Grange Resources Limited · ASX:GRR

Grange Resources — Investor Presentation (December 2017)

27 slides from Grange Resources's investor presentation, December 2017

  1. Slide 1: Australia's most experienced magnetite producer

    Slide 1: Australia's most experienced magnetite producer

    Australia’s most experienced magnetite producer Investor Presentation December 2017

  2. Slide 2: Company Highlights

    Slide 2: Company Highlights

    Company Highlights ✓ Most EXPERIENCED magnetite producer Over 49 years of operational experience at Savage River ✓ STRONG Safety Culture Achieved over 200 days LTI free after the end of Q3 2017 ✓ Shipped over ~1.2m tonnes of Iron Ore Products Over 1.2 million tonnes of pellets and chips sold through

  3. Slide 3: Iron units in = Iron units out

    Slide 3: Iron units in = Iron units out

    Iron units in = Iron units out Blast Furnace November 2017 Slide 3

  4. Slide 4: Sinter, Lump and Pellet Mix over time

    Slide 4: Sinter, Lump and Pellet Mix over time

    Sinter, Lump and Pellet Mix over time November 2017 Slide 4

  5. Slide 5: Pellet Premium

    Slide 5: Pellet Premium

    Pellet Premium November 2017 Slide 5

  6. Slide 6: Company Overview

    Slide 6: Company Overview

    Company Overview November 2017 Slide 6

  7. Slide 7: Company Assets

    Slide 7: Company Assets

    Company Assets Australia’s Most Experienced Magnetite Producer Savage River (100%) Southdown Project (70%) Focusing on the Searching for an fundamentals equity partner Quality assets in Tasmania and Western Australia. November 2017 Slide 7

  8. Slide 8: Sep 2017 Financial Position - Consolidated

    Slide 8: Sep 2017 Financial Position - Consolidated

    Sep 2017 Financial Position - Consolidated Sep 2017 Dec 2016 Difference Indicator AUD’000 AUD’000 Variance% Comments AUD’000 (Unaudited) (Audited) Cash↓, shipping receivables↑, Current Assets 217,598 232,806 (15,208) (6%) Inventories↑ PP&E ↑ Mine Properties & Dev↑ Non-current Assets 228,928 196,150

  9. Slide 9: Company Snapshot

    Slide 9: Company Snapshot

    Company Snapshot Capital Structure (A$) Share Price and Volume Ordinary Shares on issue 30 Sep 2017 1,157m Share Price 30 Sep 2017 $0.130 Market Capitalization 30 Sep 2017 $150m Cash and Term Deposits 30 Sep 2017 $120m Loan 30 Sep 2017 $4m Ownership Structure as at 30 Sep 2017 Jiangsu Shagang 43% Pa

  10. Slide 10: Iron Ore Quality

    Slide 10: Iron Ore Quality

    Iron Ore Higher Developing Iron Ore Pellet Fluxed Pellet ~65% Fe Magnetite Concentrate ~65%-67% Fe QUALITY Direct Shipping Lump ~63% Fe Direct Shipping Fines Lower ~57% - ~ 61% Fe Lower Price Higher November 2017 Slide 10

  11. Slide 11: Magnetite

    Slide 11: Magnetite

    Magnetite Magnetite is a naturally occurring mineral, commonly refined into an iron ore concentrate and used for steel production. Smelting magnetite to iron involves agglomeration or ‘clumping together’ of the magnetite concentrate, and thermal treatment to produce spherical shaped balls – pellets.

  12. Slide 12: The Benefit of Pellets

    Slide 12: The Benefit of Pellets

    The Benefit of Pellets Pellets are often preferred over iron ore fines, sinter and lump due to their favourable physical and chemical properties supporting increased Blast Furnace productivity and efficiency. Pellets are an enriched form of iron ore and provide significant benefits for the steel mak

  13. Slide 13: Tasmanian Operations Performance & Focus

    Slide 13: Tasmanian Operations Performance & Focus

    Tasmanian Operations Performance & Focus November 2017 Slide 13

  14. Slide 14: East Wall Failure – January 2012

    Slide 14: East Wall Failure – January 2012

    East Wall Failure – January 2012 November 2017 Slide 14

  15. Slide 15: Jan - Sep 2017 Performance – Indicators

    Slide 15: Jan - Sep 2017 Performance – Indicators

    Jan - Sep 2017 Performance – Indicators Indicator Unit Sep 2017 Sep 2016 Difference Variance% Comments Tonnes Mining in South Deposit completed and Concentrate 1,263 1,226 37 3% recommenced mining in North Pit in 2017 ‘000 Tonnes Pellet production line balanced with Pellet 1,221 1,160 61 5% concentr

