  1. Slide 1: Camden Gas Project CCC Update

    Camden Gas Project CCC Update Community Consultative Committee May 2014

  2. Slide 2: Land & Approvals – Recent Developments

    Land & Approvals – Recent Developments 1 › AGL have reviewed the Mining SEPP. Under the Mining SEPP, the Camden North Expansion project cannot proceed in its current form. » the Camden North Expansion Project remains suspended. › AGL is well aware of NSW’s gas demand, and the gas shortages likely to

  3. Slide 3: Well Summary

    2 Well Summary Production Well Number Exploration Core Number Status (as of 07/05/14) Hole Status (as of 07/05/14) Drilled (total wells) 144 Drilled, Plugged and 6 Abandoned (Camden North) Wells under 0 Drilled, Plugged and 3 construction Abandoned (remainder PEL2) Producing and 96 dewatering wells

  4. Slide 4: Health, Safety and Environment

    3 Health, Safety and Environment › Head of Environment appointed for Upstream Gas. › 2012-13 Annual Returns submitted to the EPA. › Fugitive Methane Emissions Monitoring Program report(s) released. › Updates to the Environmental Management Plan. › 2010-2012 Independent Environmental Audit corrective

  5. Slide 5: Field operations

    4 Field operations › No CSG Drilling since September 2012. › Well workovers undertaken in Menangle Park and Mt Taurus fields. › Next well workovers in Qld. › 3 water monitoring bores drilled at Glenlee/ Menangle Park in January and February to depths of approx 100m, 150m, and 300m › Camden Community

  6. Slide 6: Rosalind Park Gas Plant

    5 Rosalind Park Gas Plant › Noise monitoring » December 2013 and March 2014 quarterly monitoring results compliant » Noise monitoring surrounding Spring Farm (SF20) wells confirmed compliance with project noise criteria. › Air emissions monitoring » December 2013 and March 2014 quarterly monitoring

  7. Slide 7: Community

    Community 6 Open Day/ visits to Camden › CSIRO Project Team for Bioregional Assessment › Community Open Day, October 12 › Community Open Day, March 4 › EPA Board Fugitive Methane Emissions Monitoring Program › Community Consultation Group briefed, February 3 › Government Agency briefing, February 4