Slide 1: June Quarter FY2026 Activities Presentation
June Quarter FY2026 Activities Presentation 30 July 2026 1 ASX: PDI | TSX: PDI | predictivediscovery.com
Slide 2: Our Purpose
Our Purpose Creating long-term value through responsible resource development Building Africa’s next Vision leading gold producer. Develop high quality gold assets Mission that deliver lasting value. Strategy Operate Execute Grow Diversify Deliver safe, reliable Build value accretive projects Unlock
Slide 3: PDI Overview
PDI Overview Building Africa’s next leading gold producer Two producing mines: 2026 guidance of 198-220koz Board and management with track record of Kiniero (Guinea) and Nampala (Mali) Targeted production by 2029 of >400kozpa1 developing and operating African gold mines Tier-1 development project: 9
Slide 4: Health and Safety
Health and Safety Empowering our workforce, partners, and communities to create a safe, inclusive and high performing culture 1.76 0.12 Total recordable injury frequency rate (TRIFR)1 Lost time injury frequency rate (LTIFR)2 1. Recordable injury numbers and Total Recordable Injury Frequency Rate inc
Slide 5: June Quarter – Key Highlights
June Quarter – Key Highlights1 Operational momentum continues: Kiniero delivers increased production and strengthens cash generation Production Sales Merger Complete 64koz 49koz Robex and PDI merger closed on 15th April and capital gains Gold poured Gold sales agreed4 Costs Cash and Bullion Diversif
Slide 6: June 2026 Quarter Production and 2026 Guidance
June 2026 Quarter Production and 2026 Guidance Production volume and AISC in line with plan, with Kiniero performing above nameplate capacity and delivering strong gold production Summary Operational and Financial Metrics1 Units Jun-26 Quarter Mar-26 Quarter Var % o Gold poured totalled 64,026oz Au,
Slide 7: June 2026 Quarter Cash Flow Bridge
June 2026 Quarter Cash Flow Bridge1 Strong cash flow generation supported by Kiniero ramp-up and high realised pricing (US$M) o Group cash balance increased to US$274M⁴, with total cash and bullion of US$364m at 30 June 2026. This was supported by strong cash 217 generation from Kiniero and Nampala
Slide 8: Kiniero Operation
Kiniero Operation Strong quarterly performance with throughput above nameplate capacity and improving recovery o Exceeding expectations: Kiniero continued to deliver strong operational execution across both mining and processing activities during the quarter. o Consistent and reliable performance: M
Slide 9: Kiniero Operations Update
Kiniero Operations Update Strong ramp-up driven by mining and processing performance exceeding plan Summary Operational Metrics o Strong operational performance: Kiniero delivered solid operational performance during the June 2026 quarter, achieving higher gold production and sales as the Units Jun-
Slide 10: Guinea Gold Refining Update
Guinea Gold Refining Update New gold export requirements following Government decree o Regulatory transition underway: The Government of Guinea issued a decree on 8 July 2026 requiring gold produced in Guinea to be refined domestically to a minimum 95.5% purity prior to export, following a 90-day tr
Slide 11: Merger Completion & Capital Gains Tax Settlement
Merger Completion & Capital Gains Tax Settlement Transformational combination creating a leading, diversified West African gold producer o Transformational combination completed: PDI-Robex merger completed on 15 April 2026, creating a larger West African gold producer and developer. o Enhanced portf
Slide 12: Nampala Operations Update
Nampala Operations Update Established operation delivering consistent output and steady cash generation Summary Operational Metrics Units Jun-26 Quarter Mar-26 Quarter Var % o Gold poured of 9,774oz Au, down 2%, reflecting planned mine sequencing and maintaining steady operational performance. Finan
Slide 13: Bankan Update
Bankan Update Positioning Bankan as PDI’s next growth platform o Advancing execution readiness: Process plant FEED completed, detailed design activities commenced in July 2026. o Building procurement momentum: Major contracts awarded for the 40MW power station, grinding circuit and TSF design, with
Slide 14: Awalé Resources Strategic Investment
Awalé Resources Strategic Investment Exposure to an emerging exploration and development company with significant upside potential, in mining-friendly Cote d’Ivoire o US$10M for an 11.8% strategic shareholding in Awalé Resources (TSXV: ARIC). o Emerging gold (and copper) exploration and development
Slide 15: Contacts
Contacts Investor Enquiries: Media Enquiries: Matthew Wilcox Nathan Ryan CEO and Managing Director NWR Communications T +61 8 9216 1000 T +61 420 582 887 E info@predictivediscovery.com E nathan.ryan@nwrcommunications.com.au 15
Slide 16: Appendix
Appendix 16
Slide 17: Forward Looking Statements, Important Notices and Disclaimers
Forward Looking Statements, Important Notices and Disclaimers Forward Looking Statements and Important Notice. This investor presentation is dated 29 July 2026 and has been prepared by Predictive Discovery Limited (ASX: PDI) (TSX: PDI) (“PDI” or the “Company”) based on information available at the t
Slide 18: Forward Looking Statements, Important Notices and Disclaimers
Forward Looking Statements, Important Notices and Disclaimers Not an Offer This Investor Presentation is not an offer, invitation, solicitation or other recommendation with respect to the subscription for, purchase or sale of any security, and neither this Investor Presentation nor anything in it sh
Slide 19: Reserves & Resources
Reserves & Resources Kiniero1,2 Nampala3,4 Tonnage Gold Grade Contained Tonnage Gold Grade Contained Deposit Weathering Type (Mt) (g/t Au) (Moz Au) (Mt) (g/t Au) (koz Au) Probable Probable Jean 4.2 1.53 0.20 Oxide 3.3 0.90 94.6 SGA 5.1 1.52 0.25 Transition 0.8 1.06 26.4 SGD 3.4 1.34 0.14 Total 4.0 0
Slide 20: Reserves & Resources Continued
Reserves & Resources Continued Bankan Reserves1,2 Bankan Resources1,3 Tonnage Gold Grade Contained Tonnage Gold Grade Contained Deposit Mining Method Classification Deposit Classification (Mt) (g/t Au) (koz Au) (Mt) (g/t Au) (koz Au) Open Pit Probable 40.2 1.36 1,751 Indicated 78.4 1.55 3,900 NEB Un