EBITDA1,2 Net Debt / 2021E EBITDA1,2 1.4x 1.3x 1.1x 1.1x 1.0x 1.0x 0.9x 0.8x 0.7x 0.7x 0.7x 0.6x 0.5x 0.4x 0.4x 0.4x 0.3x 0.2x Net Net Net Net <0.1x Cash Cash Ca

  15. Slide 15: Environmental, Social and Governance (ESG)

    IV Culture of Accountable Mining Environmental, Social and Governance (ESG) Recent Highlights Strong ESG practices • Donations to local communities in response to the global COVID-19 crisis: – Cleaning equipment and supplies (hand-washing stands, hand-sanitizing gel) • Implemented the Toward Sustain

  16. Slide 16: Adapting to Our New Normal: COVID-19 Response

    IV Culture of Accountable Mining Adapting to Our New Normal: COVID-19 Response Zero Harm© is our commitment to continually strive to reach the highest standards in human health & safety, minimize our environmental footprint, and work co-operatively with our host communities. • COVID-19 in H1 2020: •

  17. Slide 17: COVID-19 Measures Across Operations

    IV Culture of Accountable Mining COVID-19 Measures Across Operations Essakane, Burkina Faso Rosebel, Suriname Westwood, Canada Left: Bus pick up Left: Successful first point incorporates attempt to bring workers social distancing underground under new and reduced protocol, including numbers in each

  18. Slide 18: Focus on Safety: Historical DART & TRI Rates

    IV Culture of Accountable Mining Focus on Safety: Historical DART & TRI Rates HISTORICAL GLOBAL DART & TRI RATES PER 200,000 HOURS WORKED DART1: 2020 TARGET – 0.57 2.40 TRI1: 2020 TARGET – 0.94 1.98 1.81* 1.76* 1.53* 1.56 1.44* 1.44 1.18 1.13 1.06 1.06 1.00 0.87 0.93 0.85 0.64 0.68 0.66 0.53 0.53 0.

  19. Slide 19: Ensuring a Robust Pipeline

    IV Robust Pipeline of Projects Ensuring a Robust Pipeline FUTURE PRODUCTION AND GROWTH OPPORTUNITIES GROWTH OPPORTUNITIES • Gosselin (Côté), Ontario • Diakha-Siribaya, Mali • Karita, Guinea • Monster Lake, Quebec Saramacca, Suriname Mill Optimization, Burkina Faso Côté Gold Project, Ontario • Fayoll

  20. Slide 20: Robust Exploration Pipeline

    IV Robust Pipeline of Projects Robust Exploration Pipeline West Africa North America South America Fala/Fala E Grand Duc Saramacca >5 Moz Au Production >2 Moz Au <2 Moz Au Côté Construction Brownfield Advanced Greenfield Greenfield Boto Fayolle Feasibility Study Diakha-Siribaya Monster Lake Saõ Seba

  21. Slide 21: Catalysts – 2020 Sets Up Improved Profile for 2021

    Catalysts – 2020 Sets Up Improved Profile for 2021 2020 2021*  Westwood NI 43-101 o Westwood Expands Production  Côté Construction Go-ahead o Rosebel Ramp-up with Saramacca o Saramacca Full Production o Essakane Optimized Mill o Essakane CIL Plant Optimization o Advancing Growth Projects o De-risk

  22. Slide 22: Operations

    Operations Photo: Wärtsilä 22

  23. Slide 23: Rosebel Gold Mine, Suriname

    Rosebel Gold Mine, Suriname 23

  24. Slide 24: Rosebel – Overview

    Rosebel – Overview OVERVIEW KEY NOTES Brokopondo district in north-eastern Suriname Ownership • Gross Rosebel Concession: 95% IAMGOLD, 5% Reserves & Resources Government of Suriname • Rosebel’s reserves & resources • UJV – 70% IAMGOLD, 30% extends mine life to 2033 including Staatsolie Saramacca Min

  25. Slide 25: Saramacca Update

    Saramacca Update MINDRINETTI BRIDGE – COMPLETE SARAMACCA ROM PAD 25

  26. Slide 26: Essakane Gold Mine, Burkina Faso

    Essakane Gold Mine, Burkina Faso 26

  27. Slide 27: Essakane – Overview

    Essakane – Overview OVERVIEW KEY NOTES North-eastern Burkina Faso, West Africa Ownership • 90% IAMGOLD, 10% Government of Burkina Faso CIL (carbon-in-leach) Debottlenecking Mining • Conventional drill, blast, load and • Improve throughput and gravity Method haul surface mining method recovery, $9M c

  28. Slide 28: CIL/HL Feasibility Study Highlights

    CIL/HL Feasibility Study Highlights HIGHLIGHTS1 KEY NOTES Mine Life 2031 CIL Optimization Study Mining Capacity 55.0 Mtpa • FS supported increasing mill throughput to 11.7Mtpa (hard rock) from 10.8Mtpa CIL Milling Capacity 11.7 Mtpa • Minimal capital outlay of $9 million with commissioning targeted

