Northam Platinum Holdings Limited · JSE:NPH

Northam Platinum — Nedbank Securities 2009 Investment Conference

14 slides from Northam Platinum's conference presentation, Oct 8, 2009

  1. Slide 1: Introducing the new Northam

    Introducing the new Northam • Producing and marketing PGMs since 1993 2 • fully independent, integrated producer • track record of reliable, consistent production • Cash generative and profitable • Listing on the JSE since 1987 • admitted to SRI Index in 2006 • Acquisition of Booysendal in 2008 • pr

  2. Slide 2: Improving the tradability; Transformed group structure

    Improving the tradability 3 Current shareholding structure Future shareholding structure Mvela Afripalm Mvela Afripalm Free float Holdings Resources Holdings Resources 19.6% 31.0% 13.8% 12.7% 73.5% Mvela Resources 63.4% Transformed group structure 4 100% 100% 100% 7.5% Northam metallurgical Booysend

  3. Slide 3: The platinum landscape; Zondereinde mine: quick overview

    The platinum landscape 5 Polokwane PP Rust WF Mokopane Lebowa North Dwaalkop Limpopo Twickenham CRF Marula Thabazimbi Modikwa Amandelbult Zondereinde Union Bela Bela Two Rivers Pilanesberg Mototolo Groblersdal Der Brochen Sedibelo Everest Booysendal BRPM Pandora Brits Zeerust Impala SF Rustenburg RP

  4. Slide 4: Tradition of rewarding shareholders

    Tradition of rewarding shareholders 7 ZAR cps Cash distributions to shareholders 600 500 400 300 200 100 0 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Solid track record – through thick and thin 8 4

  5. Slide 5: World class metallurgical infrastructure and expertise

    World class metallurgical infrastructure and expertise 9 • World class smelter and base metal removal plant on Zondereinde mine site • Tradition of innovation, improving recoveries • sparger column cell used as final cleaner circuit • Leveraging capacity • offtake agreement concluded with Pilanesber

  6. Slide 6: Northam F09: key features for the year

    Northam F09: key features for the year 11 • 21.7% increase in sales volumes to 10 362 kg (333 159 oz) • Increase in unit cash costs held to 14% • R db Rand basket k t price i 3131.4% 4% llower y-o-y R280 609/kg 609/k • Operating margin of 25.7% • Headline earnings of 168.6 cents per share • Cash on

  7. Slide 7: To recap – locality; Booysendal – shallow, near-term expansion

    To recap – locality 13 1A 1B 14.5km 1D 1C Booysendal – shallow, near-term expansion • 103Moz resource – unlocking value over time 14 • Flexibility in bringing production to market UG2 classification Merensky classification 7

  8. Slide 8: Booysendal: near-term shallow ounces; Key statistics

    Booysendal: near-term shallow ounces 15 Attributable Moz (3PGM+Au) 900 600 300 0 Anglo Implats Bokoni Lonmin Northam* Anooraq Eastern Aquarius* Kameni Elands Jubilee Nkwe Plats Holdco *Northam includes Booysendal *Aquarius includes Ridge Mining Key statistics • Tonnages: 16 • Module 1 - 120 000 tonn

  9. Slide 9: Capex spread and production build-up; Utilities

    Capex spread and production build-up 17 160 1400 140 1200 120 1000 100 R million 800 ktpm 80 600 60 400 40 20 200 0 0 2010 2011 2012 2013 2014 2015 Production build-up (ktpm) Initial capex (Rm) 17 Utilities 18 • Electricity • spare capacity it att M Mototolo t t l (16MV (16MVa)) available il bl to t

  10. Slide 10: Road and pipeline route

    Road and pipeline route Graphic material NORTH 2KM MR North Decline UG2 North Decline 8KM MR South Decline UG2 South Decline UG2 Outcrop MR Outcrop 10

  11. Slide 11: Mine access trade-off summary

    Mine access trade-off summary 21 Environmental Boxcut Access option Days to complete impact excavation (ha) (cubic m) Base case 539 21.9 40 000 Reverse decline option 1 399 20.5 39 500 Reverse decline option 2 410 18.6 50 000 Reverse decline option 2a 408 18.6 40 000 Vertical shaft (three options co

  12. Slide 12: Final design: reverse decline option 2a

    Final design: reverse decline option 2a 23 Decline section 24 • Click to edit Master text styles • Second level • Thi d llevell Third • Fourth level • Fifth level Ramp (9˚) 6.5m Conv. / Chair- Lift Decline 3.5m 12

  13. Slide 13: Booysendal – unlocking value over time

    Booysendal – unlocking value over time 26 Estimated production ramp up Tonnages Production ounces 4,000 350,000 3,500 300,000 PGE (4E) Ounces 3,000 250,000 Ktpa RoM 2,500 200,000 2,000 150,000 1,500 1,000 100,000 500 50,000 ‐ 0 Module 1 Module 2 Module 1 Module 2 13

  14. Slide 14: Northam – a compelling investment case

    Northam – a compelling investment case 27 27 • Moving from lease-bound operation with limited expansion opportunity to large, shallow resource with potential to double production • Track record of consistent delivery to shareholders • Multi-million ounce resource – potential for further value The on

Northam Platinum Holdings — Nedbank Securities 2009 Investment Conference on 6ix