Admie Holdings Sa · ATHEX:ADMIE

Admie Holdings Sa — H1 2024 Earnings Presentation

25 slides from Admie Holdings Sa's earnings presentation, Sep 25, 2024

  1. Slide 1: Driving the Energy Transition

    Driving the Energy Transition Financial Results H1 2024 Investor Presentation 25 September 2024 ADMIE Holding 2023 – Financial Results Full Year 2023

  2. Slide 2: Agenda

    Agenda 1. ADMIE Holding - Highlights 2. IPTO S.A. - Highlights 3. IPTO Investment Program progress 4. Appendix 2 ADMIE Holding – Financial Results H1 2024

  3. Slide 3: Disclaimer

    Disclaimer This document contains forward-looking statements that involve risks and uncertainties. These statements may generally, but not always, be identified by the use of words such as “outlook”, “guidance”, “expect”, “plan”, “intend”, “anticipate”, “believe”, “target” and similar expressions to

  4. Slide 4: Highlights ADMIE Holding

    Highlights ADMIE Holding 4 ADMIE Holding 2023 – Financial Results Full Year 2023

  5. Slide 5: ADMIE Holding Overview

    ADMIE Holding Overview FY ‘20 FY ‘21 FY ‘22 FY ‘23 H1 ‘24 Holds 51% of the Hellenic Electricity Transmission System Operator (IPTO) Net Income (m) 44.1 40.1 29.4 59.6 37.1 Dividend 0.12 0.103 0.068 0.058 0.124** Purpose: Market cap: EUR 531.3 million* ADMIE Holding Shareholding To provide operationa

  6. Slide 6: ADMIE Holding Financial Highlights H1 2024

    ADMIE Holding Financial Highlights H1 2024 Amounts in €m INCOME 37.6 27.5% Η1 2023: 29.5 OPEX 0.6 50.0% Η1 2023: 0.4 NET PROFIT 37.1 27.1% Η1 2023: 29.2 CASH 35.1 716.3% Η1 2023: 4.3 NET DEBT 0 Η1 2023: 0 DIVIDEND 0.124e* 114% FY 2023: 0.058 *2024 e 6 ADMIE Holding – Financial Results H1 2024

  7. Slide 7: ADMIE Holding P&L and Balance Sheet summary

    ADMIE Holding P&L and Balance Sheet summary Amounts in €’m Profit & Loss Statement Balance sheet 30.06.2024 31.12.2023 30.06.2024 30.06.2023 Chg % Share of profits in investments accounted Non-current assets 37.6 29.5 27.4% 808.2 800.7 using the equity method Current assets 35.5 5.8 Total Revenue 37

  8. Slide 8: Highlights IPTO S.A.

    Highlights IPTO S.A. 8 ADMIE Holding 2023 – Financial Results Full Year 2023

  9. Slide 9: IPTO at a glance

    IPTO at a glance Sole Transmission System Operator (TSO) in Greece Investment Proposition High dividend returns Natural monopoly in Reduced borrowing costs Employees Transported Energy Greece and established minimum 50% earnings payout 13,671 km of HV transmission lines 2,090 49.5 TWh Rational Leadi

  10. Slide 10: Electricity Demand & Supply for H1 2024

    Electricity Demand & Supply for Η1 2024 Production & Interconnection Mix Key figures Production mix Imports mix 1,4% • Η1’24 Total Market 6,1% 5,2% 9,1% Demand reached 24.6TWh (4.0% y-o-y) 16,5% 33,0% 35,1% • Renewable energy contribution reached 57,4% 57.4% in H1 2024 36,2% • Net imports at 2.9 TWh

  11. Slide 11: IPTO GROUP H1 2024 financials

    IPTO GROUP H1 2024 financials Profit & Loss Statement Total Revenues* reached €225.4m increased by € 36 m, driven by the Transmission System €m 30.06.2024 30.06.2023 Chg % Rent, increased by €35.2m mainly due to an increase in interconnection rights by €20.5m., reaching € Revenue from transmission s

  12. Slide 12: IPTO Group Balance Sheet and Cash flow summary

    IPTO Group Balance Sheet and Cash flow summary Amounts in €’m Cash Flow evolution (€m): Balance sheet 30.06.2024 31.12.2023 Non-current assets 3,827 3,629 Current assets 501.7 441.9 322.4 Of which: Cash & equiv. 322.4 245.7 245.7 Total Assets 4,329 4,070 120.3 64.3 Equity 1,533 1,518 Non-current lia