  29. Slide 29: Westwood Gold Mine, Canada

    Westwood Gold Mine, Canada 29

  30. Slide 30: Westwood – Overview

    Westwood – Overview OVERVIEW KEY NOTES Northwestern Québec – A Prolific Gold Mining Camp Ownership • 100% IAMGOLD Progressing Development Mining • Underground • Targeting safe, profitable, long life Method Production • Began commercial production in mine Status July 2014 • Ramp-up production and cos

  31. Slide 31: Westwood – “Hub-and-Spoke” Model

    Westwood – “Hub-and-Spoke” Model ATTRACTIVE DISTRICT EXPLORATION POTENTIAL1 THAT COULD SUPPLEMENT EXCESS MILL CAPACITY FAYOLLE PROPERTY (OP) A B ROUYN GOLD PROJECT (UG) 100% ACQUIRED FROM MONARCH GOLD IN JUNE 2020 OPTION TO ACQUIRE 100% FROM YORBEAU RESOURCES A Fayolle • ~35 km northeast of Rouyn-No

  32. Slide 32: Construction Review

    Construction Review id COTEGOLD 3 IAMGOLD

  33. Slide 33: Transformational Value in Canada

    Transformational Value in Canada CÔTÉ GOLD – HIGHLIGHTS • NPV5% of $2.5B and IRR of 25.9% at US$1,900 / oz gold1,2 ONTARIO QUÉBEC • NPV5% of $1.1B and IRR of 15.3% at US$1,350 / oz gold1,2 • Annual gold production 469 koz at $693 / oz AISC, first 6 years2 • 18+ year potential mine life2 Kapuskasing

  34. Slide 34: Key Project Metrics

    Key Project Metrics C$ 10B* C$ 5B* In estimated economic activity during In wages forecast through direct PROJECT HIGHLIGHTS: GO-FORWARD UPDATE1,2 the mine’s operations and indirect job creation (100% basis, average LOM) Mine Life 18 years Open Pit Mining 70 Mtpa Mill Capacity 13.1 Mtpa (36,000 tpd)

  35. Slide 35: Sensitivity to Gold Price – Project Economics

    Sensitivity to Gold Price – Project Economics SIGNIFICANT LEVERAGE TO THE GOLD PRICE After-Tax Net Present Value (NPV5%) – 100% Basis1 After-Tax Internal Rate of Return (IRR) – 100% Basis1 (US$Bn) (%) Spot Gold2 Spot Gold2 $2.8 27.6% Base 25.9% $2.5 Case 24.2% $2.3 22.4% Base Case $2.0 20.5% $1.8 18

  36. Slide 36: Project Timeline – Key Milestones

    Project Timeline – Key Milestones EXECUTION PLAN • Construction start at Côté in Q3 2020 with preparatory work over summer 2020 • Fish salvage, construction camp preparation and road access development • Activities ramp-up into Q4 2020 TMF Phase 1 Complete TIMELINE Construction Process Approval Majo

  37. Slide 37: Ground-breaking & Site Preparation

    Ground-breaking & Site Preparation CHESTER CAMP – 264 MAN CAMP GROUND-BREAKING CEREMONY TREE CLEARING – 456 HECTARES COMPLETED FISH RELOCATION IN TMF AREA 37

  38. Slide 38: Development and Exploration Projects

    Development and Exploration Projects 38

  39. Slide 39: Exploration Potential at Côté

    Exploration Potential at Côté GOSSELIN, YOUNG-SHANNON 1.5 KM NORTHEAST OF CÔTÉ Gosselin Drill Hole Highlights1 • GOS19-17: 342.5 metres grading 0.98 g/t Au • includes: 225.0 metres grading 1.34 g/t Au • GOS19-24: 412.0 metres grading 1.28 g/t Au • includes: 221.4 metres grading 1.47 g/t Au CONCEPTUA

  40. Slide 40: Boto Gold – High Margin Investment in Prospective District

    Boto Gold – High Margin Investment in Prospective District OVERVIEW RESERVE AND RESOURCE1 OPTIMIZATION STUDY HIGHLIGHTS1 (100% Basis) (100% Basis) Location • Senegal, West Africa Contained Mine Capacity: Tonnes Grade Mining: open pit Ounces 38 Mtpa Ownership • 90% IAMGOLD / 10% Gov’t of Senegal (000

  41. Slide 41: Bambouk District: Boto – Karita – Diakha-Siribaya

    Bambouk District: Boto – Karita – Diakha-Siribaya BOTO GOLD PROJECT, SENEGAL Gold Price After-tax NPV6%1 After-tax IRR1 Yatela Deposit Operation (US$/oz) (US$M) (%) • Announced the receipt of the exploitation permit $2,000 $732 55% Sadiola for an initial period of 20 years $1,900 $652 50% • De-riski

  42. Slide 42: Monster Lake & Nelligan

    Monster Lake & Nelligan NELLIGAN (75% JV INTEREST) • 15 kilometres south of Monster Lake • Exercised option to increase undivided interest to 75% (from 51%), MONSTER LAKE (Au) following completion of NI 43-101 Technical Report • Completed initial resource estimate1, comprising approximately 97 milli

