Hindalco Industries Limited · NSE:HINDALCO

Hindalco Industries — Q3 FY10 Earnings Presentation

33 slides from Hindalco Industries's earnings presentation, Jan 25, 2010

  1. Slide 1: Hindalco Industries Limited Q3 FY10 Investors Presentation

    Hindalco Industries Limited Q3 FY10 Investors Presentation 25th January’10 1

  2. Slide 2: Highlights

    Highlights ™Excellent Production Performance during Q3, FY10 Aluminium at 142 Kt Best Ever Alumina at 340 Kt Wire rod at 23 Kt ™ Highest-ever 9-month production of alumina, aluminium and copper cathodes ™YOY ™ Aluminium production up 5% ™ FRP production up 34% ™ Copper production up 22% ™Successfull

  3. Slide 3: Stock performance post QIP

    Stock performance post QIP Key 350 investors 340 Hindalco 330 320 LME Aluminum 310 LME Copper 300 Out performs 290 280 LME 270 260 250 240 230 220 210 200 190 180 170 160 150 5% 3% 140 130 120 110 Long only 100 8-Nov -09 21-Nov -09 5-J un-09 18-J un-09 1-J ul-09 14-J ul-09 27-J ul-09 12-J an-10 1-A

  4. Slide 4: Backdrop: World Economy is gradually recovering

    Backdrop: World Economy is gradually recovering GDP growth- Major economies India growth US, Euro Area Growth (%, qoq, SAAR) China Growth (%, yoy) (%, yoy) Growth in India and China is getting close to pre-crisis levels, while that of OECD countries is just turning positive 4

  5. Slide 5: Business Conditions: Aluminium in recovery mode

    Business Conditions: Aluminium in recovery mode Aluminium Exchange stock plateauing out, though still at high levels. tons $/t 2,600 4,500,000 2,400 LME CSP 2,200 3,500,000 US$/Mt 2,000 1,800 2,500,000 1,600 1,400 1,500,000 1,200 Exchange Stock= Comex+LME+Shanghai 1,000 500,000 800 0 8 09 -0 9 l -0

  6. Slide 6: Business Conditions: Drivers

    Business Conditions: Drivers Q3 FY 09 Q3 FY 10 Impact LME Average Al ($/ton) 1,821 2,002 LME Average Cu ($/ton) 3,905 6,648 Re/USD 48.76 46.64 Tc/Rc (Jap benchmark) 45/4.5 75/7.5 $/C In Aluminium, LME gain partially negated by adverse currency movement Benchmark Tc/Rc were higher but spot Tc/Rc now

  7. Slide 7: Hindalco Strategy: Dealing with the downturn

    Hindalco Strategy: Dealing with the downturn Challenges Actions Sweating of Assets, Focus Cost Push on Key raw materials Low LME Better product & geographical mix Cash Generation Working Capital reduction Volatility Robust Risk management practice &Early adoption of AS 30 Hindalco emerged relatively

  8. Slide 8: Hindalco Financials - YOY

    Hindalco Financials -YOY Q3 Q3 Change 9M 9M Change Rs Crores FY09 FY10 (%) FY09 FY10 (%) Net Sales 4,117 5,315 29% 14,448 14,132 -2% EBIDTA 779 748 -4% 2,722 2,115 -22% PBT 675 557 -18% 2,532 1,590 -37% PAT 545 427 -22% 1,962 1,252 -36% EPS 3.37 2.41 -28% 13.61 7.26 -47% *On early adoption of AS-30,

  9. Slide 9: Hindalco Financials – Sequential

    Hindalco Financials – Sequential Rs Crores Q2 FY10 Q3 FY10 Change (%) Net Sales 4,917 5,315 8% EBIDTA 609 748 23% PBT 434 557 28% PAT 345 427 24% EPS 2.02 2.41 19% 9

  10. Slide 10: Aluminium Business Performance

    Aluminium Business Performance 10

  11. Slide 11: Brownfield expansion and sweating of assets led to improved production volume

    Brownfield expansion and sweating of assets led to improved production volume Kt Kt FRP Prodn Kt 60.0 53.2 55.0 49.3 50.0 45.8 41.0 40.0 30.0 20.0 10.0 0.0 Q3 FY09 Q4 FY09 Q1 FY10 Q2 FY10 Q3 FY10 11

  12. Slide 12: Aluminium: Sequential Performance

    Aluminium: Sequential Performance Rs Crores Q2 FY10 Q3 FY10 Change Net Sales & 1650 1885 14% Operating Revenue EBIT 259 438 69% 12

  13. Slide 13: Aluminium: Y-o-Y Performance at a glance

    Aluminium: Y-o-Y Performance at a glance Rs Crores Q3 FY09 Q3 FY10 Change Net Sales & 1,980 1,885 -5% Operating Revenue EBIT 530 438 -17% 13

  14. Slide 14: Copper Business Performance

    Copper Business Performance 14 14

  15. Slide 15: Continuous improvement in operational performance

    Continuous improvement in operational performance Anode (Mt) 22% •Improved efficiency leading to lower conversion costs & •Value extraction from By-products •Gypsum Sale •Slag beneficiation Cathode (Mt) Helped in Offsetting the 89,152 89000 negative 85000 81000 22% impact of sharp fall in 77000 Bypr