  16. Slide 16: 2017 Quarter 3 Performance – Indicators

    Slide 16: 2017 Quarter 3 Performance – Indicators

    2017 Quarter 3 Performance – Indicators Variance Indicator Unit Q3 2017 Actual Q2 2017 Actual Difference Comments % ↑ Gained access to main ore zone in North Concentrate Tonnes ‘000 584 181 403 223% Pit ↑ Pellet production line balanced with Pellet Tonnes ‘000 550 184 366 199& concentrate production

  17. Slide 17: Highlights for 2017 — Tasmania

    Slide 17: Highlights for 2017 — Tasmania

    Highlights for 2017 — Tasmania ✓ Restored ore production from Main Ore Zone Mining resumed on the east wall with redesigns post the incident in March. While we continue to remediate upper parts of the east wall, delivery from the main ore zone is progressing well. ✓ Second Autogenous Mill Shell repl

  18. Slide 18: LOM Strategies — Leveraging Resources

    Slide 18: LOM Strategies — Leveraging Resources

    LOM Strategies — Leveraging Resources North Pit South Deposit ▪ High quality, long life resources ▪ ~19MT @ 42%DTR ▪ ~128MT @ 58%DTR ▪ Supporting LOM tailings infrastructure ▪ Supporting long life operations construction Centre Pit Long Plains ▪ Modelling in progress to further develop ore ▪ Develop

  19. Slide 19: LOM Strategies— Optimising Mining Operations

    Slide 19: LOM Strategies— Optimising Mining Operations

    LOM Strategies— Optimising Mining Operations North Pit Production Stripping ▪ Ore supply for 2017 North Pit Mine Development ▪ West wall cut-back continues South Deposit – completed for current design ▪ Ore supply for early 2017 ▪ Provided ore and material for construction of South Deposit Tailings

  20. Slide 20: Southdown Project Achievements & Strategies

    Slide 20: Southdown Project Achievements & Strategies

    Southdown Project Achievements & Strategies November 2017 Slide 20

  21. Slide 21: 2017 Project Overview – Southdown

    Slide 21: 2017 Project Overview – Southdown

    2017 Project Overview – Southdown ✓ The Project continues on reduced expenditure while Grange seeks an equity partner for a strategic share in the Project ✓ Existing tenure and approvals have been maintained . ✓ Project security has been enhanced by continuing to build land tenure and access, includ

  22. Slide 22: Southdown Project Strategies 2017

    Slide 22: Southdown Project Strategies 2017

    Southdown Project Strategies 2017 We continue the approaches adopted in 2016 into 2017, as we: ▪ Formulate valid alternate development model and seek to secure equity ▪ Seek partners for a strategic share of the Company’s interest in the project November 2017 Slide 22

  23. Slide 23: Grange — LOM Strategies Recapped

    Slide 23: Grange — LOM Strategies Recapped

    Grange — LOM Strategies Recapped ▪ Improve productivity and sustain access to high grade ore ▪ Provide high quality ore from North Pit ▪ Continue investment in mine development - progress next phase of North Pit development on the west wall ▪ Continue to invest in process infrastructure ▪ Completed

  24. Slide 24: Focusing on the fundamentals

    Slide 24: Focusing on the fundamentals

    Focusing on the fundamentals ▪ Our fundamentals remain firm ▪ Experienced magnetite producer with a long life project close to the Asian market ▪ Producer of a high quality iron ore product (65%+ Fe) that receives a premium price ▪ Strong balance sheet ▪ Stable work force with minimal turnover ▪ Our

  25. Slide 25: Ongoing Strategies

    Slide 25: Ongoing Strategies

    Ongoing Strategies We continue to: ▪ Develop and optimise LOM ▪ Develop Long Plain resources and project ▪ Seek feasible investments within the strategy undertaken by the Board ▪ Diversify the markets outside of China ▪ Improve communications/relations with all shareholders November 2017 Slide 25

  26. Slide 26: Primary Contact

    Slide 26: Primary Contact

    Primary Contact Primary Contact: Dr Michelle Li Chairman +61 488700538 Michelle.li@grangeresources.com.au Notes: - A lower cut-off grade of 15% DTR was used in the calculation of both the Mineral Resources and Ore Reserves - For details of Resources and Reserves, refer ASX announcement 30-Mar-2017 N

  27. Slide 27: Disclaimer

    Slide 27: Disclaimer

    Disclaimer The material in this presentation (“material”) is not and does not constitute an offer, invitation or recommendation to subscribe for, or purchase, any security in Grange Resources Limited (“GRR”) nor does it form the basis of any contract or commitment. GRR makes no representation or war