  43. Slide 43: Exploration Around the World

    Exploration Around the World IP Survey – Saramacca Suriname Drill Barge at Gosselin, Ontario RC Drilling – Diakha Mali Geological Field Visit Peru Visible Gold in core Rouyn Gold Project, Quebec

  44. Slide 44: IAMGOLD – Positioned for Profitable Growth

    IAMGOLD – Positioned for Profitable Growth Diversified Operating Compelling Value & I Portfolio II Production Growth Robust Pipeline Strong Strong Financial V of Projects ESG III practices Position Culture of IV Accountable Mining 44

  45. Slide 45: Appendix

    Appendix # IAMGOLD 45

  46. Slide 46: 2020 Production and Cost Guidance – revised

    2020 Production and Cost Guidance – revised REFLECTING COVID-19 IMPACTS ON PRODUCTION AND COSTS REVISED GUIDANCE1 PREVIOUS GUIDANCE2 Essakane (000s oz) 350 – 370 350 – 370 Rosebel (000s oz) 210 – 230 250 – 270 Westwood (000s oz) 85 – 100 85 – 100 Total attributable production (000s oz) 645 – 700 685

  47. Slide 47: 2020 Capex Outlook – revised

    2020 Capex Outlook – revised REVISED PREVIOUS GUIDANCE Non- Non- $millions Sustaining1 Sustaining2 Total3 Sustaining1 Sustaining2 Total3 Essakane $40 $65 $105 $40 $80 $120 Rosebel $50 $40 $90 $60 $55 $115 Westwood $25 $18 $43 $25 $15 $40 $115 $123 $238 $125 $150 $275 Côté Gold - $77 $77 - $45 $45 Bo

  48. Slide 48: 2021 Production and Capital Guidance under review

    2021 Production and Capital Guidance*under review HIGHER VOLUMES & GRADE AT ROSEBEL ♦ WESTWOOD RAMPS ♦ ESSAKANE PUSHBACKS OPEN UP ORE 2021 Guidance1 Essakane (000s oz) 355 – 385 Rosebel (000s oz) 305 – 335 Westwood (000s oz) 100 – 120 Total attributable production (000s oz) 760 – 840 Capital Expendi

  49. Slide 49: Reducing Input Exposure Through Hedging

    Reducing Input Exposure Through Hedging 2020 2021 2022 2023 Foreign Currency1 Canadian dollar contracts (millions of C$) 135 252 210 120 Rate range2 ($/C$) 1.30 – 1.40 1.30 – 1.47 1.30 – 1.48 1.30 – 1.46 Hedge ratio 94% 81% 65% 36% Commodities1,3 Brent oil contracts (barrels)4 291 588 520 170 Contra

  50. Slide 50: Reserves & Resources (Year-over-Year)

    Reserves & Resources (Year-over-Year) ATTRIBUTABLE CONTAINED GOLD (000S OZ) As at December 31st, 2019 2019 Change 2018 Proven and Probable Mineral Reserves1 16,706 (6%) 17,864 Measured and Indicated Mineral Resources2,3 27,164 (2%) 27,850 Inferred Resources 11,965 38% 8,668 • Mineral reserves have b

  51. Slide 51: Gold Mineral Reserves

    Gold Mineral Reserves 100% BASIS RESERVES Proven Probable Contained Contained Tonnes Grade Tonnes Grade As at December 31, 2019 Ounces Ounces (000s) (g/t) (000s) (g/t) (000s) (000s) Rosebel1 29,522 0.6 574 92,356 1.0 2,947 Saramacca1 111 0.5 2 26,090 1.8 1,531 Essakane1 — — — 124,713 1.0 3,805 Westw

  52. Slide 52: Gold Mineral Reserves

    Gold Mineral Reserves ATTRIBUTABLE RESERVES Proven Probable Contained Contained Tonnes Grade Tonnes Grade As at December 31, 2019 Ounces Ounces (000s) (g/t) (000s) (g/t) (000s) (000s) Rosebel (95%)1 28,046 0.6 545 87,738 1.0 2,800 Saramacca (66.5%)1 74 0.5 1 17,350 1.8 1,018 Essakane (90%)1 — — — 11

  53. Slide 53: Gold Mineral Resources

    Gold Mineral Resources1,2 (Measured and indicated resources are inclusive of proven and probable reserves) 100% BASIS RESOURCES Measured Indicated Inferred Contained Contained Contained As at December 31, 2019 Tonnes Grade Tonnes Grade Tonnes Grade Ounces Ounces Ounces (000s) (g/t) (000s) (g/t) (000

  54. Slide 54: Gold Mineral Resources

    Gold Mineral Resources1,2 (Measured and indicated resources are inclusive of proven and probable reserves) ATTRIBUTABLE RESOURCES Measured Indicated Inferred Contained Contained Contained As at December 31, 2019 Tonnes Grade Tonnes Grade Tonnes Grade Ounces Ounces Ounces (000s) (g/t) (000s) (g/t) (0

  55. Slide 55: Investor Relations Contacts

    Indi Gopinathan, VP, Investor Relations & Corporate Communications 416-388-6883 Philip Rabenok, Senior Analyst, Investor Relations 647-967-9942