Image Resources Nl · ASX:IMA

Image Resources Nl — Shareholder Meeting (May 2019)

25 slides from Image Resources Nl's shareholder meeting presentation, May 1, 2019

  1. Slide 1: Boonanarring Mineral Sands Project - Annual General Meeting

    1 Boonanarring Mineral Sands Project 100%-owned; high-grade; zircon-rich 80km north of Perth in Western Australia On-track for positive cashflow end 1st QTR 2019 Annual General Meeting of Shareholders 1 May 2019 West Perth, WA Patrick Mutz Managing Directror Image Resources NL ASX: IMA

  2. Slide 2: Disclaimer and Forward-Looking Statements

    Disclaimer and Forward-Looking Statements 2 This presentation/document has been prepared by the management of Image Resources NL ("Image”, “IMA“, or “the Company”). The information presented includes an indicative outlook of the business activities of Image for the calendar year (CY) 2019 and is pro

  3. Slide 3: Investor Snapshot

    Investor Snapshot 3 Company transitioning to profitable miner and realisation of full valuation  Project construction and commissioning completed ‘on-schedule’ and ‘on-budget’  Production commenced 1 Dec 2018  Ramp-up to full production in 2nd month of operations  Completed first full quarter of

  4. Slide 4: Investor Snapshot

    Investor Snapshot 4 Company transitioning to profitable miner at a time of supply shortage of zircon  Zircon grade in ore 129% of budget  Zircon = 84% of revenue Rough zircon grains  Revenue $24.8 million  Net Profit After Tax $0.94M vs budgeted loss of $4.5M  Share price $0.201  Market capita

  5. Slide 5: Products and Applications

    Products and Applications 5 Key products are zircon and titanium dioxide  Zircon sand is processed into zirconium compounds, intermediate products and zirconium metal for a variety of applications;  Ceramics (tiles); 55% demand  Foundry Sands (castings); 14%  Refractories (furnace linings); 10%

  6. Slide 6: Products and Applications

    Products and Applications 6 Key products are zircon and titanium dioxide  Titanium dioxide (TiO2) from rutile and ilmenite is processed into titanium based products and titanium metal for a variety of applications;  Ultra-white pigments (paint, paper, plastic); ~90% demand  Welding rods (flux coa

  7. Slide 7: Project Location

    Project Looking Forward LocationStatement 7  LOCATION  North Perth Basin in Western Australia  80 km north of Perth CBD  Proven mineral sands address  Including majors Iluka and Tronox  Infrastructure rich  paved roads, power, gas pipeline water, telecommunications etc.  Local communities an

  8. Slide 8: Project Types and Locations

    Project Types and Locations 8  1,000 km2 tenements portfolio Atlas Ore Reserves  100% focus on mineral sands Probable: 9.5Mt @ 8.1% HM  Strandline projects (dry mining)  Dredge mining prospects Boonanarring Ore Reserves Multiple opportunities for a second Proved: 9.3 Mt @ 8.6% HM Probable: 10.5M

  9. Slide 9: Ore Reserves

    Ore Reserves Forward Looking Statement 9  QUALITY ORE RESERVES  JORC Code (2012) Compliant  High HM, VHM and very high zircon at Boonanarring High Grade Ore Reserves - Strand Deposits; in accordance with the JORC Code (2012) Project/Deposit Category Volume Tonnes % HM % Slimes HM Tonnes VHM Ilmen

  10. Slide 10: Products and Prices

    Products and Prices 10 Notes: VHM assemblages and commodity prices are estimates based on Boonanarring project heavy mineral concentrate product.