  16. Slide 16: Copper: Sequential Performance at a glance

    Copper: Sequential Performance at a glance Rs Crores Q2 FY10 Q3 FY10 Change Net Sales & 3269 3432 5% Operating Revenue EBIT 217 159 -27 % 16 16

  17. Slide 17: Copper: Y-o-Y Performance at a glance

    Copper: Y-o-Y Performance at a glance Rs Crores Q3 FY09 Q3 FY10 Change Net Sales & 2,139 3,432 60 % Operating Revenue EBIT 116 159 38 % 17 17

  18. Slide 18: Projects

    Projects 18

  19. Slide 19: Hirakud Smelter and Power Plant Expansion

    Hirakud Smelter and Power Plant Expansion Smelter Expansion Capacity increase from 155 to 213 KTPA through two projects 1) 28 Pots – 80 KA 2) 80 Pots – 235 kA Power Plant Expansion Capacity to increase to 467.5 MW by Addition of 100 MW. 80 Pots –Status Update First Metal Oct’ 2011 Technology GAMI De

  20. Slide 20: Greenfield Project – Mahan Aluminium

    Greenfield Project – Mahan Aluminium First Metal from Smelter- July ’11 20

  21. Slide 21: Mahan Smelter- Pot line and area grading photos

    Mahan Smelter- Pot line and area grading photos 21

  22. Slide 22: Greenfield Project – Utkal Alumina

    Greenfield Project – Utkal Alumina Engineering Basic Engg-100 % Complete, Detailed Engg- 86% Completed, not on critical path Statutory Clearances Obtained Commitment & Spent Rs.3877 Crs Committed & Rs 1423 Cr Spent. All major order placed. Site Progress: Major Contractors have fully mobilized at sit

  23. Slide 23: Greenfield Project – Utkal Alumina

    Greenfield Project – Utkal Alumina Digestion area – civil foundation under progress Pipe rack‐ PR 022, 48 columns & beams erection completed OH Tank Foundations under progress Evaporation Package – Foundations ready for structure PPTs – 5 tanks shell erection in various stages (TK-202, 23 columns er

  24. Slide 24: Greenfield Project – Aditya Smelter

    Greenfield Project – Aditya Smelter Engineering Basic Engg-nearing completion, Detailed Engg- 43% Complete. Statutory approvals Major approval received. Stage I clearance for MOEF received. Commitment & Spent Rs.4349 Cr. Committed and Rs 1020 Cr. spent Site Progress Project Office at Lapanga – Samba

  25. Slide 25: Jharkhand Smelter

    Jharkhand Smelter Land Total land requirement of ~4000 Acres identified. Water Water drawl clearance received for 55 MCM. Route Survey and Design of water drawl scheme completed and report submitted. Environmental TOR presentation done at MoEF. clearance Railway Report for Conceptual Approval of Rai

  26. Slide 26: Aditya Refinery

    Aditya Refinery Land Land requirement is ~ 1881 Acres. Entire Private land is registered in the name of company, Process for government land in process. Water Agreement signed with Government of Orissa for drawl of water from Pathgarha river. Environmental Clearance received, subject to Forest diver

  27. Slide 27: Brownfield Project – Can Body Stock at Hirakud

    Brownfield Project – Can Body Stock at Hirakud Project Cost Approved for 850Cr. Dismantling at The work has started from 1st week of January. Duration – 6 Rogerstone Months. Shipping will start from 3rd week of February. Upgradation of Hot The order has been placed Mill New Cold Mill order Technical

  28. Slide 28: Summing Up

    Summing Up ™ All-out cost focus helped us during the downturn ™ With improving economic prospects, outlook seems promising ™ Energy prices and concentrate sourcing continue to be the key challenges ™ Positive about coming out of the downturn with our targeted growth trajectory unchanged 28

  29. Slide 29: Appendix

    Appendix 29

  30. Slide 30: Aluminium Production

    Aluminium Production Production (MT) Q3 FY10 Q3 FY09 9M FY10 9M FY09 Alumina 339,899 319,074 963,522 918,959 Metal 142,048 135,073 417,382 390,274 Wire Rod 23,363 18,657 68,726 54,703 Flat Rolled Products 55,030 40,968 157,484 137,474 Extrusion 10,531 7,555 29,158 28,780 30

  31. Slide 31: Aluminium Sales Revenue

    Aluminium Sales Revenue Q3 Q3 9M 9M Sales Units FY09 FY10 FY09 FY10 Chemicals Rs Crs 138 161 494 418 Primary metal Rs Crs 1,025 804 2,646 2,105 Flat Rolled Products & Rs Crs 621 712 2,139 1,913 Foil Extruded products Rs Crs 108 151 462 391 Others Rs Crs 88 57 302 129 31

  32. Slide 32: Copper Production Volumes

    Copper Production Volumes Production (MT) Q3 FY10 Q3 FY09 9M FY10 9M FY09 Copper Cathodes 89,152 72,877 258,626 210,851 CC Rods (Own) 32,969 33,189 93,671 91,249 32

  33. Slide 33: Copper Sales Revenue

    Copper Sales Revenue Sales Revenue Unit Q3 FY09 Q3 FY10 9M FY09 9M FY10 Copper Cathodes Rs Crs 729 1,706 3,385 4,318 CC Rods Rs Crs 1,016 1,114 3,351 3,222 Others Rs Crs 394 612 1,675 1,641 33

Hindalco Industries — Q3 FY10 Earnings Presentation on 6ix