China Wind Power International
China Wind Power International — Investor Presentation (September 2010)
24 slides from China Wind Power International's investor presentation, September 2010
Slide 1: Investor Presentation September 2010
Investor InvestorPresentation Presentation September September2010 2010 TSX-V: TSX-V:CNW CNW
Slide 2: Forward-looking statements
Forward-looking statements This presentation contains “forward-looking statements” within the meaning of applicable securities legislation. Forward-looking statements may include financial and other projections, as well as statements regarding future plans, objectives or economic performance, or the
Slide 3: About China Wind Power International Corp.
About China Wind Power International Corp. China Wind is uniquely positioned to capitalize on the growing demand for wind energy in China 3 •3
Slide 4: Demand, Exclusivity, Guaranteed, Profitable
A tremendous opportunity for following four main reasons: Demand China Exclusivity Du Mon County Guaranteed Power Purchase Agreement Profitable 12-14% IRR, and higher for future projects 4 •4
Slide 5: China Overview
China Overview • Rapid industrialization • Looming energy shortage • Facing one of the world’s biggest environmental crisis 5 Source: IEA
Slide 6: China's commitment to wind power
China’s commitment to wind power 2008 2009 2010 2020 12.0 GW 25.8 GW 40 GW 100 GW China: 4th 2009 2nd today 1st tomorrow 6
Slide 7: Guaranteed demand for China Wind
We make it, they take it Guaranteed demand • National Renewable Energy Law, effective January 2006 • Grid is obligated to purchase all output! for China Wind • Heilongjiang Provincial Power Grid must buy our electricity 7
Slide 8: Our current focus: Heilongjiang Province
Our current focus: Heilongjiang Province Beijing Exclusive rights to Shanghai Wind Power Generation Du Mon County, Heilongjiang Heilonjoang Province Population: ~38 million Annual electricity use by 2010*: 74 million MWh 8 * forecast 8
Slide 9: Favourable location
Favourable location Power Grid <2km Beijing Shanghai Wind Speed 70m: 6.9-7.5 m/s Well Located • Flat, solid ground • Easy access with roads and highways 9
Slide 10: Our portfolio
Our portfolio 546 MW over 5 development phases: Beijing Shanghai Included in power grid master plan Longer-term potential for building out 1,150 MW 10
Slide 11: China Wind — Phase 1
China Wind — Phase 1 Phase 1: 49 MW Phase 2: 49.5 MW Phases 3-5: 448.5 MW Status Turbines Financing Completed Commenced 26% 34 turbines equity commercial producing Production 74% power Dec. 2009 debt 360M RMB (US$53M) of debt. Interest rate: 5.94% 67 GWh generated by end of June 2010. 11
Slide 12: China Wind — Phase 2
China Wind — Phase 2 Phase 1: 49 MW Phase 2: 49.5 MW Phases 3-5: 448.5 MW Status Turbines Financing Completed 15 35.15% Construction installed, equity half way 20 on 65.85% completed order bank* 330 million RMB bank loan has been approved at a variable Interest rate. 12
Slide 13: Turbine Overview: Phase 1 and Phase 2
Turbine Overview: Phase 1 and 2 DW1.0/56 HFDY1500/77 DT-1500 Two-Bladed Directly Driven Doubly Fed 4 30 Phase 1 Phase 2 6 (Installed) 10 19 (10 installed) 56% of all globally installed wind power equipment is manufactured in China (2007) 13
Slide 14: Phase 2: project timeline
Phase 2: project timeline Q1/09 Q3/09 Q4/09 Q3/10 Q4/10 Construction Equity Turbines Debt Construction commenced financing installation financing completed commenced. approved All foundations completed 14
Slide 15: China Wind — Phases 3 to 5
China Wind — Phases 3 to 5 Phase 1: 49 MW Phase 2: 49.5 MW Phases 3-5: 448.5 MW Status Turbines Financing (targeted) 30% Phase 3 Phase 4 & 5 equity close to get feasibility 299 turbines final studies planned 70% approval underway debt Phase 3 projects (198MW) will be financed using EPC Contract. 15
Slide 16: Phases 3 to 5: project timelines
Phases 3 to 5: project timelines Phase 3 Phase 4 Phase 5 (Sino-Denmark) ~100MW ~150MW 198 MW Q4/11 Q4/12 Q3/13 Construction Construction Construction completed completed completed Q1/11 Q1/12 Q3/12 Construction Construction Construction commences commences commences Construction phase ~ 12 months 16
Slide 17: Financial Results for Phase I
Financial Results for Phase I Revenue Adjusted EBITDA (millions) (millions) $1.2 $1.2 $0.8 $0.6 $0.5 $0.5 Q3/FY10 Q4/FY10 Q1/FY11 Q3/FY10 Q4/FY10 Q1/FY11 • Phase I Commercial production begun in Q4 FY2010. • Adjusted EBITDA excludes stock-based compensation 17
Slide 18: Business model: costs and revenues
Business model: costs and revenues* Total ~49M Project Cost Total Revenue for 49MW (including installation) Phase 1 & 2 * Phase 3 ** Electricity Production • Production: 110,743 MWh/yr Turbines/towers: US $53.6M US $46.8M • Power Price: US$89/MWh Construction: US $13.1M US $10.5M • Revenue: US$8.5M
Slide 19: Targeted project economics for Phase I & II
Targeted project economics for Phase I & II * (20 year average) Installed capacity 49MW Capacity factor 26.31% Revenue: wind power US $8.5M Revenue: carbon credits US $1.8M Total revenue US $10.4M EBITDA US $8.3M Total profit after tax US $3.2M Annual cash flow to equity US $3.9M Capital cost/MW Lev
Slide 20: Recent Milestones
Recent Milestones • Completed construction of Phase 1 • Commenced commercial production • Generated more than 67 GWh to date • Total sales of $1.2 million for Q1 FY2011 • EBITDA* of $598,000 for Q1 FY2011 • Approval of Grid connection for Phase 3. *Excludes stock compensation charges 20
Slide 21: Management and Board of Directors
Management and Board of Directors Jun Liu Chief Executive Officer and Director • 20 years of experience including executive positions with subsidiary companies of Daqing Petroleum Administration Bureau, China National Petroleum Corp. Wendell Zhang Chief Financial Officer • 9 years public accounting
Slide 22: Management and Board of Directors
Management and Board of Directors Honliang Xu Independent Director • Chairman of the Board of China Fulin Wind Power Development Corp. Linda Dundas Independent director • Risk Management and Financial Sector Regulation Expert with Royal Bank of Canada。 Joshua Gerstein Independent Director • Merchant
Slide 23: Demand, Exclusivity, Guaranteed, Profitable
Demand China Exclusivity Du Mon County Guaranteed Power Purchase Agreement Profitable 12-14% IRR 23
Slide 24: Walter Huang, Senior Vice President