  11. Slide 11: Target Production Rate

    Target Production Forward Rate Looking Statement 11 Base Assumptions  Start mining at Boonanarring  Dry, open-cut mining  Production rate - 500 dry tonnes per hour • 3.7M dry tonnes per year  Conventional gravity separation using spirals  Product: Heavy Mineral Concentrate (HMC) • Production ra

  12. Slide 12: Boonanarring – Production Statistics

    Boonanarring – Production Statistics 12 Average annual production at Boonanarring (5 yrs)  240k tonnes HMC; containing; • 60kt zircon (70kt/year in 2019-20) • 130kt ilmenite • 6kt rutile • 4kt leucoxene  5.5 years mine life with potential to add 3-4 years additional ore reserves

  13. Slide 13: Boonanarring – 2019 Guidance

    Boonanarring – 2019 Guidance 13 2019 CY Production and Profitability Guidance1,2 2019 Production Guidance 2020 Forecast Ore processed (million tonnes) 3.4-3.7 3.6-3.8 HMC3 produced (000 tonnes) 220-240 280-300 HMC sold (000 tonnes) 220-240 280-300 Costs (AU$) Project operating costs4 (million) $85-9

  14. Slide 14: Boonanarring – HM Ore Grade

    Boonanarring – HM Ore Grade 14

  15. Slide 15: Boonanarring – Zircon Grade in Ore HM

    Boonanarring – Zircon Grade in Ore HM 15

  16. Slide 16: Boonanarring – HMC Production

    Boonanarring – HMC Production 16

  17. Slide 17: Zircon Prices

    Zircon Prices Forward Looking– Statement Actual and Forecast 17 Current price for Tronox premium grade zircon

  18. Slide 18: Upside Potential

    UpsideLooking Forward Potential Statement 18 Upside potential at and near Boonanarring  Confirmed potential to extend mine life with high grade mineralisation (ASX announcement 13 March & 26 June 2017);  Assuming mineralisation in extension area is identical to known Ore Reserves in all aspects an

  19. Slide 19: Boonanarring High-Grade Extension

    Boonanarring High-Grade Extension 19 ASX - 13 March & 26 June 2017 New Drilling Results (Feb 2017)  Confirm 5.6km northern extension of Boonanarring mineralisation  Outstanding high grade intersections:  8m @ 23.8% HM in IX00245  8m @ 21.1% HM in IX00244 and  8m @ 16.3% HM in IX00250 Importantl

  20. Slide 20: Projects Pyramid – Strand Deposits

    Projects PyramidStatement Forward Looking – Strand Deposits 20 Mineral Resources – Accessible by Dry Open-Cut Mining Projects ranked by combined Zircon (Zr) plus Rutile (Ru) BFS assumes mining at Boonanarring Tonnes-grades are for Mineral Resources; Boonanarring and Atlas per JORC Code (2012); follo

  21. Slide 21: Projects Pyramid – Dredge Prospects

    Projects PyramidStatement Forward Looking – Dredge Prospects 21 Mineral Resources – Accessible by Dredge Mining Projects ranked by HM Grade Positive attributes • 90+%VHM; • <5% slimes; Tonnes-grades are for historic Mineral Bidaminna • 25-67% Leucoxene; Resources per JORC Code (2004). 45Mt; 3.0%HM;

  22. Slide 22: Potential Royalty from Tronox

    Potential Royalty from Tronox 22 Royalty agreement in place as of 2014  Small cash payment (already received)  Sliding-scale royalty on production Avg. HM Grade Royalty 2.5% 1.25% 3.0% 2.50% 3.5% 3.75% 4.0% 5.00%  Indefinite production schedule  Potential for future arrangements with Tronox or o

  23. Slide 23: Image Corporate Snapshot

    Image Corporate Snapshot 23 Diverse and experienced Board and Management ASX Code: IMA Board of Directors Share Price: A$0.20* Bob Besley – Independent Chairman 12-Month Price Range: A$0.10– 0.21 Patrick Mutz – Managing Director Shares on Issue: 964m Chaodian Chen - Non-Executive Director Market Cap

  24. Slide 24: Use of Solar Energy

    Use of Solar Energy 24 Heads of Agreement with Sunrise Energy Group Pty Ltd to provide 3-4 MWAC solar farm to be:  Constructed and operated by Sunrise Energy;  Located on Image owned land adjacent to Boonanarring mine site; and  Providing 25% of total electricity requirements for mine and process

  25. Slide 25: Contact

    For further information Contact 25 Patrick Mutz Managing Director Image Resources NL info@imageres.com.au Office: +61 8 9485 2410 Ground Floor, 23 Ventnor Avenue West Perth, WA 6005 PO Box 469, West Perth, WA 6872 www.imageres.com.au