  13. Slide 13: IPTO Financial Performance ratios

    IPTO Financial Performance ratios Key figures: Net Debt € 843.4 million Η1 2023: € 981.6 Leverage 5.0 Net Debt/adj. EBITDA Η1 2023: 7.1 Coverage ratio 6.8 x Interest coverage ratio* Η1 2023: 7.5 *EBIT/Net Interest expense Leverage 0.55 Net Debt/Equity Η1 2023: 0.57 Leverage ratio 35.5% Η1 2023: 40%

  14. Slide 14: IPTO Capex

    IPTO Capex Euro million 17% Crete phase II (including Ariadne) : €100.1 Other: €42.2 FY22: EUR 335 39% 19% Greece – Cyprus – Israel: €47.5 *Capital investment: EUR 254.4 m 25% Cyclades interconnection (phase D): €64.6 *H1’23: EUR 296.5m. 14 ADMIE Holding – Financial Results H1 2024

  15. Slide 15: Updated Regulatory Framework

    Updated Regulatory Framework RAEWW’s Decision E-102/2023 on Regulatory Period 2023-25 WACC (pre-tax nominal) 2022 2023 2024 2025 6.10% 7.57% 7.51% 7.45% Special RAB (for PMI - by 2025) RAB Allowed Revenue (by 2025) (in 2025) € 711.8 million € 2,682.7 million € 484.8 million with 1% WACC premium 15 A

  16. Slide 16: IPTO Investment Program progress

    IPTO Investment Program progress 16 ADMIE Holding 2023 – Financial Results Full Year 2023

  17. Slide 17: Major Projects 2024-2031

    Major Projects 2024-2031 Cyclades Phase D 2024-2025 2026 2028-2029 2028-2030 2031 North Aegean Greece-Italy Crete Peloponnese Dodecanese Phase II Corridor B’ Phase I-II Interconnection Interconnection Phase I-III 17 ADMIE Holding – Financial Results H1 2024

  18. Slide 18: Major Projects 2024-2035

    Major Projects 2024-2035 Major Project Locations Total Capex Greece-Italy Interconnection 4 5 €6.1bn Expected Commissioning: 2031 Total project cost: €507m North Aegean Interconnection Expected Commissioning : 2030 Total project cost: €1.2bn Second 400 kV branch to Peloponnese (Megalopoli - Korintho

  19. Slide 19: Key project developments 2024

    Key project developments 2024 Ariadne Interconnection Dodecanese and Northeast Aegean Ariadne Interconnection Interconnection of Cyclades The completion of Cyclades will enable the islands interconnections The project will be fully operational In August 2024, the conclusion of the first phase of the

  20. Slide 20: Key project developments 2024

    Key project developments 2024 Eastern Peloponnese Corridor Great Sea Interconnection Upgrading of the Koumoundourou The construction of the new transmission line of the project Greece-Cyprus-Israel The project will be fully operational by the end of the H1 2025 is underway 6th list of Projects of Co

  21. Slide 21: International Interconnection Plans

    International Interconnection Plans 2nd interconnection with Italy Interconnection with Egypt 2nd interconnection with Albania Commissioning: 2031 Commissioning : 2030 Cooperation with EETC and ELICA SA to • Greece -Albania interconnection, together Interconnection between Greece and evaluate partic

  22. Slide 22: Appendices

    Appendices 22 ADMIE Holding 2023 – Financial Results Full Year 2023

  23. Slide 23: IPTO H1 2024 Adjusted EBIT evolution

    Appendix 1 IPTO H1 2024 Adjusted EBIT evolution Key figures Adjusted EBIT (€m) 27.2% Adjusted EBIT Includes provisions for staff compensation and 36.1 0.2 risks and expenses amounted to €2.2m from €0.8m in H1 2023. -4.2 -2.0 105.6 -7.1 -0.4 Revenue Increase of revenues €36.1m driven by the 83.0 incr

  24. Slide 24: WACC calculation

    Appendix 2 WACC calculation On 20.07.2023 the Energy Sector of WACC components 2023 RAEWW released its decision regarding the approval of the revised return Risk-free 2.36% (WACC) on the Regulated Asset Base of the Affiliate IPTO S.A. The return for the Market risk 5.5% years 2023-2025 of the Regula

  25. Slide 25: Contact

    Contact For additional information please contact ADMIE Holding Investor Relations: Lilian Filips Head of IR Tel: +30 210 3636 936 E-mail: l.filips@admieholding.gr ADMIE Holding 2023 – Financial Results Full Year 2023 25