  1. Slide 1: Delivering a Network for Net Zero

    Delivering a Network for Net Zero Investor Relations Event 7 September 2022

  2. Slide 2: Disclaimer

    01 Delivering a Network for Net Zero Disclaimer This presentation has been prepared by SSE plc solely for use on 7 September SSE plc gives no express or implied warranty, representation, assurance or 2022 during the SSEN Transmission Management presentation section of undertaking as to the impartial

  3. Slide 3: Agenda

    Delivering a Network for Net Zero 02 Agenda Day 1: Agenda – SSEN Transmission Management Presentations​ Blackhillock HVDC Substation Site Visit​ Morning 09:00-13:00​ Afternoon 13:00 – 18:00​ Moray Firth Scale of Opportunity Rob McDonald​ Travel to Blackhillock and site tour System Planning 1 hr 30 m

  4. Slide 4: Transmission Growth

    Rob McDonald Managing Director Transmission Growth​

  5. Slide 5: Safety in SSEN Transmission

    Delivering a Network for Net Zero 04 Safety in SSEN Transmission​ Looking after ourselves and each other​ Safety Measure 2016/17 2021/22 Change HSE Reportable Incidents 10 4 ↓ 60% Lost Time Incidents 3 0 ↓ 100% Medical Treatment Incidents 7 5 ↓ 29% TRIR (Total Recordable Injury Rate per 100k hrs wor

  6. Slide 6: Introducing Our Experienced Management Team

    05 Delivering a Network for Net Zero Introducing Our Experienced Management Team​ Industry Experts with Proven Track Record Management team Rob McDonald​ Wick Managing Director of SSEN Transmission​ Blackhillock Training School 25 INVERNESS Hub and depot Elgin Operations – Project Planning & Deliver

  7. Slide 7: SSEN Transmission

    Delivering a Network for Net Zero 06 SSEN Transmission Uniquely positioned to play a central role in Net Zero​ ✓ One of the fastest growing regulated electricity networks in Europe​ ✓ Underpinned by one of the most established and well-respected regulatory frameworks in Europe ✓ Experienced manageme

  8. Slide 8: North of Scotland is a key enabler of GB's energy transition

    07 Delivering a Network for Net Zero North of Scotland is a key enabler of GB’s energy transition SSEN Transmission set to deliver 10% of GB total emissions abatement required for net zero​ FES 2022 Total Generation including <10MW: SSEN Transmission (SHET) Area Only 60 50 40 GW 30 20 10 0 2021 2022

  9. Slide 9: Delivering a Network for Net Zero

    Delivering a Network for Net Zero 08

  10. Slide 10: SSEN Transmission

    09 Delivering a Network for Net Zero SSEN Transmission Critical to delivery of UK’s decarbonisation targets​ ✓ Double Digit RAV growth rate ✓ Line of sight on specific projects​ ✓ Working with Ofgem to approve these projects by the end of the year ✓ Proven track record and ambitious plans to deliver

  11. Slide 11: System Planning

    Bless Kuri Head of System Planning and Investment​ System Planning​

  12. Slide 12: System Planning and Investment

    11 Delivering a Network for Net Zero System Planning and Investment Key to Understanding SSEN Transmission Growth Drivers Highly technical team of Power System engineers (30 strong) Specialist power system analysis​ Unprecedented rapid expansion of the transmission network​ System complexity is incr

  13. Slide 13: SSEN Transmission – Growth Drivers

    Delivering a Network for Net Zero 12 SSEN Transmission – Growth Drivers​ SSEN Transmission Area (GW) Export network capacity ESO forecasts ESO forecasts 60 30 Generation Capacity * 47.8 50 30 25 Peak Demand 25 40 20 20 29.0 30 15 15 20 10 10 Cu10.7 rren t 3.2 GW C urren t 3.2 GW 10 5 4.4 5 1.4 2.1 0

  14. Slide 14: North of Scotland: Renewable Generation Growth

    13 Delivering a Network for Net Zero North of Scotland: Renewable Generation Growth Future Energy Scenarios (FES) There is currently 8.1GW of renewable generation capacity connected FES 2022 Total Generation including <10MW to our network. SSEN Transmission (SHET) Area Only This is expected to grow

  15. Slide 15: Delivering a Network for Net Zero

    Delivering a Network for Net Zero 14

  16. Slide 16: Questions

    Questions ” “late:

  17. Slide 17: Regulatory & Financial Outlook

    Michael Ferguson Director of Regulation Maz Alkirwi Director of Finance Regulatory ​& Financial Outlook​

  18. Slide 18: Government support to meet climate change targets

    17 Delivering a Network for Net Zero Government support to meet climate change targets​ Strong political support for both increased investment in energy security and lowering energy bills SSEN Transmission 2030 grid investment meets the challenge​ ​ • Connection of growing volume of GB low carbon ge

  19. Slide 19: Regulatory Outlook

    Delivering a Network for Net Zero 18 Regulatory Outlook Pathway to 2030 & Ofgem Consultation SSEN Transmission HND1 Projects RIIO-T2 MECHANISMS License change process Need Competition Funding • Provide early • Confirm TO • Funding to certainty delivery de-risk delivery NEW ACCELERATED FRAMEWORK FOR

  20. Slide 20: Looking ahead to RIIO-T3

    19 Delivering a Network for Net Zero Looking ahead to RIIO-T3 Securing regulatory regime which supports acceleration of net zero delivery Draft timeline January 2022 January 2023 January 2024 January 2025 January 2026 Open Framework Business Final letter consultation Plan Determination Sector Draft

  21. Slide 21: Delivering on the Net Zero Acceleration Programme

    Delivering a Network for Net Zero 20 Delivering on the Net Zero Acceleration Programme The optimal pathway to maximise shareholder value and growth into the 2030s FULLY-FUNDED ENHANCED …DELIVERING ACCELERATED GROWTH …AND THE PLATFORM FOR INVESTMENT PLAN… AT ATTRACTIVE RETURNS INTO 2026… GROWTH TO 20

  22. Slide 22: RIIO-T2 Our Business Plan Financial Highlights

    21 Delivering a Network for Net Zero RIIO-T2 Our Business Plan Financial Highlights Significant capital investment required by SSEN Transmission to deliver on UK Net Zero ambition Frontier Transmission Operator: Our RIIO-T2 Business Plan Forecast Totex Allowances reflected highest RAV growth in sect

  23. Slide 23: RIIO-T2 Our Targeted Returns

    Delivering a Network for Net Zero 22 RIIO-T2 Our Targeted Returns Our return on equity outlook to 2026 • Nominal Return on Equity (RoE) target of 7-9%* Targeted return on equity 7-9% set in NZAP • Achieved RoE reflects increasing regulatory focus on operational performance through: 5-7% - Business P

  24. Slide 24: RIIO-T2 Our Revenue Outlook

    23 Delivering a Network for Net Zero RIIO-T2 Our Revenue Outlook Our T2 forecast allowed revenue • Revenue expected to peak in FY25*, driven by timing from regulatory framework: - FY22 & FY23 include legacy impact from T1 revenue allowances - T2 allowed revenue allowance growth accelerates through F

  25. Slide 25: A clearer path for growth to 2026

    Delivering a Network for Net Zero 24 A clearer path for growth to 2026 Highly supportive backdrop is driving mid-to-long term growth SSEN Transmission forecast RAV growth to 2026 FY26 RAV expected to reach £6.5-7bn 8 • Based on Ofgem inflation forecast Regulated Asset Value (£bn) 7 • Increasing clar

  26. Slide 26: A clearer path for growth to 2031

    25 Delivering a Network for Net Zero A clearer path for growth to 2031 North of Scotland generator growth to FY31 requires acceleration of reinforcements and connections SSEN Transmission forecast RAV Growth to 2031 FY31 RAV expected to exceed £12bn 14 • Supported by HND and Regulated Asset Value (£

  27. Slide 27: Questions

    Questions

  28. Slide 28: Proven delivery track record & plan to step up to 2030 challenge

    Rob McDonald Managing Director Dave McKay Director of Asset Management & Operations Proven delivery track record & plan to step up to 2030 challenge

  29. Slide 29: Pathway to 2030: Our Plan for Delivery

    Delivering a Network for Net Zero 28 Pathway to 2030: Our Plan for Delivery Preparing to step up to the challenge ✓ Operations and Asset Management ✓ Project Delivery ✓ Stakeholder Engagement ✓ Supporting Infrastructure

  30. Slide 30: Delivering Exceptional Asset Management

    29 Delivering a Network for Net Zero Delivering Exceptional Asset Management Essential to business performance Strong performance in international benchmarking • Operational benchmarking: on track to be upper-quartile company across key operational metrics in ITOMS • Asset Management benchmarking: c

  31. Slide 31: Operational Excellence

    Delivering a Network for Net Zero 30 Operational Excellence Strong asset management results in efficient and effective network outcomes Reliable Operations • Sector leading network availability • HVDC >99% availability since first energisation in 2018 • Lowest number of unplanned network outages due

  32. Slide 32: From Excellent to World Class

    31 Delivering a Network for Net Zero From Excellent to World Class Improving and innovating to become world class Innovation and working differently – an investment in the future • HVDC Multi Terminal connection and Circuit Breaker • World’s first 400kV SF6 alternative at Kintore • Composite poles a

  33. Slide 33: Proven Track Record

    Delivering a Network for Net Zero 32 Proven Track Record Multiple complex projects Caithness - Moray Tealing Blackhillock

  34. Slide 34: Delivering a Network for Net Zero

    33 Delivering a Network for Net Zero

  35. Slide 35: Sustainable Supply Chain

    Delivering a Network for Net Zero 34 Sustainable Supply Chain Working collaboratively with our procurement partners HVDC Transformer Delivery to Shetland

  36. Slide 36: Offshore Delivery

    Sandy MacTaggart Director of Offshore Delivery Offshore Delivery

  37. Slide 37: Build for a Billion

    Tony Scott Director of Capital Development & Delivery Build for a Billion

  38. Slide 38: Sector leading environmental and sustainability strategy

    37 Delivering a Network for Net Zero Sector leading environmental and sustainability strategy First energy network to be recognised for science-based targets Awarded ‘leadership status’ by Ofgem for excellence in environmental sustainability Sustainability Report 2021/22 Only TO to be awarded RIIO-T

  39. Slide 39: Sector Leading Stakeholder Engagement

    Delivering a Network for Net Zero 38 Sector Leading Stakeholder Engagement Delivering best practice Awarded top category ‘advanced’ score in Accountability AA1000 82% international benchmark 21/22 with a score of 82% 20% uplift on our 19/20 score of 62% Achieved advanced rating four years faster tha

  40. Slide 40: Continuously Improving

    39 Delivering a Network for Net Zero Continuously Improving Delivering on stakeholder feedback New website goes live Autumn 2022 Established and growing community engagement Three chicks hatched this year from Alyth substation’s resident ospreys Visit our website: www.ssen-transmission.co.uk Follow

  41. Slide 41: Investing in our Supporting Infrastructure

    Delivering a Network for Net Zero 40 Investing in our Supporting Infrastructure Preparing our technology and people to deliver at scale RIIO-T2 IT and OT* spend including cyber resilience investment c.£100m People and culture Mar 2023 c. 1,300 people Sept 2022 1,030 people Opened our new office Aug

  42. Slide 42: SSEN Transmission

    41 Delivering a Network for Net Zero SSEN Transmission Critical to delivery of UK’s decarbonisation targets​ ✓ Double Digit RAV growth rate ✓ Line of sight on specific projects​ ✓ Working with Ofgem to approve these projects by the end of the year ✓ Proven track record and ambitious plans to deliver

  43. Slide 43: Questions

    ia) N N \\ A BO ~ ry Questions BMC SL I ey

  44. Slide 44: Blackhillock Substation & HVDC Convertor Station Visit

    43 Delivering a Network for Net Zero Blackhillock Substation & HVDC Convertor Station Visit Safety Briefing Our five safety golden rules If it’s not Safe, we don’t do it… ✓ Assess risks ✓ Wear P.P.E. ✓ Accept challenges ✓ Reverse park ✓ Everyone holds the handrail

  45. Slide 45: Blackhillock Substation

    Delivering a Network for Net Zero 44 Blackhillock Substation

  46. Slide 46: Blackhillock substation: c.183,000m2 = 25 football pitches

    45 Delivering a Network for Net Zero Blackhillock substation: c.183,000m2 = 25 football pitches Safety briefing • This is a live operational site with high voltages present – • You may hear loud banging noises if plant operates – please do not interfere with any plant and follow there is no need to

  47. Slide 47: Substation Login

    Delivering a Network for Net Zero 46 Substation Login For safety and security reasons, all staff / visitors attending any SSEN Transmission substation must be recorded in and out This is done through the Atlas SOS app Your SSEN Transmission host will do this on your behalf before and after entry

  48. Slide 48: Slide 48

SSE — Investor Presentation (September 2022) on 6ix